My company wants to build a staff dormitory. What procedures do I need to go through and which departments should I go to?

Examination and approval procedures for enterprises to build their own houses:

First, for land acquisition procedures (that is, for construction land permits) to provide:

1. Project approval;

2. General plan (design institute);

3. The EIA reply;

4. Planning red line control chart (marked by planning office on both sides of the road).

Two, before the start of the relevant procedures (i.e., for the construction project planning permit) to provide:

1. General plan and renderings (subject to the approval of the town);

2. Geological exploration report;

- 1-

3. Design of individual buildings;

4, fire audit opinions, land approval;

5. New wall materials must be used;

6, urban construction center pay-off inspection qualified rear can start;

7. Pay the infrastructure supporting fee of 5 yuan/m2.

Four, after the start of the processing:

1. Land use certificate;

2. Construction project quality supervision and construction permit;

3. Project completion acceptance certificate;

4. Real estate license.