Job Recruitment Website - Job information - How to calculate the labor cost of building lighting construction

How to calculate the labor cost of building lighting construction

Generally speaking, it can be roughly divided into two pricing methods.

1. the first type: calculate the engineering quantity and how much labor is needed.

Example: 10000 lamps are installed, and there are 6 workers in one group. It takes 33 days for each person to install 50 lights every day.

Plus 5 days of commissioning and acceptance, it takes 38 days, and the daily salary of workers working high above the ground ranges from 400 to 800 (Hubei area).

Then the daily labor cost multiplied by the number of days is your labor cost.

———————————————————————————————————————

2. The second type: calculate the number of lamps and multiply it directly by the installation fee of each lamp.

This method is relatively simple, but it is also very different. For example, different lamps have different installation positions, different installation methods and different prices.

Generally speaking, installing a lamp costs tens of dollars on average.

———————————————————————————————————————

The above is for reference only. I suggest you find a professional installation company according to the specific situation. The personal installation team is not insured. If something goes wrong, you will not only have to bear huge compensation but also be detained. The lighting of the building belongs to high-altitude installation with high risk factor. I hope to pay more attention.