What information does the developer need to hand over when the property company takes over the property?

1. According to the property management regulations, the materials to be handed over when the property company and the developer (developer) hand over are as follows:

Overview of handover main data:

(1) Completion acceptance data such as completion general plan, single building, structure and equipment completion drawings, supporting facilities and underground pipe network project completion drawings;

(2) List of facilities and equipment used in * * * and technical data such as installation, use and maintenance;

(3) Water supply, power supply, gas supply, heating, elevator, fire protection, environmental protection, lightning protection, communication, cable TV and other documents. ;

(4) Quality warranty documents and property use documents of the property;

(5) List of houses and facilities;

(6) Check other information required (such as property ownership information, customer information, warranty information, etc.). ).

Second: attach some detailed information that needs to be handed over:

1, * * * Some houses and * * * facilities

(1) as-built drawings and as-built reports.

1) completion site plan;

2) Single building, structure and as-built drawings;

3) Completion drawing of supporting facilities and underground pipe network project;

4) Completion acceptance data:

(1) Record Form for Completion Acceptance of Housing Construction Project and Municipal Infrastructure Project;

(2) the construction project completion acceptance report;

(3) the quality inspection report of the survey and design unit, the quality evaluation report of the supervision unit and the project completion report of the construction unit;

(4) the approval documents or acceptance opinions of the planning, public security and fire protection, environmental protection, urban construction archives and other departments on the unit project;

(5) the project quality guarantee signed by the construction unit;

⑥ Relevant documents deemed necessary by the filing authority.

(2)*** list of facilities and equipment and technical data such as installation, use and maintenance.

(3) water supply, power supply, gas supply, heating, communication, cable TV and other licensing documents.

(4) Property quality warranty documents and property operating instructions.

(5) Other materials required for inspection.

2. The elevator lifting system needs to be handed over.

(1) The construction unit needs to hand over:

Elevator safety use registration certificate

Elevator annual inspection report

Elevator inspection certificate

(2) The production unit needs to hand over the following information:

Elevator packing list

Product ex-factory certificate

Engine room shaft layout

Operation and maintenance instructions (including elevator lubrication summary table and elevator standard function table)

Schematic diagram and symbol description of elevator power supply and safety circuit

Electrical layout diagram

Component installation drawing

installation instructions

Copy of conclusion of type test report of door lock device, speed limiter, safety gear and buffer, in which speed limiter and progressive safety gear must also have a copy of debugging certificate.

(3) The installation unit needs to hand over the following information:

Self-inspection records and inspection reports

Accident records and handling reports during installation.

List of converted parts, certificate of main parts, copy of type test report, etc. , drawings and calculation data should be provided when necessary.

3. The fire control system needs to be handed over.

(1) as-built drawings, as-built data and as-built reports.

1) system diagram.

2) Architecture diagram of the system.

3) Logical description or design requirements of fire fighting equipment linkage.

4) Technical documents for equipment installation:

① Installation dimension drawing (including installation drawing of control equipment and linkage equipment, installation dimension of detector embedded parts and junction box, etc.). );

(2) the external wiring diagram of the equipment (including the tail line number of the equipment and the outgoing line of the terminal board, etc.). ).

5) Change the actual construction drawing of the design part.

6) Design change certification documents (including changes in the design requirements of fire fighting equipment linkage logic).

7) Installation acceptance sheet:

① Installation technical records (including hidden routine inspection records).

(2) Installation inspection records (including insulation resistance and grounding resistance test records.

8) Instructions for use of the equipment (including the circuit diagram and the description of allowable discharge of standby power supply).

(2) System inspection report, certificate and related materials

Weak current system needs to be handed over.

(1) Drawing design description;

(2) Schematic diagram of weak current system;

(3) wiring diagram of weak current system;

(4) bitmap of monitoring points of security technology prevention system;

(5) Construction pipeline diagram of weak current system;

(6) Acceptance data of concealed works;

(7) Test records of single equipment;

(8) System debugging report and operation record.