Responsibility book for target management of engineering projects

Responsibility book for target management of engineering projects

In today's society, we are all directly or indirectly related to the letter of responsibility, which is a document stating the scope and responsibility of responsibility. There are many precautions in drafting the responsibility book. Are you sure you can write it? The following is the project target management responsibility book I compiled for you. Welcome to share.

Responsibility Letter of Project Target Management 1 Party A:

Party B:

In order to strengthen the management of construction projects, fully mobilize the enthusiasm of project managers, ensure the full implementation of Party A's commitment to the construction unit, achieve various management objectives such as time limit, quality, safety and civilized construction, and improve economic and social benefits, Party A entrusts this project to Party B to organize the construction according to the Contract Law, and both parties reach an agreement through consultation, sign this responsibility letter and strictly abide by it.

I. Overview of the Project

1, project location:

2. Project name:

3. Contract price of the project: the comprehensive unit price is RMB/㎡, and the total project amount is the settlement of engineering quantity.

4. Building area and engineering structure: building area ㎡, brick-concrete structure.

5. Project content: all projects within the scope of the drawings.

6. Duration: According to Party A's requirements.

7. Contracting method: fixed total price.

Second, the management mode:

Party A shall carry out macro control and management of the whole process of project implementation. Party B shall, according to the scope authorized by the legal representative of Party A, conduct overall construction management of the project, operate independently, be responsible for its own profits and losses, undertake all the responsibilities and obligations of the contractor stipulated in the contract signed between Party A and the construction unit, and undertake corresponding economic and civil responsibilities.

Third, fund management.

1. The funds used by Party B for this project must be used for special purposes and shall not be misappropriated; During the construction period of the project, Party A will not advance various funds such as engineering labor, materials and machinery.

2. Party B shall establish all kinds of ledgers in strict accordance with Party A's financial system and regulations, and reasonably avoid all kinds of risks, otherwise all consequences arising therefrom shall be borne by Party B. ..

Fourth, the project quality and warranty

1. Engineering quality grade: qualified.

2. During the construction period, Party B must strengthen the project quality management to ensure the realization of quality level. Failure to reach the quality level is regarded as breach of contract, and Party B will pay Party A a penalty of 5‰ of the total project price, and all losses such as fines and rework given by the construction unit shall be borne by Party B. ..

3. During the warranty period, if Party B fails to guarantee in time, Party A has the right to arrange personnel to carry out maintenance, and the required expenses shall be deducted from the due amount of Party B (plus 10% management fee).

4. The warranty money shall be executed according to the contract signed between Party A and the construction unit, and shall be returned to Party B after the warranty period expires.

V. Safe production and civilized construction

Six, time limit for a project management

Party B shall complete the project on time with good quality and quantity according to the construction period specified by the construction unit or Party A, and the commission given by the construction unit or the reward and punishment for delaying the construction period shall be borne by Party B. ..

Seven, human resources management

1. Party B must provide pre-job training and education for new workers. For those who need to apply for a work permit, they must apply for a work permit in accordance with the regulations, so that they can work with certificates. Those who are uneducated or undocumented shall not take up their posts, otherwise the consequences arising therefrom shall be borne by Party B..

2. Strictly implement the employment management system, and handle the relevant formalities with the company's human resources department in time for temporary employment, and Party B shall bear the salary, labor insurance, welfare and other expenses, otherwise, it will be treated as private recruitment and arbitrary employment, and all the consequences arising therefrom will be borne by Party B. ..

3. After the payment of the project funds, Party B shall first ensure the payment of workers' wages, and shall not delay the payment of workers' wages without reason. Otherwise, Party A has the right to directly deduct the wages owed to the workers from Party B's project payment, and Party B shall pay Party A a credit compensation of 654.38+10,000 yuan for each delay in payment of Party B's wages.

