History of Jiangxi Yadong Cement Co., Ltd.

1994 10 Zhang caixiong, general manager of Taiwan Province Asia cement company, was invited to visit Ruichang city, Jiangxi province to discuss with relevant leaders of Jiangxi provincial government about investing in the construction of a cement plant.

June 65438+July 0997 Singapore Asia Investment Pte Ltd signed a joint venture contract with Jiangxi Building Materials State-owned Assets Management Company on behalf of Taiwan Province Asia Cement Company.

1997 In September, the Ministry of Foreign Trade and Economic Cooperation approved the establishment of the company.

1997 65438+February Ruichang manufacturing factory started construction.

In July 2000, the production line 1 was successfully put into production.

In September 2000, the first kiln was completed and put into operation, and the company began to operate.

On July 2nd, 20065438+0, the expansion of the production line of No.2 kiln was approved by the State Planning Commission.

In February 2002, it passed the ISO 900 1 quality management system certification.

In March, 2002, nine kinds of cement products were awarded the certificate of "National Inspection Exemption for Product Quality".

In March 2002, the production line of No.2 kiln was expanded and ground was broken.

On September 2, 2003, No.2 kiln was put into operation.

2003165438+12 October kiln completion ceremony.

Shareholder change in June 2004: Jiangxi Building Materials Group transferred all its shares to Jiangxi Investment Group Company.

In September 2004, the expansion of the production line of No.3 kiln was approved by the Development and Reform Commission of Jiangxi Province.

From June 5, 2004 to 10, the construction of waste heat power station was approved by Jiangxi Development and Reform Commission.

In June 2004, 165438+ 10, the waste heat power station started construction.

In May 2005, it passed the ISO 1400 1 environmental management system certification.

In June 2005, the production line of No.3 kiln was expanded and ground was broken.

In June, 2005, Baishui Lake Branch (Nanchang Changbei) was put into operation to prepare and transport various types of cement.

In March 2006, the waste heat power station was successfully put into operation.

In July 2007, No.3 kiln was put into production.

On June 5438+ 10, 2007, the expansion project of No.4 kiln production line was approved by Jiangxi Provincial Development and Reform Commission and held in cooperation with the provincial government project.