Talking about the general progress and safeguard measures of residential building construction?

General progress plan and safeguard measures of residential building construction

The main contents of the management and control measures of the construction progress plan include: the preparation of the construction progress plan, the stage control, the main partial progress plan, the method and analysis of the control plan, the control measures of the progress plan, etc.

1 principles of schedule

According to the construction organization design, decompose the milestone plan to ensure the realization of the management objectives promised by our company to the construction unit. Combined with the overall analysis, construction method, resource allocation and the experience of similar projects in our company, our company attaches great importance to this project and determines the overall schedule of this project.

Progress control is an important guarantee for the realization of this project. Through the decomposition of various workloads and quantities, reasonable and scientific construction methods are selected, resources are effectively allocated, subcontractors are effectively coordinated and controlled, and powerful measures are formulated to ensure the implementation of the whole process control of construction progress, ensure the realization of the schedule and achieve the expected goals.

2 overall progress plan

2. 1 The planned commencement date of this project is March, 20**, and the planned completion date is February, 20XX, and the total construction period is 642 days. The specific commencement date shall be subject to the commencement order issued by the chief supervision engineer or the agreement in the contract.

2.2 Determination of General Schedule

According to the main partial project schedule, according to the organization and logical relationship of the project construction, determine the total construction schedule of this project.

3 General schedule control principle

3. 1 On the basis of the total project schedule control, determine the key points and key lines of each division and sub-project as the control focus.

3.2 According to the experience of similar projects that our company has completed, and referring to our company's comprehensive coordination ability and the budgeted number of working days, we will determine the progress plan of each subdivisional work and subdivisional work, and take it as the monitoring point of each subdivisional work and subdivisional work.

3.3 According to the planned budget expenses and the actual completed budget expenses in the project construction, and considering the actual completion of the field work tasks, observe the changes of the project situation and decide whether to speed up and postpone the progress of related subdivisional work. On this basis, the project progress of each subcontract and directly organized subcontract that affects the project progress is estimated, and the difference between the site progress and the total schedule is corrected.

3.4 The monitoring and correction of progress control adopts the front-line method to adjust, and the relationship between each work on the key line and the adjacent work is solved by adjusting the free time difference and the total time difference. The realization of various plans is ultimately guaranteed by various guarantee measures related to the progress.

4. Hierarchical control of progress

4. 1 Primary Master Plan

Express the stage objectives of various professional projects, and derive the total project duration objectives from this, form a master control plan, and provide it to the construction unit, supervision, design and general contractor. The master control plan is managed by crossing diagram and network diagram. In the construction process, with the general schedule as the control baseline and the schedule as the main line, all departments and groups prepare and implement various management plans realized by the comprehensive schedule of the project, and conduct monitoring and dynamic management during the construction process. The master schedule is one of the ways that our company promises to the construction unit to implement the contract schedule guarantee. The overall control plan will be detailed after winning the bid.

4.2 Secondary Schedule Control Plan (Stage Plan)

Based on the general schedule, the main subdivisional work is divided in a targeted way, and the work content that needs to be completed in the specific implementation of each stage is decomposed based on the division of professional stages, so as to form a stage plan, which is convenient for the arrangement, organization and implementation of the progress of each profession, so as to effectively control the progress of the project and provide it to the labor force and subcontractors when they enter the site, so that they can have a clear understanding of their working hours. At the end of each month, inform all personnel, labor subcontractors, material subcontractors and professional subcontractors of the progress of the secondary progress.

4.3 Three-level control plan (monthly progress plan)

On the basis of the secondary progress plan, the work arrangement of flow construction and cross construction will be carried out to further strengthen the scope and intensity of control. Considering the arrangement of the monthly plan, every unit involved in the project construction needs to pay attention to it, specifically control the time required for each working procedure, and fully test the time to be controlled in the specific operations of various professional subcontractors. This is the biggest point of monitoring and implementing management for each subcontractor. The key points that all departments, professional groups and professional subcontractors must abide by are the basis of optimizing dynamic management.

4.4 Auxiliary plan (weekly plan, supplementary plan and itemized control plan)

Supplementary plan: provide the construction unit with the plan for the next month on the 25th of each month, correct the deviation in the plan, make a supplementary plan for the revised plan in time, and report it to the supervisor for approval.

