The following table shows the civil construction contracts of stations and sections of Fuzhou Metro 1 Line. Among them, Chating Station combined with road reconstruction and underground engineering construction, and Fuzhou South Station combined with the main construction of the railway station has started ahead of schedule. Civil construction of Fuzhou Rail Transit 1 Line. The contract section includes the station containing the interval contract unit 0 1. Xiangfeng Station, Xiangfeng Station-Xiushan Station China Railway No.17 Bureau Group Co., Ltd. 02 Xiushan Station, Luohanshan Station Xiushan Station-Luohanshan Station-Fuzhou Station China Railway No.4 Bureau Group Co., Ltd. 03 Fuzhou Station, Doumen Station Fuzhou Station-Doumen Station ~ Shudou Station China Railway No.11 Bureau Group Co., Ltd. 04 Shudou Station, Pingshan Station Shudou Station ~ Pingshan Station ~ Dongjiekou Station China Railway No.1 Bureau Group Co., Ltd. 05 East Street Nanmendou Station ~ Chating Station China Railway Third Bureau Group Co., Ltd. 06 Avenue Station Chating Station ~ Avenue Station China Railway Tenth Bureau Group Co., Ltd. 07 Shangteng Station and Sanchajie Station Avenue Station.

, Hulu Array Station ~ Huangshan Station China Railway Third Bureau Group Co., Ltd. 09 Paixia Station, Chengmen Station, Triangle City Station Huangshan Station ~ Paixia Station, Paixia Station ~ Chengmen Station,

Chengmen Station ~ Sanjiaocheng Station China Railway Electrification Bureau Group Co., Ltd. 10 Dongli Station Sanjiaocheng Station ~ Dongli Station and Dongli Station ~ Fuzhou South Station

China Railway 19th Bureau Group Co., Ltd. 1 1 Xindian Vehicle Comprehensive Base in the shield section and open excavation section of the entrance line of Qingliangshan parking lot,

The open-cut section from Xindian Vehicle Comprehensive Base of Qingliangshan Parking Lot to Xiangfeng Station is Guangxu Station of China Railway Fourth Engineering Group Co., Ltd.-China Railway Construction Engineering Group Co., Ltd. The following table shows the civil construction supervision of stations and sections of Fuzhou Metro 1 Line. Civil construction supervision of Fuzhou rail transit line 1 (Phase I) Station, section and parking lot supervision unit included in the scope of this contract 0 1 Three-station and four-section shield working well ~ Xiangfeng Station, Xiangfeng Station, Xiangfeng Station ~ Xiushan Station, Xiushan Station ~ Luohanshan Station, Luohanshan Station ~ Fuzhou Railway Station ~ Doumen Station, Shanghai 3D Engineering Construction Consulting Co., Ltd. Sanchajie Station, Sanchajie Station ~ Baihuting Station, Baihuting Station ~ Hulu Array Station, Hulu Array Station, Hulu Array Station ~ Huangshan Station, Huangshan Station Guangdong Heavy Industry Construction Supervision Co., Ltd. 05 Station 6 Section Huangshan Station ~ Paixia Station, Paixia Station, Paixia Station ~ Chengmen Station, Chengmen Station ~ Triangle City Station, Beijing Railway Research Construction Supervision Co., Ltd., Fuzhou South Station East-West Extension Line Vehicle base Shanghai Sanwei Engineering Construction Consulting Co., Ltd., Xindian two parking lot vehicle comprehensive bases, Xindian vehicle comprehensive base to Xiangfeng station open excavation section, shield working well, Qingliangshan parking lot engineering consulting supervision Co., Ltd. The following table shows the track engineering contract of Fuzhou Rail Transit 1 Line (Phase I). Fuzhou Rail Transit 1 Line Project (Phase I) Content of Rail Engineering Construction Unit Design Unit Supervision Unit 1 Bid Section Xiangfeng Station to Nanmendou Station (excluding) Main Line and Auxiliary Line, Track-laying of Entrance and Exit Lines China Railway 11th Bureau Group Co., Ltd. Shanghai Tunnel Engineering Rail Transit Design and Research Institute Huatie Engineering Consulting Co., Ltd. Second Bid Section Nanmendou Station to Fuzhou South Railway Station Main Line and Auxiliary Line, The following table shows the power supply system of Fuzhou Rail Transit 60 1 Line Project (Phase I) 1 Line (Phase I) Project (including substation, medium voltage ring network cable, catenary, stray current protection, substation integrated automation, interval dynamic lighting, station environment control cabinet, etc. Consulting unit Beijing Urban Construction Design and Research Institute Co., Ltd. Design unit Shanghai Tunnel Engineering Rail Transit Design and Research Institute Construction unit China Railway Second Bureau Group Electrical Engineering Co., Ltd. Supervision unit Huatie Engineering Consulting Co., Ltd. and Tianjin Lu 'an Electrification Supervision Co., Ltd. The following table shows the weak current installation contract of Fuzhou Rail Transit 1 Line Project (Phase I). Fuzhou Rail Transit 1 Line Project (Phase I) The whole line of weak current installation works (from Xiangfeng Station to South Station), Xindian vehicle base, Qingliangshan parking lot, communication system of control center, signal system, comprehensive monitoring (including environmental and equipment monitoring) and AFC system procurement. Consulting unit Beijing Urban Construction Design and Development Group Co., Ltd. Design unit Shanghai Tunnel Engineering Rail Transit Design and Research Institute Co., Ltd. Guangzhou Metro Design and Research Institute Co., Ltd. China Railway Communication Signal Survey and Design (Beijing) Co., Ltd. Construction unit China Railway Electrification Bureau Group Co., Ltd. Supervision unit Tianjin Lu 'an Electrification Supervision Co., Ltd. The following table shows the wind and water power construction installation and equipment area in Fuzhou Rail Transit 1 Line (Phase I) station reconstruction contract. Fuzhou Rail Transit 1 Line Project (Phase I) Construction and Installation of Wind Power Station and Decoration of Equipment Area

