Job Recruitment Website - Ranking of immigration countries - Discuss the conditions that should be met for engineering project procurement.

Discuss the conditions that should be met for engineering project procurement.

Answer: Generally speaking, the conditions that engineering project procurement should meet include the following aspects:

(1) The engineering construction project or plan has been approved

The engineering construction project has been approved by the competent authorities and included in the annual investment plan. Approval of construction projects is an important part and link of capital construction procedures. According to regulations, construction projects that are not included in national plans or regional plans cannot be organized. Even foreign-invested and financed construction projects must have project approval procedures. Therefore, construction projects that are not included in the plan cannot be subject to construction bidding.

(2) The design documents have been approved

The design documents of the engineering project include: preliminary design and cost estimate, or technical design and revised estimate, or construction drawing design and budget, by project Depends on the size and level. The practice of many projects shows that as long as time permits, construction drawings and cost estimates should be used as much as possible when bidding, which is most conducive to the project owner's preparation of bidding documents and preparation of base bids. After the contract is awarded and signed, construction can start when other relevant conditions are met, and there are few changes during project construction. However, in actual work, once a construction project is approved, there is often a rush to start work for various reasons. Therefore, the relevant measures for bidding stipulate that "the preliminary design and budget estimate documents have been approved" is one of the necessary conditions for the implementation of construction bidding, which is also the minimum condition for preparing bidding documents.

(3) Construction funds have been secured

Construction funds, for World Bank projects, firstly means that the World Bank loan has been committed, the project evaluation has been completed, and a loan agreement will be signed. ; The second refers to the fact that domestic supporting funds have been implemented or basically implemented, and both are indispensable. For domestic projects, construction funds include own funds and bank loans. Usually, self-owned funds are not less than 30% of the total project investment, and bank loans must also be secured. If the funds are not secured, bidding cannot be carried out and pre-qualification cannot be carried out.

(4) The bidding documents have been prepared and approved

The importance and main content of the bidding documents are prerequisites for project construction bidding and should be approved by relevant departments.

(5) Construction preparations are ready

Construction preparations, including land acquisition and demolition, resettlement, environmental protection measures, temporary roads, public facilities, communication equipment and other site conditions have been prepared Ready, local construction permits have been obtained.