Job Recruitment Website - Ranking of immigration countries - Environmental Impact of Wendeng Pumped Storage Power Station in Shandong Province

Environmental Impact of Wendeng Pumped Storage Power Station in Shandong Province

(1) installed capacity of the power station 1800MW, annual power generation of 2.628 billion kW·h and annual pumping power of 3.504 billion kW·h. After completion, it can improve the single and unreasonable power supply structure of Shandong power grid, meet the requirements of peak shaving, improve the operation of thermal power units and improve the economic operation efficiency of the power grid.

(2) After the power station is put into operation, compared with the pure thermal power peaking scheme, Shandong Power Grid can save 0/74,800 tons of standard coal every year, which is equivalent to 244,700 tons of raw coal, and correspondingly reduce the emission of carbon dioxide (CO2) and sulfur dioxide (SO2) by 420,000 tons every year, thus reducing the degree of air pollution. The environmental benefits are remarkable.

(3) During the construction period, local labor resources can be greatly utilized, personal income can be increased, consumption level can be improved, and local economic development can be promoted. Local taxes can also be increased during the construction and operation of power stations, which has a positive role in promoting economic development.

(4) Building permanent roads can improve local traffic conditions; After the completion of the power station, the upper and lower reservoirs and underground workshops can be developed into industrial tourist attractions, which can be jointly developed with other scenic spots around the power station and Shengjing Mountain scenic spots to promote the development of local tourism. (1) During the construction of the project, wastewater and waste gas will have different impacts on the surrounding environment. However, the treatment and reuse of production wastewater and domestic sewage during construction period has little effect on surface water quality and water use; The dust around the construction site and some construction roads has a certain impact on the atmospheric environment; The increase of noise sources has a certain adverse impact on the production and life of surrounding residents; Construction waste residue and domestic garbage will be treated in a standardized way, which will basically have no adverse impact on the surrounding environment.

(2) The construction and operation of the project will partially change the groundwater environment in the project area and have a certain impact on some groundwater environments in the project area.

(3) Although the project construction has a certain impact on local vegetation, it has little impact on the overall ecological environment. The project construction will not change the local vegetation types, will not cause the disappearance of plant species, and will not have long-term adverse effects on the local ecosystem.

(4) The project is affected by reservoir inundation and occupation of construction land. According to the preliminary investigation, 240 people need to be relocated, and the production resettlement population is 147 people. Judging from the number and mode of resettlement, resettlement has little impact on social environment and ecological environment.