The whole process of real estate development project construction.

Planning, construction and reporting procedures

A, bid for the "construction project site submissions" procedures

1. Information to be submitted for bidding for the Construction Project Site Selection Opinion:

(1) project proposal approval document;

(two) the feasibility report of the construction project;

(3) An application report on the site selection of the construction project;

(4) environmental impact statement;

(5) Location map and land use scope map.

2 "construction project site submissions" bidding procedures:

(1) Application for site selection: The construction unit shall apply for site selection to the town planning and construction office where the site is located with the required materials.

(2) Propose site selection opinions: The town planning and construction office puts forward preliminary site selection opinions according to the requirements of urban planning and the nature and scale of construction projects.

(3) Fill in the Application Form for Site Selection of Construction Project: The construction unit shall fill in the relevant part of the Application Form for Site Selection of Construction Project according to the preliminary site selection opinions, and after the preliminary opinions are signed by the Town Planning and Construction Office, attach the documents and materials to be submitted, and report them to the Planning Section of the Municipal Planning and Land Bureau for approval.

(4) Issue of site selection opinions for construction projects: After the approval of the Planning Department of the Municipal Bureau of Planning, Land and Resources, issue site selection opinions for construction projects and submit them to the Town Planning and Construction Office for use by the construction unit.

Two, the bid for the "construction land planning permit" program

1. Information to be submitted when applying for a planning permit for construction land:

(1) land application report (project nature, land use basis, construction purpose, area, technological process, environmental protection requirements, etc. , and the categories of expropriated land, water and electricity, transportation and house demolition);

(2) Relevant approval documents of the construction project (the approval of the competent department, planning department and municipal government and the approval of the municipal government are required for the construction of villa-style commercial housing and single-family commercial housing with walls);

(3) the location map of the plot or the planning map and general plan of the area where the plot is located (including four or four);

(4) Written opinions of relevant departments (land, environmental protection, water and electricity, power supply, transportation, highway, municipal administration, fire protection, sanitation, etc.). );

(5) A copy of the Construction Project Site Selection Opinion issued by the planning department (except the site selection opinion).

2. Procedures for bidding for "Construction Land Planning Permit":

(1) The unit applying for construction land shall prepare the required documents, apply to the town planning and construction office, and fill in the Approval Form for Construction Land Planning Permit.

(2) the location and boundary of the selected land

Town planning and construction office according to the nature, area and scope of land use, in accordance with urban planning, agreed on the specific location and boundaries of land use, and marked on the topographic map or planning plot map.

(3) solicit opinions

Units applying for construction land shall solicit specific opinions from relevant departments such as land and environmental protection on the location and boundary of land use as needed.

(4) provide planning and design points

According to the opinions of the planning and relevant departments, the Town Planning and Construction Department provides the planning and design conditions to the applicant, mainly reviews the location and boundary of the land, determines the requirements such as the building red line, and the construction unit carries out the general layout design according to the planning and design points.

(5) Review the general plan of planning and design.

The town planning and construction office organizes the review of the general plan of planning and design provided by the applicant (mainly to review the location and boundary of land use and determine the requirements of building red lines), and after signing the preliminary examination opinions, it shall be submitted to the planning department for examination and approval together with relevant drawings and accessories.

(six) the issuance of construction land planning permits.

After the approval of the Planning Department of the Municipal Bureau of Planning, Land and Resources, the "Construction Land Planning Permit" will be issued, and the town planning and construction department will issue it to the units applying for construction land.

Extended data:

Application for construction refers to the application for construction of engineering construction projects. The application for construction of a construction project refers to the behavior that the construction unit or its agency must submit an application for construction application to the local construction administrative department or its authorized institution after the feasibility study report of the project or other project approval documents are approved, and submit the approval documents for project approval, including the credit certificate issued by the bank and other relevant documents such as the approved construction land.

Architectural application program

First, the construction unit to the construction administrative department or its authorized agencies to receive the construction project registration form.

Two, fill in the registration form according to the contents and requirements of the registration form.

Three. Submit the application form to the construction unit [1]? The competent department shall examine and sign opinions.

Four, submit the registration form to the construction administrative department and submit the project approval documents and construction project planning permit, land use permit, investment permit and proof of funds.

Five, the construction administrative department or its dispatched office after the signing of the audit opinion, return to the construction unit project registration form, enter the construction drawing document review process.