How long will it take for the reservoir to start construction?
Generally speaking, the basic construction procedures for new reservoir projects within one and a half years mainly include the following aspects:
1. Project proposal stage (medium and above reservoirs only): Prepare the project proposal and complete the land survey and demarcation report at the same time.
2. Feasibility study report: At the same time, water resources demonstration report, soil and water conservation plan report, land pre-examination document, special report on land requisition and resettlement, environmental impact assessment report and forest land use report have been compiled;
Three. Preliminary design report stage: all special reports in the feasibility study stage must be approved before the preliminary design report review. After the preliminary design is approved, the project can start construction.
- Previous article:What is ivory soap?
- Next article:Life record of new immigrants in mainland Canada
- Related articles
- Where is Zherong County in Ningde? What towns are there around Zherong County, Ningde City? Thank you.
- Liu Xiaoyu's ancestral home
- How about Anhui Huaishang Commercial Management Group Co., Ltd.?
- Montreal investment immigrants
- Canadian immigrants have the benefits that children can enjoy.
- Where is Ligang in Jiangyin?
- I want to learn English and join an English group
- How to choose a major when going to Australia for a master's degree?
- Cultural traces around me
- Historical dictation of Diaoyu Island