Job Recruitment Website - Job seeking and recruitment - Minutes of engineering construction meeting
Minutes of engineering construction meeting
In the engineering department, it is necessary to write meeting minutes when conducting construction content meetings, so how should I write meeting minutes? The following is the template of project construction meeting minutes I shared with you, hoping to help you.
Template of minutes of engineering construction meeting: time: 20xx year x month x day.
Venue: On-site Meeting Room of Jiangning Wanda Project
Participating units and personnel: See signing in for details.
At 2:30 pm on March 16, the construction unit Manager Chen organized the first regular meeting of wanda plaza Project in Jiangning, Nanjing, and the construction unit, construction unit and supervision unit attended the meeting. At the meeting, Manager Chen introduced the responsible persons of all parties. The parties introduced the personnel and division of labor of their respective on-site organizations, and authorized China Consulting Construction Supervision Jiangning Wanda Project Department and Director. On behalf of the owner, the project supervision department controls the progress, quality, investment and safety of the whole project, manages contracts and information, and coordinates the relationship between the parties.
The construction unit introduced the project preparation, the main civil engineering of the sales office has been completed, two decoration units have entered the site, and the earthwork in the east and west areas has been transported abroad. The construction data is not completed, which needs the supervision to cooperate with all construction units to complete.
The main contractor introduced the construction preparation and site construction, as well as the problems that need to be solved by the construction unit. The construction unit puts forward opinions and requirements on the construction situation, and the chief supervision engineer introduces the main contents of the supervision plan and submits it to the construction unit for review. The meeting agreed to hold a regular project meeting every Friday, and determined the project manager and technical director to be in charge of safety and quality? A href = '/ Yang Sheng/kesou/'target =' _ blank' > Cough for Wei Yong < What's the matter? Isn't new thinking good? /p & gt;
Zhongzi engineering construction company Nanjing Jiangning wanda plaza project supervision department
First of all, thank the owner for his support and trust in our supervision work. As a supervisor, we will work diligently, be loyal to our duties, serve the owner wholeheartedly, and do all the work of the project well. Take the initiative to coordinate with the project parties, and use scientific management means and advanced technical means to ensure good customs and services for the owners. At the same time, we also hope that all contractors will work hard and carry out construction in strict accordance with design drawings, construction specifications and relevant technical standards. We will speak according to the contract, adhere to the standards, and handle the problems in the project fairly. Do a good job of four controls, two tubes and one coordination. The combination of pre-control, in-process control and post-control keeps the project under control all the time. The specific requirements for the construction management of this project are as follows:
A, the construction preparation stage:
1, the construction unit shall submit the relevant technical documents to our supervision department for review before the project starts, for example, the technical qualification documents, quality assurance system documents, construction organization design, special construction scheme and technical measures of the construction unit. The construction organization design/scheme is submitted for approval (declare in advance construction scheme is required for important divisions/projects), and the procedures for submitting for approval are standardized, with compilers and reviewers, and the technical director of the company approves and signs it and seals it.
2. Design disclosure and system of blue prints.the design: the construction unit shall make all technical preparations before the formal construction, including familiarizing with the drawings, dividing and numbering the project, conducting necessary technical disclosure and technical training, sorting out the records of blue prints.the design and other technical disclosure materials, and signing them with all parties as the construction basis.
3. The construction unit must review the original coordinate points, leveling points and other survey control points provided by the construction unit, and report the retest results to our supervision department for review. After approval, the construction survey control network can be established.
4. The main materials, semi-finished products and finished products used in the project should be submitted for inspection, and the related materials related to the project safety and use function should be reinspected according to the engineering quality acceptance specifications of various professions, and can be used only after being approved by the supervision engineer to ensure the quality.
5. The types, performance and parameters of construction machinery and equipment used in the project site should match the actual conditions, construction technology and technical requirements of the construction site, and the selection, main performance parameters and operation requirements of the machinery and equipment should be controlled to ensure that the machinery and equipment can meet the actual requirements of construction and production.
