Construction of Zhengzhou Metro Line 3

Xinhuanet Henan Channel, February 20th, Dahe. Com report: Recently, the resettlement action plan of the first phase project of Zhengzhou Rail Transit Line 3 loaned by the World Bank was publicized on the website of Zhengzhou Development and Reform Commission. According to the public notice, the north and south ends of Zhengzhou Metro Line 3 were fine-tuned, and the high-tech zone was no longer taken, and the economic development section in the south was also extended by 3 kilometers. At the same time, Zhengzhou Metro borrowed from the World Bank for the first time to carry out engineering construction and resettlement.

Yesterday, Henan Business Daily reporter learned from Zhengzhou Rail Transit Co., Ltd. that this is the first time that Zhengzhou Rail Transit has borrowed from the World Bank. The loan is mainly used for the construction of Zhengzhou Metro Line 3, and resettlement is only a part of it.

Why did Line 3 turn to World Bank loan? Yesterday, the relevant person in charge of Zhengzhou Rail Transit Co., Ltd. said: "Compared with domestic commercial banks, the World Bank has low interest rate, long repayment period and relatively low capital cost."

In this publicity, Zhengzhou Metro Line 3 was fine-tuned again. According to the relevant person in charge of Zhengzhou Rail Transit Co., Ltd., Line 3 will no longer take the high-tech zone, because according to the new plan, other subway lines will take the high-tech zone, and Line 3 will be adjusted to go to the provincial sports center along nanyang road and Changxing Road.

In addition, considering that Line 3 will be connected with the future subway network, the opening section of the line has also been partially adjusted and extended by about 3 kilometers, but the station has not changed.

Like the 1 line, Line 3 was built by stages. The first phase of the project includes the section from Liu Xin Road to Hanghai East Road Station, with a total length of 25.2 kilometers. Total length of the second phase project15.8km. ..