Content 1 Line Project (Phase I) Wind, water and electricity installation (including ventilation and air conditioning system, water supply and drainage and fire fighting system, low-voltage power distribution and lighting system, entrance guard installation) and equipment area decoration. Construction Bid Section Access Line of Bid Section I of Construction Unit Supervision Unit ~ Xiangfeng Station, Xiangfeng Station, Xiangfeng Station ~ Xiushan Station, Xiushan Station ~ Luohanshan Station, Luohanshan Station ~ Fuzhou Railway Station (excluding), Fuzhou Railway Station ~ Doumen Station ~ Shudou Station, and Pingshan Station ~ Dongjiekou Station (excluding) of Bid Section II of Guangdong Industrial Equipment Installation Company Zhejiang Electromechanical Design and Research Institute Co., Ltd. Chating Station, Chating Station ~ Avenue Station, Avenue Station, China Railway 14th Bureau Group Electrification Engineering Co., Ltd./Jiangsu Jingcheng Decoration Engineering Co., Ltd. ~ Avenue Station (excluding) ~ Shanghai Sanchajie Station ~ Baihuting Station, Baihuting Station, Baihuting Station ~ Hulu Array Station, Hulu Array Station ~ Huangshan Station of Guangdong Heavy Industry Construction Supervision Co., Ltd. (excluding) ~ Paixia Station, Paixia Station. The following table shows the situation of renovation contract in the public area of Fuzhou Rail Transit 1 Line (Phase I). Fuzhou Rail Transit 1 Line Project (Phase I) Public Area Decoration Project

