Detailed explanation of home improvement construction sequence

One thing that must be done in the preliminary design is to measure your room in detail, which mainly includes: defining the area involved in the decoration process, especially the tile area, wall paint area, wallpaper area and floor area; Identify the main wall dimensions, especially the wall dimensions that need to be designed for furniture in the future. By the way, don't forget to go to the property to go through the construction procedures and pay the decoration deposit before starting work.

Demolition and transformation of main body

When entering the construction stage, the main body demolition is the first project, which mainly includes wall demolition, wall building, wall skin, plastic steel window replacement and so on. To put it bluntly, the main body demolition is to put up the framework of the construction site first.

Hydropower transformation

Before the water circuit reform, the main structure should be basically completed. Between hydropower transformation and main demolition, the first test of the cabinet should also be carried out. The so-called initial measurement of cabinets has no actual content, because the walls and floors have not been treated, and it is impossible for cabinet designers to give specific design dimensions, but only put forward some relevant suggestions on the positions of water inlets and lampblack machine sockets reserved by developers.

Woodworking craft

Woodworking, bricklayer and painter are the "three brothers" in the construction process, and the basic order of appearance is: woodworking, bricklayer (bricklayer) and painter. The basic principle of appearance is that whoever is dirty will go first. "Whoever is dirty goes first" is also one of the basic principles to determine the order of home improvement, which I will talk about later.

tiling

If the workers are busy, the foreman will usually ask the "second bricklayer" to stick bricks in the field before the "carpenter boss" finishes. This is normal, because the two do not conflict.

painter

The "Third Oil Worker" enters the site, mainly completing the basic treatment of the wall surface, painting the top coat and brushing the furniture made by the "carpenter". Students who are ready to paste wallpaper only need to let the "third oil worker" do basic treatment on the wall surface where wallpaper is planned.

Install water heaters and kitchen and bathroom ceilings.

After the wall and floor decoration is completed, you can inform the water heater to deliver and install. Water heaters are generally installed in front of the ceiling, and gas water heaters have become the current trend, generally installed in the kitchen or closed balcony. If it is an electric water heater, install it in the bathroom.