6. Project commencement application:
Before commencement, it must be approved: construction organization design/scheme, mobilization plan of materials and equipment, general project schedule, enterprise qualification (including subcontractor and inspection qualification), business license, construction permit, organization of project department, qualification of relevant personnel and post certificate of special type of work, submission of mobilization material quality assurance and re-inspection report, design disclosure and blue prints.the design. The construction party must apply to start construction. Construction can only be started after the conditions for construction are met and approved by the owner and the supervisor.
Second, the construction stage:
Relevant systems implemented by the site supervision department in the construction stage: The Site Supervision Table of Construction Projects in Jiangsu Province (4th Edition) supervised by the Construction Department of Jiangsu Province is used in this project. In addition to the construction organization design review system, the project commencement application system and the blue prints.the design system, the relevant systems of project management formulated by the construction unit should be implemented in the construction stage:
1, quality inspection of engineering materials and semi-finished products
Materials and equipment shall be checked and accepted by special personnel, and the production license, factory certificate, technical certificate or warranty of main materials shall be submitted to the supervisor. New materials have technical appraisal documents, and it is necessary to inspect the manufacturers of important materials when necessary. Materials, finished products and semi-finished products shall be piled up in categories, with obvious signs indicating the names, specifications, entry date, quantity and origin of materials and components, and relevant tests shall be carried out according to professional engineering to ensure the quality of raw materials.
2, site construction survey
Before the project starts, the survey control scheme shall be worked out, the surveyors shall hold relevant certificates, and the instrument accuracy shall meet the requirements and be within the validity period of verification. The survey control points set during construction shall be properly protected and shall not be moved without authorization. In the process of construction, the survey must be carefully reviewed and submitted to our supervision department for review. After verification, it meets the requirements of design drawings before the construction of related processes can be carried out.
3, engineering inspection system
After the process construction is completed, the construction unit shall report to the supervisor within 24 hours after passing the self-inspection, and can enter the next process construction only after being signed by the supervisor.
4, concealed engineering quality acceptance system
During construction, before concealed works are concealed, the construction unit shall report to the supervision engineer after self-inspection and acceptance (24 hours in advance) according to the requirements of relevant standards, specifications and design drawings, and the supervision engineer shall determine the time, organize relevant units to jointly accept them, and sign and seal the quality acceptance record of concealed works before concealment.
5, design change processing system
The design change requirements put forward by the construction unit shall be reported to the supervisor in written form (technical approval form) as required, and the construction unit shall contact the design institute to perform the design change procedures.
6, site meeting minutes system
Hold site meetings regularly every week, with participants: site representatives of the construction unit, members of the supervision department, project department managers, technical leaders, builders, safety officers and quality inspectors. The manager of the project department must attend, and shall not be absent without reason, and must ask for leave in advance if something happens.
7. Measurement visa system
The measurement visa of the project must be confirmed by the construction unit, the construction unit and the supervisor (see the relevant project management system formulated by the construction unit for details).
8, project payment and project claim signature system
The project payment shall be strictly implemented in accordance with the relevant regulations of the construction unit. If the design changes exceed the contract workload, the construction party shall report them in time (within fifteen working days), and the supervisor shall sign with the owner for approval. If it exceeds the time limit, it will not be signed.
9, schedule control
The construction unit shall report the progress plan for next month and the completion of the project this month every month, and submit the weekly plan and completion at the supervision meeting. Through the analysis, adjustment and implementation of the weekly progress plan, the plan can be realized. Through the whole construction process, our supervision department carefully and comprehensively analyzes the rationality and feasibility of the construction progress plan compiled by the construction unit, puts forward supervision opinions and makes scientific adjustments. Those who seriously deviate from the progress plan will be ordered to rectify, and even the construction unit will be advised to adjust the construction team in the form of supervision notice to ensure the realization of the project progress.
