What is fire construction audit and fire acceptance? What is the general procedure of fire control construction audit?

Fire control program flow

Party A: Construction unit

Party B: the construction unit of fire fighting project.

Party C: the construction unit of the decoration project.

1. Design: Party A shall submit to the design institute to design the fire fighting engineering drawings.

2. Budget: Party B shall make the project budget according to the fire engineering drawings.

3. Contract: Party A and Party B sign a fire control project construction contract.

4. Audit: report to the fire brigade for design audit (or online audit for filing), and Party B shall provide the audit data of fire fighting project and Party C shall provide the audit data of decoration project. If the audit is unqualified, issue < < Opinions on Fire Control Audit of Unqualified Building Projects >, Party A, Party B and Party C respectively modify the nonconformities and re-declare, and issue > (or online qualified announcement), then the construction can be started.

5. Construction: Party A, Party B and Party C shall carry out the construction according to the approved drawings, and the fire brigade shall conduct sampling inspection on Party B's fire fighting engineering materials and Party C's decoration engineering materials, and the inspection expenses shall be borne by Party A. If the sampling inspection of Party B and Party C's engineering materials fails, the inspection expenses and fines shall be borne by Party B and Party C. ..

6. Testing: After the project is completed, the testing company will test the quality of the project, and after passing the test, it will issue the < < fire control facilities inspection report > > and issue it to Party C > >, the testing fee contract. If the test is unqualified, Party A, Party B and Party C shall rectify the unqualified part and retest.

7. Acceptance: report to the fire brigade for project acceptance (or online acceptance filing). Party B shall provide the acceptance data of fire fighting project, and Party C shall provide the acceptance data of decoration project. If the acceptance is unqualified, issue < < the opinion that the fire protection acceptance of the building project is unqualified > >, Party B and Party C respectively modify the nonconformities and re-declare, and issue < < the fire protection acceptance opinion of the building project > > > (or online admission announcement). Party B and Party C hand over the project to Party A. ..

8. Commencement: After Party A has obtained the>, the non-public gathering place can be put into use. Public gathering places shall formulate fire control management systems and opening hours, and report to the fire brigade for fire control safety inspection before opening. After passing the inspection, it will be issued with the << Safety Inspection Certificate before the public gathering place is put into use >>

9. Precautions: Party A is responsible for civil works, Party B is responsible for fire fighting works and Party C is responsible for decoration works. In the process of audit, inspection and acceptance, every problem should be dealt with separately, every expense should be paid separately, and every responsibility should be borne separately.