Job Recruitment Website - Ranking of immigration countries - The construction permit was completed and accepted twice. How to write the safety instructions?
The construction permit was completed and accepted twice. How to write the safety instructions?
(1) Overview
Project name, project location, construction basis, construction scale, standards and main contents, contractors, construction process of major projects and important temporary facilities, etc.
(2) Project construction management
1, organization and work of the project unit. Sample acceptance report. The project management system of the project unit, the establishment and work of the superior departments, quality supervision institutions and local government organizations that serve the project construction.
2. Bidding management: the bidding situation of survey, design, supervision, construction, materials and equipment, the qualification of the winning bidder, the main tasks undertaken, etc.
3. Design change management: handling of major technical problems in implementation and related information of design change.
4. Safety and quality management: safety and quality management system, safety and quality control measures, accident treatment results, civilized construction, etc.
5. Investment management: investment sources, investment control measures, approved budget and actual implementation, annual plan release and completion, and budget adjustment.
6. Schedule management: planned control objectives and actual implementation of major project nodes, schedule control measures, etc.
7. Contract management: the performance of the contractor, the settlement method of the contract price and the handling of special problems, and whether there is any default in the project payment by the time of completion.
8. Compensation for land acquisition and demolition in construction: whether the land acquisition and demolition can meet the requirements of construction progress, whether there is any violation of policies, the approval and actual land acquisition, the handling of relevant land acquisition procedures, and the use of resettlement fees for land acquisition and demolition, etc.
9. Innovation achievements: technological innovation (new structure, new materials, new technology, new equipment, etc. ) and management innovation achieved in the process of project construction.
10, Clean Government Construction: Clean Government Measures and Clean Government Contract Execution, etc.
- Previous article:Ask for some classic romance novels, such as Phoenix Prison, Phoenix, Phoenix Prison, Phoenix Prison, Phoenix Prison, Phoenix Prison, Phoenix Prison, Phoenix Prison, Phoenix Prison, Phoenix Prison, Ph
- Next article:Common sense of primary school allocation needed to immigrate to Hong Kong
- Related articles
- How to return to China after Malaysia visa expires?
- How do Vietnamese get China hukou?
- How much does it cost to study in New Zealand?
- Which countries cannot import syphilis?
- The word "cloud" is used in ancient poetry.
- In which province is Mingtang Village located?
- Want to immigrate to Canada, what to study in Canada?
- How many people immigrated to Chenxi Pumped Storage Power Station?
- Jiang Xinzheng immigrants
- Please tell me who is a national worker. Thank you.