10, data requirements:
The application materials are in triplicate, and the signature is written by myself with pen or signature pen. The process inspection sheet uses the demonstration form of Jiangsu construction project and construction stage, and the data should be filed according to the document specification.
1 1, safety and civilized construction requirements
To achieve safety first, prevention first, the construction unit should have a special person responsible for safety issues, so that whoever constructs will be responsible. There should be practical safety organizations and measures. Construction personnel should be equipped with safety protection measures (such as helmets) when entering the construction site, and the power consumption on the construction site must be distributed in three levels and protected in two levels.
The on-site supervision of the above-mentioned systems will be strictly controlled in accordance with relevant specifications and mandatory specifications, and the technical data must be synchronized with the site.
Template 2 of project construction meeting minutes In order to further strengthen the communication and exchange between the construction management and the parties involved in the construction, at 9: 30am on March 9th, xx, the third resident office from Jinan to Leling expressway organized a site meeting in February in the conference room of the project department of bid LQSG-6. Participants include project managers Zhao and Zhao Lei, chief engineer, engineering minister and the third resident office. Qi Youguang, deputy chief engineer of resident supervision, presided over the meeting.
I Chang Haiming, Project Manager of LQSG-5 Bid Section, reported the preliminary work:
1, progress completed
(1), the project is completed
The physical project of LQSG-5 Bid Section completed 26 bored piles1017.8m/68 in total this month, accounting for 4.75% of the annual plan of this month. 12994m/ 1573 cement mixing piles have been completed, and 23082m/2349 cement mixing piles have been completed this month, accounting for 5.48% of the annual plan; 2365m2 of dynamic compaction has been completed, totaling 4673m2, and 2.43% of the annual plan has been completed this month; Trenching was completed 1.2 million cubic meters, totaling 38,000 cubic meters, accounting for 28.26% of the annual plan. The output value completed this month is 1.998 million yuan, accounting for 60.5% of the planned output value in 1 and February, and the cumulative output value is 1.47 million yuan, accounting for 6.79% of the contract list.
(2), the construction progress analysis
According to the owner's 1 and February construction output plan and completion analysis, our project department only completed 60.5% of the plan and failed to complete the planned task. The main reasons are as follows: first, the early working face is narrow and it is difficult to start work; Secondly, the construction land was delivered late, which missed the good construction period; Third, winter construction has caused certain objective difficulties to the construction progress; Fourth, the construction planning time spans the Spring Festival and the construction time is shortened.
(3) Measures taken
(1) In February, the project department concentrated on organizing personnel and machinery to enter the site to make full preparations for the climax. (2) According to the annual construction plan issued by the owner, rearrange the construction plan and adjust the number of machinery and personnel entering the site, so as to level off the debts in March and April and ensure the realization of the annual overall construction plan. ③ Closely monitor the construction progress, and timely adjust the production factors according to the actual construction production efficiency. (4) According to the actual situation of the construction site, reasonably arrange the construction process, try to avoid unfavorable construction areas, and quickly form a comprehensive dry situation. ⑤ Arrange the work reasonably, and give priority to solving the key problems that affect the construction progress and the realization of the annual plan, such as the three-pole problem and the borrow yard problem.
2, the next work plan
(1), make every effort to ensure the safety of personnel, machinery, technology, materials and funds at the construction site, and ensure the steady growth of construction output value in March. (2), do a good job of task cohesion, arrange the follow-up construction tasks of the construction site to be completed, and make construction preparations in advance. (3), completes the process cohesion, gradually arrange the small structure and bridge substructure construction team comes into play.
(4) According to the weather conditions, construction projects such as impact rolling, ditch and pond treatment and subgrade test section will be carried out step by step.
(5), actively coordinate and solve? Three tricks? There is also the problem of soil source.
3. Problems existing in the started projects and improvement measures.
The project department shall carry out the construction in strict accordance with the construction plan approved by the resident office and the director office. At present, the construction is normal, and there is no abnormality during the construction. After the finished products of bored pile and cement mixing pile are tested, the bored pile is qualified, the pile body of cement mixing pile is in good condition, and all testing indexes meet the specifications and design requirements.
