1. Investment process of land purchase and factory construction

Sign an investment intention or a letter of intent for joint venture cooperation.

Industrial and commercial registration (industrial and commercial administration): application form for pre-approval of enterprise name, specific company name, names of shareholders, total capital contribution, proportion of capital contribution (if the shareholder is a legal person, a copy of business license is required), capital verification certificate, environmental protection certificate and property certificate.

Project filing (Planning Bureau, Development and Reform Commission): prepare the project introduction, fill in the project application filing form, the application for project filing, the original and duplicate copies of the business license of the enterprise as a legal person, and the copy of the organization code certificate.

Relevant procedures (Environmental Protection Bureau, Construction Bureau, Land Bureau): environmental protection approval, site selection opinion, construction land planning permit, geological disaster assessment report, land assessment, construction land survey and demarcation report, and pre-examination of construction land.

Handling land certificate (Land and Resources Bureau): cadastral questionnaire, land application form and copy of legal person's ID card, company's articles of association and business license, drawing opinions of the planning unit of Land and Resources Bureau, one certificate and one book from the construction department, environmental protection certificate, one book and four drawings, and land evaluation.

Construction procedures before construction (construction bureau): review and approval of construction drawings, approval of single construction projects,

Construction project planning permit, bidding

Handling construction permit (construction bureau): construction land permit, construction application form and number, construction project planning permit, bid-winning notice, accident insurance policy, drawing review and approval, etc.

Post-construction acceptance (Audit Bureau, Construction Bureau, Fire Brigade, Meteorological Bureau, Environmental Protection Bureau): environmental protection acceptance, audit acceptance, planning acceptance, lightning protection acceptance, fire protection acceptance and project acceptance.

Handling the property right certificate (Housing Authority): two copies of the business license or the identity certificate of the registrant, the state-owned land use certificate, the construction project planning permit, the completion acceptance record certificate, and the report on the surveying and mapping results of the housing construction area.

2. The investment process of the leased factory

Sign the agreement for entering the zone (management committee): letter of intent for the project, bank credit certificate, land and factory lease agreement.

Industrial and commercial registration (industrial and commercial administration): application form for pre-approval of enterprise name, specific name of company, names of shareholders, total amount of capital contribution, proportion of capital contribution (legal person shall carry a copy of business license), capital verification certificate, environmental protection certificate and property certificate.

Environmental protection approval (environmental protection bureau): fill in the application form for environmental protection filing and the opinions of the municipal and county environmental protection bureaus.

Signing the lease contract (Management Committee): The contract is in quadruplicate with a geographical map.

Apply for the project proposal, establish the project, and receive the project proposal (Foreign Economic Commission, Fire Bureau, Labor Bureau, Health and Epidemic Prevention Station, Planning and Land Bureau, Environmental Protection Bureau): project letter of intent, project proposal, business commencement certificates of both parties, identity certificate of foreign legal representative, bank credit certificate, geographical location map, land workshop lease agreement.

Enterprise name registration (State Administration for Industry and Commerce): enterprise name application registration form, enterprise name registration application, project letter of intent, project proposal and project proposal reply.