Sub-control plan: according to the project implementation, formulate sub-control plan. In the case of overlapping disciplines, tight construction schedule or complicated working procedures, the sub-item control plan will be adopted. When carrying out the following standard layer construction, the hourly plan of standard layer flowing water construction will be made according to the relationship between flowing water rhythm and working procedure.

Weekly plan: The weekly plan is the concrete implementation of the work plan completed by each professional team and subcontractor every week, which is implemented by the field leaders of each professional at the regular project meeting and checked at the next regular project meeting. The work completed every week and the adjustment and rectification of the work plan for next week will be notified to the construction unit and the supervisor at the regular meeting of the supervisor.

5 safeguard measures for construction progress control

The safeguard measures of construction schedule control mainly include: the responsibility allocation of construction organization and schedule, the implementation of schedule, disclosure and training, on-site scheduling, concentrating superior resources to grasp key work, strengthening professional contract management, adopting advanced technologies and methods, ensuring the supply of material resources and resisting risks. ;

6. 1 construction organization and schedule responsibility guarantee

(1) Establishing a perfect management organization is the key link to grasp the initiative of construction management, control the construction production situation and ensure the progress of the project. Perfect management organization includes time limit for a project control organization and planning control system. The organization of time limit for a project control is composed of the project manager as the main person in charge and the heads of relevant departments and offices of the project. The planning system of this project will take the plan as the main line, from which a series of plans will be derived, including schedule plan, contractor and supplier bidding plan and mobilization plan, technical support plan, material supply plan, quality inspection and control plan, safety protection plan and logistics support, which will be adjusted and rectified in time according to the actual situation, so as to form a clear, in-depth, comprehensive, dynamic tracking, effective and consistent system for schedule management.

The progress plan of each subcontractor is based on the progress plan of the general contractor, and the progress plan of this unit is put forward pertinently, which is in line with the overall image progress plan of the general contractor. When each subcontractor puts forward the progress plan, it will explain in detail the influencing factors of other disciplines, and the general contractor will coordinate and solve them. If the subcontractor can't make it clear that it will affect the implementation of the schedule, the subcontractor must report to the general contractor in time, and the general contractor will negotiate with each subcontractor to solve it.

(2) organizational security management

Whether the construction schedule control plan can be completed has a great relationship with the project management department. In the construction management of this project, the project manager, project chief engineer, project installation executive manager, construction site commander and other management personnel to be dispatched by the company are all composed of personnel with perfect knowledge system, rich experience in construction site and good personal quality. And send experienced professional engineers to focus on engineering technology, and implement penetrating management at the operational level to ensure that the project is completed on time and with good quality.

According to the actual characteristics of this project, the project manager is responsible for the whole process of construction. According to the actual situation of the project and the company's program documents, the project department compiles the management system, and each member of the project department has a clear responsibility to ensure the realization of the construction period. In the preparation of the management system, the working principles and scope of project personnel are defined, and the responsibilities, rights and interests are defined and unified.

Strict management system, according to the total time limit for a project arrangement, prepare the overall progress plan of the project, set up time limit for a project control points, and ensure the realization of the total time limit for a project.

Establish a production meeting system, arrange weekly and daily work plans, check whether the progress control points are implemented at the regular meeting under the control of the general schedule, solve existing problems, and ensure the realization of the total construction period. Summarize the construction progress and construction area of each major every day, and provide it to the construction parties and subcontractors of each major to prepare for each other and avoid conflicts.

Manage the construction progress, adjust the construction progress plan according to the site conditions, ensure the realization of the construction period, and carefully prepare the weekly progress report and next week's progress plan for the construction unit and supervision to review.

Make full use of the construction space and time, balance the construction process, implement flow operation, arrange the process reasonably, especially strengthen the development of civil working face, and scientifically organize the three-dimensional crossing operation between the construction teams of various disciplines and the designated subcontractors on the premise of ensuring quality and safety.

Be prepared for seasonal and special environment (such as indoor lighting, construction electricity, etc.). ) in advance.