In the process of construction, there are cases that the sand contains large stones. Under the supervision of on-site engineers, all of them will be screened according to the requirements of higher-level units such as the resident office, and financial penalties will be imposed on suppliers according to regulations.
4, safety, environmental protection and civilized construction site
This month, the construction team entered the construction site more frequently. Before the start of different construction projects, the Engineering Department and the Safety, Quality and Environmental Protection Department of the Project Department respectively provide technical safety disclosure and pre-job safety training for the labor force. The captains and team leaders of all construction teams attended the meeting, and the on-site supervision engineer attended the disclosure meeting as nonvoting delegates, and put forward the supervision requirements. During the construction, the safety, quality and environmental protection departments went deep into the construction site to provide construction safety education and pre-job safety training for laborers one by one.
From the start of construction, the project department will pay close attention to the civilized construction on the construction site and check the safety hazards and civilized construction one by one. This month, the safety protection places 17 were rectified and 59 signs were set.
5. Implementation of existing problems in the last regular meeting
(1), with the substantial settlement of construction land, the project department timely adjusted the construction plan, increased the number of management personnel, mechanical equipment and labor, and comprehensively improved the construction production capacity and management capacity.
(2), fully enable the steel processing plant in the beam yard to solve the problem of storage in the reinforcement cage yard, and each team is equipped with square wood to solve the problem of storage in the reinforcement cage yard.
(3) Strictly implement the incoming materials management system, impose economic penalties on sand suppliers, reduce the problem of excessive silt content in sand materials, and take measures to remove unqualified materials from the scene.
Second, Zhao Jiangshan, chief engineer of bid LQSG-6 project, reported the preliminary work:
1, progress completed:
Subgrade engineering: cement mixing pile completed 25,380 linear meters, accounting for 65.56% of the monthly plan; Dynamic compaction and dynamic compaction replacement are not planned this month. Dynamic compaction 17532m2 and dynamic compaction replacement of 3392m3 are completed, and the output value of subgrade engineering is1719.48 million yuan, accounting for 133.8% of the monthly plan.
Bridge and culvert works: 94 piles with 254 1 linear meter have been completed, among which the pile foundations of K54+394 Zhangzhaigou Middle Bridge, k6 1+753 Oilfield-Shanghe Separated Overpass and K54+ 140 Passage have all been poured; The pile foundations of K52+5 10.5 channel, K57+627.5 channel, K57+ 169 Liuligou middle bridge and K59+432 Wangniegou middle bridge are under construction. The completed output value of bridge and culvert works is 2395720 yuan, accounting for 127.4% of the monthly plan. Without special circumstances, the pile foundation construction can be completed in the near future.
The total output value of this month is 4320389 yuan, accounting for 1, 298+0% of the monthly plan.
Next work plan
According to the current construction situation, the project department has formulated the following March plan:
(1). It is planned to complete the table clearing of the whole line in March, complete the construction access road, and strive to connect the entire access road as soon as possible.
(2), increase investment, focusing on assault soft soil foundation treatment and bored pile construction.
(3) It is planned to carry out the first construction of pile caps, columns, prestressed hollow slabs, impact rolling, circular tube culverts and passages this month, so as to summarize data and accumulate experience for the next large-scale construction. After the first piece is passed, all subdivisional work will be constructed normally.
2. Quality control of completed projects and further improvement measures
In February, the project department constructed cement mixing pile, dynamic compaction and bored pile, and completed some engineering quantities. In view of the low weather and temperature in February, there are still many unfavorable factors in winter construction, and the project department strictly follows the winter construction safeguard measures to ensure the construction quality. The cement mixing pile uses high-temperature groundwater to mix the cement slurry, and at the same time, a thermometer and a heating device are arranged in the water storage tank to heat the mixing water at any time to ensure the mixing temperature of the cement slurry; In dynamic compaction construction, increase the number of tamping to break the frozen soil and ensure the construction quality; The concrete used in bored pile is heated by boiler, and the raw materials and transport vehicles are covered with heat preservation, so as to ensure that there is no frozen block in the concrete, and the concrete outlet temperature is not lower than 10℃, and the concrete inlet temperature is not lower than 5℃.