Eight. Rights and obligations of Party B:

Nine. Termination of contract

In any of the following circumstances, Party A may revoke this responsibility letter and entrust others to manage the project:

1. During the project construction, Party B failed to achieve the main responsibility indicators;

2. Party B fails to fully perform the duties agreed in Article 8, resulting in management confusion, and Party A considers it difficult to complete the contract objectives after examination;

3. Party B has seriously violated Party A's enterprise management system and still refuses to correct it after criticism and education;

4, illegal, illegal business, resulting in adverse effects;

5. Both the construction unit and Party A consider Party B incompetent;

X. In addition to the fine that must be paid in cash, the fine imposed by Party A on Party B shall be deducted from Party B's project payment.

XI。 Matters not covered in this contract shall be implemented according to the construction contract signed between Party A and the owner and the documents issued by Party A. ..

12. This contract is made in quadruplicate, with Party A holding two copies and Party B holding two copies. It shall come into effect after being signed or sealed by both parties, and shall automatically terminate after the project warranty period expires and the accounts of both parties are settled.

Party A: (Seal) Representative: (Signature)

Party B: (Seal) Representative: (Signature)

Date of Signing: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Responsibility letter of project target management 2 Chongqing XX Real Estate Development Co., Ltd. (hereinafter referred to as the owner or the construction unit) contracted by Chongqing Engineering Company (hereinafter referred to as the construction unit) responsible for Chongqing XX Real Estate Development Co., Ltd. (hereinafter referred to as Party A) manages the project. The project overview is as follows:

Party A appoints the company's project manager (builder or site representative) (hereinafter referred to as Party B) to undertake all the construction of the above projects.

Party A takes the responsibility system of the project manager (builder or site representative) as the core, the project as the object, the construction drawing, the construction contract and related materials (data) as the basis, the quality and safety as the center, and the cardinal number management as the means, adheres to the principle of "guaranteeing the cardinal number, guaranteeing the delivery, sharing the excess part equally and making up the excess part", and adopts the principles of "highlighting indicators, clarifying responsibilities, strict assessment, personal responsibility and overall contracting.

1. Economic objective: Party A will reward Party B with RMB (in figures: _ _ _ _ _ _) in one lump sum after Party B completes all the clauses in this objective.

2. Quality objective: According to the current quality acceptance standards and regulations, it will pass the one-time acceptance.

3. Safety objective: put an end to fatal accidents, serious injuries, major traffic accidents and fire accidents, and control the frequency of minor injuries below 3‰.

4. civilized construction goal: to reach the district-level "standardized construction site for safe production and civilized construction"

5. Time limit: according to the construction contract and the requirements of the owner, supervisor and Party A. ..

6. Others: provide complete completion data as required within 15 days after completion acceptance.

According to the above objectives, in accordance with the Contract Law of People's Republic of China (PRC) and relevant laws, regulations and provisions, in coordination with the relevant rules and regulations of Party A and the construction unit, and in combination with the actual situation of the owner and the project, in order to achieve the above objectives, Party A and Party B have reached the following terms, which shall be abided by both parties.

Work content of 1

1. 1 Party B must carry out the construction in strict accordance with the construction drawings and design documents (including design changes and records of joint review of drawings, etc.). ) provided by the owner or the construction unit.

1.2 Party B must carry out the construction in strict accordance with the bidding documents (including drawings answering questions, addenda or notices, etc.). ) provided by the owner or the construction unit.

1.3 Party B must strictly follow the construction contract (including supplementary contract and meeting minutes, etc. ) signed by the construction unit and the owner or construction unit.

1.4 Party B must carry out the construction in strict accordance with the contracts and requirements signed by Party A and the construction unit.

1.5 completion data

2 Organizational structure and personnel arrangement

2. 1 Party A sets up a project department for this project, and determines the personnel and responsibilities of the organization;

Party B shall manage and arrange the work and check the attendance of agency personnel.

2.2 Party B accepts Party A's leadership, unified command and management, consciously abides by Party A's rules and regulations, carries out Party A's decisions, and fulfills Party A's obligations for project construction (contract terms).

2.3 Party A's management (technical) personnel stationed at the site shall obey Party B's work arrangement and command, exercise their rights within the scope of their duties in their work, cooperate with each other, unite as one, take the initiative to discuss when something happens, and complete all tasks assigned by Party B. ..

3 Determination and payment of wages

3. 1 During the contract construction, Party A shall pay Party B the salary 1000.00 Yuan/month.

