Job Recruitment Website - Ranking of immigration countries - Large reservoirs have been investigated in China. When will land acquisition and demolition be carried out?

Large reservoirs have been investigated in China. When will land acquisition and demolition be carried out?

Land can be requisitioned after half a year. After the reservoir project is approved, the land can be requisitioned after half a year. The construction procedure of a reservoir is roughly such a process: firstly, the construction planning report is compiled and approved; Then the feasibility study report is prepared and approved. Only after the feasibility study report is approved can the reservoir project be considered established. After the project is approved, a preliminary design report will be prepared, and the construction can be officially started only after the preliminary design report is approved.