3, safety, environmental protection and civilized construction site
(1), security situation
According to the characteristics of winter construction, the project department formulated specific fire safety measures, and put the responsibility to people. It is strictly forbidden to use open flame for heating in the construction site and temporary work shed; When using natural gas and gas, prevent explosion; When using coke oven, coal stove or natural gas and gas, pay attention to ventilation to prevent gas poisoning.
Power switch, control box and other facilities shall be arranged in a unified way, locked and protected. It is forbidden to pull wires indiscriminately, and designated persons shall be responsible for management to prevent leakage and electric shock. It is forbidden to drag the frequently moving machine wires on the ground and immerse them in water.
The temporary water pipes on the construction site should be buried in the soil or wrapped with thermal insulation materials such as straw bags and reinforced with paper. There is water in the water tank, which should be drained before work. Anti-skid measures should be taken in the construction site. Straw bags should be laid on roads with snow on the ground or slopes. Check whether there is any icing phenomenon at any time and clean it up in time.
(2) Environmental protection
The project department strives to do a good job in environmental protection, strictly control environmental pollution, maintain the ecological balance of the region, and minimize the impact of construction on the surrounding environment.
Carry out regular environmental education for construction personnel, enhance environmental awareness, improve the quality of construction personnel, make construction personnel consciously abide by environmental laws and regulations, reduce man-made pollution, and take some practical measures for inspection, supervision and reward.
Minimize domestic garbage. Inevitable domestic garbage is stored centrally, disinfected frequently and transported away in time. Do a good job in environmental sanitation and reduce domestic sewage. Domestic sewage and oily wastewater are strictly forbidden to be discharged directly, and can only be discharged into waterways after sewage treatment and water quality reaches the standard.
Non-constructive destruction of vegetation, indiscriminate cutting and caring for farmland crops are strictly prohibited. When using new machinery and equipment with normal operation and low noise, the machinery and equipment entering the site must be overhauled, and mechanical maintenance and anti-freezing and heat preservation work should be done regularly.
(3), civilized construction situation
Three links and one leveling shall be made on the construction site to keep the drainage unblocked and the surroundings of the construction site clean. Ensure that the temporary water supply and drainage is free from dripping and running water, and the temporary drainage is self-contained according to regulations, and finally discharged into the designated drainage channel.
Set relevant safety warning signs at eye-catching positions on the construction site, and personnel entering the construction site should wear safety helmets and work shoes; Drinking, gambling and fighting are strictly prohibited on the construction site; The machinery on the construction site should be parked at the designated location, and it is forbidden to occupy the road at will. The operating points of all kinds of machinery should be hung with safety operation instruction cards, and unlicensed operation is strictly prohibited, and the equipment should be cleaned and maintained in time.
Construction spoil and muck shall be piled up in strict accordance with the place designated by the owner, and mud shall not be discharged into rivers and farmland. It is forbidden to overload cars and transport bulk materials, and cover them with tarpaulins to prevent bulk materials from being scattered on the road.
4, the last meeting of the existing problems to solve the implementation.
(1), Shanghe county government has replied that it can clear the table one after another in the near future; There are 4 houses in the permanent land acquisition. Because the householder is not satisfied with the compensation amount, no agreement has been reached, and it is difficult to demolish and requisition land. I hope the company can solve it. The locations of the four houses are: K60+025 in the west of Shijiacun, K60+230 in the north of Shanghe-Ji Hu Highway in Shijiacun, K60+260 in the south of Shanghe-Ji Hu Highway in Shijiacun, and K64+425 in the southwest of Nanxiangfang Village. ) the above problems have not been implemented, and we hope to solve them as soon as possible.