3.2 If the contract period is exceeded (without the extension notice from the owner and supervisor), Party A shall pay Party B 70% of the monthly salary of 1000.00 yuan.

3.3 Wages of other personnel

4 the provisions of the economic goals

4. 1 reward distribution

4.2 Payment of incentives

5 Quality management

5. 1 Party B must carry out fine construction in strict accordance with the current construction specifications and technical standards to ensure the project quality; According to the current quality evaluation standards for acceptance, to achieve acceptance.

5.2 If the one-time acceptance is unqualified, Party B shall bear 50% of all re-acceptance expenses.

5.3 Party B shall bear all expenses for rework during construction.

5.4 Party B shall bear all expenses arising from the non-conformity of samples.

5.5 Party B unconditionally accepts the quality inspection of Party A (or on-site quality inspector), the owner, the construction unit and the supervision unit.

6. Safety management

6. 1 Party B must do a good job in safety education, training, personal protective equipment and health maintenance of workers in strict accordance with the current national safety operation regulations; Do a good job in the safety protection and facilities protection of machinery (equipment), obey the command and management of Party A, ensure safe operation and prevent safety accidents.

6.2 In case of a safety accident of less than 500.00 yuan, all expenses shall be borne by Party B, and Party B will be fined 100.00 yuan.

6.3 In case of a safety accident of RMB 500.00 ~20xx.00, all expenses shall be borne by Party B, and Party B shall be fined RMB 65,438+RMB 000.00 ~ RMB 500.00.

6.4 In the event of a safety accident of more than 20xx.00 yuan, Party B shall bear all the expenses and impose a fine of 1 000.00 yuan on Party B. ..

6.5 In the event of a major casualty accident, Party B shall bear all legal responsibilities, deduct all rewards and impose a fine of 20xx.00 yuan on Party B. ..

7 civilized construction management

7. 1 party b must carry out the construction in strict accordance with JGJ59-99, and the project must reach the district-level "standardized construction site for safe production and civilized construction".

7.2 2 yuan will be deducted from the bonus for failing to meet the standard.

8 time limit for a project management

8. 1 Party B must arrange the design and construction (scheme) in strict accordance with the construction contract period, and make reasonable arrangements to ensure the construction period.

8.2 If the construction period is delayed for 7 days, Party B will get a 20% bonus.

8.3 If the construction period is delayed for more than seven days, Party B will be punished by 40% of the bonus amount within one month.

8.4 If the construction period is delayed for more than one month, Party B shall pay a bonus of 100%.

8.5 If there is time limit penalty in the construction contract, it shall be punished at the same time according to the terms of the construction contract.

8.6 If the owner, the construction unit and the supervision unit effectively prove that the completion is delayed, it will not be handled.

9 material (parts) management

9. 1 Party A shall manage and purchase materials (parts) in a unified way.

9.2 The materials (components) needed by Party B shall be provided with a plan three days in advance, and shall be purchased after examination and approval according to regulations.

9.3 Damaged, lost and wasted materials (components) shall be compensated according to the price.

9.4 The stolen materials (components) shall be compensated by 10 times.

10 management of mechanical equipment and turnover materials

10. 1 Party A shall uniformly manage and arrange the use of machinery (furniture) equipment and reusable materials.

10.2 The machinery (furniture) equipment and turnover materials required by Party B shall be provided with a plan ten days in advance, and purchased after examination and approval according to regulations.

10.3 the damaged and lost machines and tools and turnover materials shall be compensated according to the price.

10.4 the stolen machines, tools and turnover materials shall be compensated at the price of 10 times.

1 1 wealth management

1 1. 1 Before 25th of this month, Party B will report to Party A the completion of the project this month and the actual situation on site, and provide the plan for next month.

1 1.2 The on-site receiver and a representative of Hutchison Whampoa, Party B and Party A's company sign the on-site receiver, and issue the completion list, which will be paid after the approval of the company.

1 1.3 The settlement bill issued by Party B must comply with the relevant provisions of the financial system, otherwise Party A has the right to refuse to pay.

1 1.4 The bills issued by Party B are not allowed to evade taxes, and the consequences are at their own risk.

