20 1 1 year answers to practical calculation questions of property manager exam

Normal hourly wage:1500/21.75/8 = 8.62 yuan.

Overtime hourly wage: 8.62* 1.5= 12.93 yuan.

There are 8 people in a class of 2 people, and the total time required for on-the-job monitoring every month is 30*24*2(2 people in a class) = 1440 hours.

Normal working hours per person per month: 8*2 1.75 (the daily wage is calculated as 2 1.75 days) = 174 hours.

Total normal working time of 8 people: 174*8= 1392 hours.

Overtime is: 1440 hours-1392 hours =48 hours.

Overtime per capita: 48/8=6 hours.

Actual salary:1500+6 *12.93 =1577.58 yuan.

The above answers are in line with the actual situation of working in the control room. The key to this problem is that the control room should be on duty by two people as required, so it needs to be arranged according to two people * four shifts, each shift is 8 hours, that is, four shifts and three shifts.