(2) Shanghe County Headquarters has arranged for the project department to conduct earthwork negotiations with the three towns along the line;
(3) The problem of oil pipeline and three poles has not been implemented, and it is hoped that it will be solved as soon as possible;
5. Other matters
(1), the temporary land requisition for the construction access road has not been solved;
(2) Local roads (Shanghe to Huairen Highway) are used in the construction process, and the fees charged by the highway and transportation departments are too high. I hope the relevant local departments will give support;
(3) The unpaid land payment was used by local villagers to stop work, hoping to solve it as soon as possible;
In the future, the project department will further strengthen management, scientific planning, increase investment, strive for progress, and fully complete the construction plan issued.
III. On behalf of the Resident Office, Deputy Resident Supervision Engineer Qi Youguang spoke about the problems existing in the construction of two blocks this month and the construction requirements for next month:
1, construction progress, plan completion analysis
Judging from the current construction progress, it is slightly behind the plan issued by the owner. The reason is not only limited by objective conditions, such as LQSG-5, because the first land is Shahe Bridge and Dehui Xinhe Bridge. In fact, because there is no local road in the early stage of Dehui Xinhe site, it is impossible to build a service road when the permanent land is not delivered, resulting in a narrow working face and lagging progress; Secondly, the preparatory work plan before construction is not implemented in place, and the initiative of construction coordination is not strong, which leads to the lag of work and delays the progress of the entity project. Thirdly, the slow temperature rise in February still belongs to the winter construction stage, so it is difficult to carry out construction in an all-round way.
My requirements for the above situation are as follows:
(1), the fifth and sixth paragraphs have worked out practical implementation plans and made reasonable arrangements for the construction team, machinery and materials, so as to do a good job in the future. At present, the construction team has been basically in place, and all the work has been carried out one after another.
(2) Grasp the construction of small structures to create favorable conditions for subsequent construction.
(3), require the construction unit to increase investment in construction strength, strengthen management, and rationally adjust labor and machinery according to the actual situation, so as to achieve the annual overall time limit for a project goal.
2. The problems existing in the quality control and scheme of the completed project and the measures for further improvement. The resident office supervised the partial projects started in the bidding of LQSG5 and LQSG6. Especially the quality of winter construction projects, the inspection results show that the quality is qualified. In view of the large number of construction teams entering the site after the festival, our bureau requires technical disclosure of sub-projects before construction, which must be handed over to front-line workers for disclosure. You can't start work without disclosure. Each project department must strictly follow the plan in the construction process to ensure the quality of the project.
(1). During the construction of bored pile, individual reinforcing cages were not stored according to the specification requirements, which led to the rust of reinforcing cages. The Beijing Office has issued a supervision instruction, which has now met the requirements for rectification.
(2) Individual aggregate is needle-shaped and the silt content is too large, which directly affects the quality of concrete. It is required to strengthen the sampling inspection of raw materials and strictly control the materials. Unqualified materials are strictly forbidden to be used in entity engineering.
(3) In view of the development of third-party testing, our office arranges supervisors to carry out patrol testing, especially the small strain, coring and bearing capacity testing of cement mixing piles. We adopt the method of tripartite spot check by the supervisor, the tester and the construction unit, and randomly determine the number of spot checks and pile locations, which effectively ensures the representativeness and reliability of the test results.
3, safety, environmental protection and civilized construction site
The starting point of this month is relatively concentrated. According to the patrol inspection of the resident office, the safety and environmental protection system is running well this month, no major safety hazards have been found, and no safety and environmental accidents have occurred this month. The resident office focuses on the pre-construction safety disclosure inspection of cement mixing pile, dynamic compaction, bored pile and subgrade surface cleaning for the projects that the construction unit starts first. In view of the large number of teams entering the site after the festival, our office inspected and put on record the certificates, safety qualifications, mechanical equipment, safety protection and operating procedures of the personnel of the construction unit, and inspected the safety of electricity consumption, warning signs, foundation pit protection, mud pit protection and living quarters on the construction site. For the problems existing in the inspection, the construction unit is required to make a rectification plan and complete the rectification within a time limit. After the rectification, the resident office will review the problems and meet the rectification requirements.