1 1.5 Party B shall not falsely report or cheat the customs, and put an end to all unhealthy practices.

1 1.6 Party B consciously safeguards the interests of enterprises and employees and correctly handles the interests of the state, enterprises, collectives and individuals.

12 others

12. 1 Party A has macro and micro control and supervision over the site construction process, and has the right to request any information and data on the site, which Party B unconditionally provides and collects.

12.2 in case of violation of many clauses in this responsibility book, it shall be punished at the same time.

12.3 In case of repeated violation of the target responsibility book, Party A has the right to cancel delisting and terminate the target responsibility book.

12.4 The final interpretation right of this target responsibility book belongs to Party A. ..

12.5 This target responsibility book is made in quadruplicate, with Party A holding three copies and Party B holding one copy, and all the clauses will naturally become invalid after being fulfilled.

Party A:

Person in charge:

Party B:

Responsibility book for target management of engineering projects. The company implements the project manager responsibility system, and the project manager is fully responsible for project management. In order to stimulate the sense of responsibility, enthusiasm and initiative of the staff of the project department, comprehensively improve the quality of the project team and project management level, improve the profitability of each project, enhance the core competitiveness of the company and increase the economic benefits of the enterprise, this responsibility book is specially formulated.

I. Project name:

Second, the target work content:

Complete all the remaining work of the project after the initial inspection, including but not limited to: all the projects that need to be rectified are completed, the final accounts for completion are completed, and the engineering materials are complete and submitted to the owner for filing.

Third, the time to complete the target work:

Four, the project personnel composition and its main work requirements

1. Project manager: fully responsible for the work of the project department, independently arrange the work of the project department members, and ensure that all objectives and requirements are completed within the time specified by the company;

2. Documentation: responsible for completing all engineering data of this project as required;

3. Constructor: cooperate with the related work of project completion;

4. Technician: Complete the civil engineering drawings and hydropower completion drawings of this project;

Five, the project manager job responsibility requirements

(a) familiar with and implement the laws, norms and systems.

1. Seriously implement the Construction Law of People's Republic of China (PRC), the Law of People's Republic of China (PRC) on Work Safety, national and industrial norms, procedures and standards, as well as the company's management manuals, program documents and work instructions on quality, environmental protection and occupational safety and health.

2. Be familiar with and strictly implement the company's rules and regulations and management requirements, supervise the work of subordinates according to the work flow and work standards, formulate, improve and implement the management system of the project department in combination with the characteristics of its own projects, and reward and punish relevant parties according to the company's relevant rules and regulations and management requirements.

(2) coordinating foreign relations

1, coordinate the relationship between units involved in design, owner, supervision, survey, quality inspection and test, and improve the external environment of construction.

2. Actively carry out market research, actively collect engineering construction information, and participate in project tracking, public relations, regional market development and rolling development of the follow-up projects of this project.

(three) fully responsible for project management, implementation, inspection and supervision of the work of each position.

1. The company implements the project manager responsibility system, and its work includes but is not limited to: project safety, project progress, project quality, project data management and collation, internal and external coordination, personnel organization and arrangement, inspection, training, machinery and equipment organization and management, raw material procurement and storage, finished product protection, organization of completion settlement, collection of project progress payment, review and signing of various project documents of the project department, and inspection of project progress.

2. The project manager is responsible for the overall management, coordination, implementation and process supervision of all the work involved in this project. On the basis of ensuring safe construction, he must ensure that the construction task is completed according to the schedule, quality and cost control, earnestly fulfill the contract signed with the construction unit and the company, and ensure the completion of various economic and technical indicators issued by the company.

3. Strengthen and improve the cost management of the project department, do a good job in economic analysis and accounting, strictly implement the requirements of energy saving and consumption reduction, put an end to waste, reduce costs, improve profits, and deeply realize that measurement is the key to project profits.

4, according to the relevant requirements of the province and city, do a good job in the construction site safety production temporary buildings, civilized construction settings. Strengthen on-site civilized construction and safe construction. Safety requirements must be implemented in the construction site, including but not limited to wearing safety helmet, barefoot shoes, taking safety precautions, finding and properly handling emergencies in time, etc.