6.2 Implementation, disclosure and training of progress plan

Progress plan is a plan to guide a certain stage and a necessary condition for the implementation of progress. Only when everyone knows what is going on can the plan be effectively implemented. After the subcontracting team and the labor service team directly organized enter the site, the scheme disclosure and training must be carried out.

The general schedule shall be submitted to the construction unit and the supervisor before the commencement of construction, the secondary schedule shall be strictly implemented by various professional engineers and departments, and the tertiary schedule shall be submitted before the monthly summary of the supervisor and made public at the supervision meeting. The four-level progress plan is mainly the daily work arrangement, and the training and study are carried out at the weekly meeting.

6.3 to do a good job of on-site scheduling

On-site scheduling is the core part of comprehensive utilization of various resources. On-site scheduling takes planning as the main line, and the utilization of various resources related to scheduling and implementation plan is an important aspect of schedule implementation. In the implementation of this project, the company will send experienced personnel to conduct on-site command and stay at the construction site to solve the deployment contradiction at any time. Do a good job in the distribution and comprehensive utilization of the construction site, the arrangement of the planned entry and exit of various materials, and the on-site monitoring of the labor force.

6.4 Concentrate superior resources and focus on key tasks.

After making the overall progress plan of this project, determine the key lines and comprehensively analyze all the work on all the key lines to ensure the realization of the total construction period.

In terms of resource allocation, the site manager gives priority to the process management and resource supply on key lines, and the project manager personally coordinates when necessary.

6.5 Strengthen the management of professional subcontracting

This project has many functions and complex systems, so it is very important to manage all subcontractors well, and the deployment of professional subcontracting teams should be carried out in strict accordance with the plan. When signing the contract with the subcontractor, strictly define the entry time, and set up monitoring points in strict accordance with the secondary plan, conduct dynamic monitoring and negotiate well. Specify subcontractors for the construction unit. If the content cannot be completed as required, please ask the construction unit to solve it if necessary. At the daily project meeting, all subcontractors must report the daily progress, and the general contractor should provide all possible construction conditions.

6.6 Adopt advanced technologies and methods.

In the construction of this project, the use of advanced technology and construction methods is an important guarantee to ensure the construction progress. When choosing the construction method, try to be scientific and reasonable, and adopt modern, mature and advanced technologies and construction methods:

In the process of formwork support, by grasping the section characteristics of column formwork, the adjustable column formwork is adopted, which greatly improves the construction progress. The wall part adopts shaped wooden formwork, which saves assembly time and improves concrete forming quality.

Steel bar connection adopts straight thread (diameter ≥20) and electroslag pressure welding (wall vertical steel bar diameter 16 or more) to improve the construction progress of steel bar joint.

In the process of construction, summarize various technologies and construction methods, and achieve the purpose of saving construction period through continuous innovation.

6.7 Optimize resource allocation

In the construction of the main structure, it is necessary to carry out labor competition, set a benchmark and introduce competition mechanism. Ensure that the workforce meets the construction requirements.

In the construction site, the pump machine is equipped with a boom or directly uses a car pump to improve the rate of concrete entering the site.

6.8 Coordination of foreign relations

The company will take the initiative to coordinate with local streets, police stations, transportation, sanitation, planning, labor bureau and other administrative departments, and often communicate with them to gain their support and understanding, so as to provide more convenient conditions for construction.

6.9 seasonal construction safeguard measures

Take preventive measures for seasonal construction. The main structure of this project will be constructed in rainy season at the initial stage of construction, and the structure and initial decoration stage will be constructed in rainy season in winter, and the electromechanical installation will be constructed in rainy season in winter. We will take corresponding measures at each stage.

Property service contract (model text doc version)

(ContractNo.:)

Chapter I General Provisions

Article 1 Both parties to the contract

Party A:

Address:

Owner's Committee filing receipt number:

Person in charge of the owners' committee:

Telephone: Postal Code:

Party B:

Legal representative:

Registered address:

Business license registration number: qualification grade:

Enterprise qualification certificate number:

Telephone: Postal Code:

In accordance with the Regulations of Shaanxi Province on Property Management and other relevant laws and regulations, Party A and Party B enter into this contract on the basis of voluntariness, equality and consensus on providing property management services for (property name) (hereinafter referred to as the property) at the owners' meeting.