With the development of next month's work, the whole line will enter the stage of comprehensive construction. The resident office will strengthen the publicity of safety knowledge on the construction site and intensify the inspection on the construction site, such as the inspection of key parts and key links such as deep foundation pit excavation, hoisting machinery, construction machinery, construction vehicles, aerial work, temporary electricity utilization and overlay facilities. Conduct special safety inspections on the construction site regularly, and improve the safety inspection data and safety ledger at any time.
4, the implementation of the last meeting to solve the problem.
(1), with a large number of construction land solved, each project department adjusted the construction plan in time, increased the number of management personnel, mechanical equipment and labor force, and improved the construction production capacity and management capacity.
(2) The on-site storage of reinforcing cages all adopts stow-wood, which solves the problem of on-site storage of reinforcing cages.
(3) The quality control of raw materials entering the site has been strengthened, and the quality of raw materials has been well guaranteed, especially the problem of large silt content in sand and gravel, which has basically been effectively controlled.
Template of project construction meeting minutes for three times:
Location:
Participants:
Theme:
1, the qualification requirements for the tenderer are:
2. Project duration: calendar days.
3. Bid bond: 10000 yuan (each bid section).
4. Bid evaluation method: price single factor bid evaluation method.
4. 1 The quotations of bidders whose prices are lower than the maximum price are sorted from low to high, and the top ten bidders participate in the qualification examination. If there are less than ten bidders, all of them will enter the qualification examination. In the process of qualification examination, if the number of bidders decreases, it will be replenished according to the bidders' quotations from low to high, so that the number of bidders participating in qualification examination will reach ten.
4.2 A bidder whose price is higher than or equal to the maximum price set by the tenderer shall not participate in the qualification evaluation and bid evaluation of commercial targets.
4.3 Qualification examination methods
4.4 The Bid Evaluation Committee of this project conducts qualification examination for bidders according to the qualification examination application submitted by the bidders participating in the qualification examination, and according to the qualification examination standards. Only bidders who have passed the qualification examination can participate in the evaluation of commercial targets, and bidders who have not passed the qualification examination are not allowed to participate in the evaluation of commercial targets.
4.5 According to the actual situation of this project, the commercial bid of qualified bidders must meet the requirements of the tender documents, and the winning candidate and the winning bidder shall be determined in the following ways:
4.6 The evaluation content of commercial target is the effective quotation of each bidder, and the lowest effective quotation of each bidder is the first successful candidate. If the lowest valid quotation is the same, the tenderer will draw lots on site to determine the first successful candidate.
5. Contract payment method: when 50% of the total project amount is completed, 30% of the contract price will be paid; 65% of the contract price shall be paid after the completion acceptance of the project and the submission of complete completion data; Pay 90% of the approved price after the project is audited; The balance will be paid one year after the audit (without interest). When the project payment is paid after the completion acceptance, the performance bond will be refunded (interest-free).
- Previous article:Is Suzhou Hitachi Chemical easy to enter?
- Next article:Hami Vocational and Technical College has winter vacation time.
- Related articles
- Guang Zhouta's tour guide words
- Wuxi nali hot and sour soup is delicious
- How about Anhui Water Conservancy (Bengbu) Heshun Real Estate Co., Ltd.?
- Which is the best graduate department in National Grid?
- How is this company in Xi'an 58.com?
- What is the treatment for a Xinjiang public security bureau that recruits 600 people?
- How about Hainan Boao Yinfeng Kangyang International Hospital Co., Ltd.
- Where is Lanzhou Reader Museum?
- What are the requirements for working in a gas station?
- How about Liuzhou Institute of Technology?