5, reasonable organization and deployment of people, machines, materials and other construction organization arrangements, sign relevant contracts, daily work arrangements need to be forward-looking.

(4) Engineering data management

1, responsible for supervising and checking whether the employees of this department (librarians, technicians and builders) collect, fill in and sort out the materials needed for the project according to the technological requirements and construction process, and whether the original materials of the project are scanned and archived, with complete requirements and clear directories. These materials include, but are not limited to, construction diary, survey data, laboratory data, change visa data, supervision visa of Party A, material qualification certificate, photos of construction site, engineering data signed by Party A and supervision, original data of unique vouchers and other relevant materials of the project.

2. Ensure that the data required for the project must be synchronized with the construction progress, ensure its completeness, accuracy and traceability, and do not delay the settlement after the completion of the project. After the completion of the project, organize personnel to carry out the final acceptance settlement in time.

3. Every Friday, the project completion table will be summarized and reported to the engineering director, and the electronic documents of engineering data synchronized with the construction will be submitted to the company office for backup.

4. During the project, submit the following materials to the company every Friday.

4. 1 project preparation stage: the project manager is responsible for compiling the construction organization design and submitting it to the technical director of the company for approval; Before construction, the project manager shall organize the disclosure of the main personnel of the project; And form a disclosure process record, and the disclosure personnel shall sign the disclosure record; Project construction schedule, required raw materials and equipment, construction machinery and tools, labor plan and project management reserve funds, etc. ; General situation of project department management personnel, project commencement report, full set of construction drawings published after deepening design, labor contracts for partial projects (subcontracting if necessary), etc.

4.2 Construction stage: Before the commencement of each sub-project, the safety technical disclosure shall be made to the construction personnel and recorded, and the personnel participating in the disclosure shall sign the disclosure record; Weekly construction situation and site construction progress summary; Overall project material and equipment schedule, phased material and equipment entry schedule, capital demand schedule, and construction site work log; Contact visa form for engineering quantity change on the construction site; Design modification change order; Attendance records of on-site construction personnel; Process quality inspection sheet signed by the supervisor; Take cover engineering supervision has a work visa and weekly safety education records.

4.3 Completion acceptance stage: sub-project quality acceptance report issued by the supervision company, project completion acceptance document issued by Party A, and project qualification acceptance report issued by residential engineering technical defense office; Handover visa for handing over equipment to the property; List of completed engineering equipment, detailed written materials of engineering completion drawings and equipment installation and distribution approved by the Chief Engineer's Office, list of remaining materials of completed engineering, etc.

(five) to complete other tasks assigned by the leadership on time, and timely feedback the results of the assigned tasks to the assigned person.

Six, target assessment, cash

1. Regular inspection The company will organize various professionals to conduct routine inspections on each project department every week, and put forward written rectification opinions on the problems existing in the project department.

2. After the target work content is completed, the company will organize relevant personnel to conduct overall inspection and assessment of the project, and pay wages and bonuses according to the assessment results and the actual completion of the work.

3. Wages and bonuses.

(1) From the date when the target assessment is required, the members of the project department will only be paid for two months, and only 50% of the salary will be paid each month. After completing all the target requirements within the time specified by the company, the remaining wages and bonuses will be paid in one lump sum.

(2) The bonus distribution is as follows:

A. Project manager: RMB XX million will be awarded;

B, documenter: issue all progress awards;

C, the builder: with the completion of the project, RMB XX will be awarded;

D. Technician: RMB X will be awarded for completing civil engineering drawings and hydropower completion drawings;

E. Technician: RMB X will be awarded for completing the greening completion drawings and general drawings;

(3) Punishment for failing to complete the target work content on time

1. If the target work content is completed beyond the specified time, the project members have no salary;

B. If the target work is completed within one month beyond the specified time, 50% bonus will be deducted until the penalty is deducted;

C, the project manager is the first person in charge of the company's target management responsibility assessment. The working time and target work completion time of all personnel in the project department shall be specifically arranged by the project manager, and the bonus deduction of personnel in the project department shall be decided by the project manager.

4. The project manager should explain to the project members and implement the contents of the project management by objectives responsibility book.

;