Contents Public area decoration, accessory building decoration (four small pieces on the ground), steel structure, curtain wall (including all property entrances and exits and reserved entrances and exits), dynamic lighting engineering, and other coordination work for deepening design work. 4 stations of the construction unit 1 Bid Section: Xiangfeng Station, Xiushan Station, Luohanshan Station and Fuzhou Railway Station; Fuzhou Jianyi Construction Co., Ltd. has 4 stations in the second bid section: Doumen Station, Shudou Station, Pingshan Station and Dongjiekou Station; Fuzhou Pengcheng Architectural Decoration Design Engineering Co., Ltd. has three stations in the third bid section: Nanmendou Station, Chating Station and Daodao Station; Fujian Xingmei Ecological Building Decoration Co., Ltd. has five stations: Shangteng Station and Sanchajie Station in the fourth bid section: Baihuting Station, Hulu Array Station and Huangshan Station; Bid 5 of Paixia Station, Chengmen Station, Sanjiaocheng Station, Lei Yu Station, Shenzhen Overseas Decoration Engineering Co., Ltd. and Fuzhou Huaju Decoration Engineering Co., Ltd., and the bidding situation of Fuzhou Rail Transit 1 Line Project is shown in the following table. Shenzhen Li Nan Decoration Engineering Co., Ltd. Fuzhou Rail Transit 1 Line (Phase I) Station Decoration Design and Guiding Sign System Design (1 Bid) Procurement and Construction Bidding Related Bidding Project Name Rail Transit 1 Line Procurement and Installation Project (Xiangfeng-Avenue Station 1/Bid) Co., Ltd. Procurement and installation project of guiding sign system for Line 2 (Shangteng-South Railway Station 654 Co., Ltd. Rail Transit 1 Line Project (Phase I)) Integration of special communication and civil communication system (AFC) of China Railway Electrification Bureau Group Co., Ltd. Rail Transit 1 Line. Project Fujian Shenwei System Integration Co., Ltd. Rail Transit 1 Line (Phase I) Integrated Monitoring System Integration (including ISCS, BAS and access control) Shenzhen Dashi Intelligent Co., Ltd. Rail Transit 1 Line (Phase I) Platform Screen Door System Supply and Installation Project Shenzhen Fangda Automation System Co., Ltd. Rail Transit Clearing Center (ACC) System Integration Project Fujian Shenwei System Integration Co., Ltd. Rail Transit 1 Line Project (Phase I) Automatic Fire Alarm and Gas Extinguishing System Nanjing Fire Equipment Co., Ltd., Limited Rail Transit 1 Line Subway Public Security Transmission, PDT Wireless Communication and Large Screen System Integration Project Guangdong Huazhiyuan Information Engineering Co., Ltd. Rail Transit 1 Line 1 Project Technical Security System Procurement Project Beijing Zhongdun Anmin Analytical Technology Co., Ltd. Rail Transit 1 Line 1 Project (Phase I) Station Advertising Resource System Equipment Procurement Project Hangzhou Bainian Photoelectric Logo Co., Ltd., Ltd. Rail Transit Line 1 Project Automatic Train Cleaning Machine Procurement and Installation Project Harbin Wake Rail Transit Communication Technology Development Co., Ltd. Rail Transit Line 1 Elevator and escalator package 1- All-line 2 1 There are 43 elevators in the underground station without machine room 1 Elevator and escalator package 2- Xiangfeng Station to Nanmendou Station 100 escalator Shanghai Mitsubishi Elevator Co., Ltd., Limited Rail Transit Line 1 Elevator and escalator package 3- tea Kloc-0/ 15 Rail Transit Line of Schindler (China) Elevator Co., Ltd. 1 Technical Support Project for Engineering Operation Guangzhou Zhongzi Urban Rail Transit Engineering Consulting Co., Ltd. (consortium: Guangzhou Urban Rail Transit Training Institute Co., Ltd.) Rail Transit Line 165438+. Fuzhou Yili Electric Power Engineering Co., Ltd. Rail Transit 1 Tea Pavilion 1 10kV Main Substation Project Construction Fuzhou Yili Electric Power Engineering Co., Ltd. Fuzhou Rail Transit 1 (Phase I) Project is as follows. Fuzhou Rail Transit 1 Line (Phase I) project interval breakthrough schedule (as of 20 15 and 65438+February), the interval breakthrough time is up and down, and the access sections of Xindian vehicle base are 20 14, 1 and 201. 438+Before February 2005, Xiushan Station, Luohan Station, 2065438+July 2004, 65438+June 2065438+2004 10, Luohan Station, Fuzhou Railway Station, 2065438+September 2005 18, Doumen Station, Fuzhou Railway Station, 2065438+2008. 38+September 1 1, 2065438+June 30, 2003 Shudou Station Pingshan Station 2065438+August 5, 2065438+July 1 1, Pingshan Station Dongjiekou Station 2065438+ Jiekou Station Nanmendou Station 2065438+June 2005 Qiannanmendou Station Chating Station 2065438+March 2005 365438+October 30, 2065438/Kloc-Chating Station Avenue Station 2065438+February 25, 2065438+August 2005. Before June 65433438+04, Huangshan Station 2065438+July 20, 2065438+May 2004, Huangshan Station 20 14 June, Huangshan Station 20 19 February, Huangshan Station 2065438+August 2004. 5438+September 26th, 2003, Bulei Station, Triangle City Station, 2065438+April 8th, 2005, Bulei Station, Fuzhou South Station, 2065438+April 9th, 2005, Qingliangshan parking lot access section, 2065438+March 25th, 2005, the following table shows Fuzhou rail transit 65438. Fuzhou Rail Transit 1 Phase II Project (Construction) Unit: This contract section includes the site including the interval construction unit supervision unit 0 1 station (Fuzhou South Station ~ Jihu Station), China Railway Eighth Bureau Group Co., Ltd. Shanghai Xianxian Construction Supervision Co., Ltd. 02 Liangcuo Station (Station ~ Liangcuo Station), China Railway Fourth Bureau Group Co., Ltd. 03 Xiayang Station (Liang