How to write the notice of the protection regulations for finished and semi-finished products on the decoration construction site?

Notice on Protection Provisions for Finished Products and Semi-finished Products on Decoration Construction Site

A, finished products, semi-finished products protection responsibilities and measures

1, responsibility

The project department will set up and invite engineers from various professional companies to set up cross-operation agreement teams to work in the same place on site, formulate construction sequence coordination methods, and focus on coordinating the protection of finished products. Because decoration is different from other majors, the protection of finished products is the most important in the later construction. If the protection is not good, the consequences will be very serious. The technical director of the project is the head of the internal finished product protection agreement group of our company, and also the main finished product of the cross-operation coordination group. Take full responsibility for finished product protection and lead the work of finished product protection team members at all levels and departments. Their specific responsibilities are:

1. 1 Responsible for the whole process of finished product collapse and report to the project team regularly;

1.2 contact other professional companies to coordinate the construction sequence and finished product protection.

1.3 has the right to propose the composition of finished product protection personnel to the project manager.

1.4 is responsible for formulating and implementing the finished product protection plan.

1.5 Other matters not covered.

2. Measures

2. 1 finished product protection measures mainly include protection, packaging, covering and sealing.

(1) "Protection" means protection in advance. For example, after the dry hanging stone wall is completed, in order to prevent the ceiling and the ground from being polluted, all the walls should be protected by plastic film paper. At traffic intersections such as doorways and corners, in order to prevent collisions, several layers of film paper or small pieces of wood should be pasted.

2 "bag" is a parcel. For example, the glass tops of stainless steel handrails and fences should be wrapped, and electrical switches, sockets and lamps should also be wrapped to prevent pollution when painting.

(3) "Covering" is a surface covering. For example, after the completion of the ground project, the surface should be covered with carpet rubber mats, and the passage position should also be covered with wooden plywood.

(4) "Sealed" means closed. For example, toilets and main stairs should be closed after construction to achieve the purpose of protection.

Second, the finished and semi-finished products maintenance measures

1. Draw the construction flow chart according to the construction procedure, and the work content and completion time are marked on the flow chart. If the type of work does not meet the process time, it is not allowed to carry out other people's construction areas. All fire water supply and drainage systems and electrical air conditioners should be tested and debugged before decoration.

2. Designate a person to be responsible for finished product protection, public security and fire fighting, and hierarchical and segmented patrol inspection. Operators enter the construction area with the permit and go through the registration formalities at the entrance. After the work is completed, the finished product protection personnel should check and find out the responsible person immediately when problems are found.

3, for the completed area, hold people accountable for keeping the key and opening the door, and no one is allowed to enter the completed room without permission.

4, after the preview of the repair project with a special license to enter.

5, unified overall product protection signs, such as hanging "wet paint" warning signs for protection.

6. Protective measures for purchasing finished products:

Do a "four inspections" before entering the site, check the specifications, varieties, quality and quantity, and do not enter the site if it is unqualified. Do a good job in site and warehouse management.

7, according to the particularity of each part, formulate detailed finished product protection measures.

8. Stairs are temporarily closed in elevator halls, bathrooms and other small areas on each floor. When necessary, special personnel will be responsible for commuting or working procedures to open the door.

9, dry hanging stone wall construction, erection of 2m high fence and warning.

10, all stainless steel stair handrails, etc. After construction, wrap it with adhesive tape or pearl film paper and affix warning signs, and then dismantle it after completion acceptance.

1 1. All water fittings, sanitary wares and lamps shall be installed and debugged in the last process, and then packaged and accepted.

12, granite floor, granite stair board, etc. After completion, it should be covered with carpet rubber mats.

13, strengthen the education of finished product protection, formulate and implement the above protection regulations, and impose a fine system on those who damage finished products.

14, all process operators need to protect the finished product of this process, so as to complete this process and receive the salary of this process.

Three, some suggestions about the use of finished products and semi-finished products

After the project is completed and delivered for use, the house use and maintenance manual should be provided in written form according to the characteristics of the project, guiding the owner how to clean, operate and use various facilities in the project, introducing the basic requirements and suggestions for regular maintenance and cleaning of all parts of the decoration project, and introducing the possible impact of the use of electromechanical equipment on the decoration products. For example, the air conditioner can't turn on the hot air for the first time, the indoor humidity is relatively high, and a large number of decorative surfaces are in a state of fine-tuning to adapt to the environment. Whether the air conditioner is used correctly for the first time will seriously affect the quality and effect of decorative surfaces. The correct way to turn on the air conditioner is to open the air for three days, gradually eliminate the indoor humidity, let the decorative materials fine-tune and expand the stress, and then rise or fall to the normal temperature range day by day. Two characteristics of air conditioning: one is to change the indoor temperature; The second is to lower the temperature. When the indoor temperature difference and humidity change, the material will expand with heat and contract with cold, destroying the splicing of fine wood products and stone products with the wall, and the stone products will bulge and the wall (non-splicing part) will crack. Problems caused by improper operation and use of equipment will seriously reduce the quality, appearance and service life of facing. The surface paint of joinery is often painted with nitrocellulose, which is sprayed once every two months, which can play a protective role, prolong the service life and maintain the matte finish effect. Don't drag light-colored stones with water during use and maintenance, because some light-colored stones are afraid of water. When cleaning, it is best to remove dirt with a clean rag and then wipe it with a long mop. Generally, granite with hardness greater than 75 degrees is true light. As long as the surface is kept clean every day and the surface smoothness is not lost, the natural patterns of granite can be fully displayed. Different materials should be decorated with different cleaning agents, and the corresponding operating specifications should be followed when using them, which will bring considerable convenience to property management.