Construction organization design of weak current engineering

Prepared by: XXXXXXXX Co., Ltd.

Review:

Compile:

Date of Compilation: Year Month Day

catalogue

Chapter I Project Overview and Compilation Basis

1. 1 project overview

1.2 compilation instructions

1.3 compilation basis

Chapter II Overview of Implementation of Construction Organization and Management

2. 1 construction management organization structure

2.2 Introduction to the responsibilities of the main personnel of the project implementation agency

2.3 Construction coordination work

2.4 Resource supply plan for project implementation

2.5 Emergency handling strategies in the process of project implementation

2.6 The main contents of construction management

Chapter III Engineering Implementation Steps

3. 1 Deepening design and engineering construction drawing

3.2 submission, procurement and mobilization management of equipment and materials

3.3 Construction Steps and Methods

3.4 Inspection and testing

3.5 Quality Assurance Plan

3.6 Safety production plan

3.7 Construction progress control plan

Chapter IV Analysis of Construction Difficulties and Key Points and Countermeasures.

Chapter V Important Guarantee Measures in the Process of Construction Implementation

5. 1 Article 12 Economy measures

5.2 civilized and safe construction guarantee measures

5.3 Fire control measures on the construction site

5.4 Protection measures for finished and semi-finished products on site

5.5 Main measures of quality management in construction process

5.6 Hydropower measures for site construction

5.7 time limit for a project guarantee measures

Chapter VI Project Warranty Commitment and Measures

Submission Plan and Record Form of Weak Current Equipment/Materials

Chapter I Project Overview and Compilation Basis

1.3. 1 project overview

XXXXXX, located at the junction of the entrance and exit lanes of XXXXXX, is one of the development projects of XXXXXX, adjacent to the completed XXXXXX by the owner. Its residential area includes office building, conference center, dining building, underground garage, electromechanical room and civil air defense part.

The construction land area of XXXX is about164,500 square meters. The master plan is a comprehensive development project, which is mainly divided into three areas; 1 area includes a two-story and three-story XXXX office building and a single-story XXXX restaurant building; The second area includes a four-story marketing building, a five-story management XXXX building and a two-story staff canteen building. The third zone consists of four single-storey conference centers. The staff canteen building, marketing department and XXXX building in the second district are located in one basement, while the two XXXX office buildings in the first district are also located in another basement. The building area of XXXX office building and XXXX canteen in Area 1 is about 15730 square meters, the basement of XXXX office building is about 9990 square meters, the building area of marketing department and operation XXXX building in Area 2 is about 386 10 square meters, and the building area of staff canteen is about1400 square meters. The construction area of the marketing department and the basement where XXXX is operated is about 36,560 square meters, the construction area of the three-zone conference center is about 3 130 square meters, and other ancillary buildings are about 4,490 square meters. The total construction area is about119,910 square meter.

The architect of this project is XXXXXX Co., Ltd., the electromechanical engineer is XXXXXX Co., Ltd., the local design unit is XXXXXX Co., Ltd., the supervision engineer is XXXXXX Co., Ltd., and the quantity surveyor is XXXXXX Co., Ltd.

The weak current subcontracting project of this project includes the design, supply, installation, debugging and warranty of the weak current system devices of the above development projects according to the subcontract conditions, general contract conditions (involving designated subcontractors), quantity specifications and subcontracting drawings; Including but not limited to building equipment automatic control system, building intelligent management platform system, integrated wiring system (with outdoor wiring), public antenna system, intelligent security monitoring system (including burglar alarm, patrol, closed-circuit television monitoring, access control and employee card device), multimedia system integration, garage management system, audio-visual and dimming system (but excluding audio-visual and dimming equipment itself), weak current control center and weak current computer room decoration.

According to the document, the total construction period of this project is 500 calendar days, which requires weak current.

Subcontracting projects must be completed within this time limit.

The quantities of this project are divided into the following systems:

1, BAS system-it will monitor and manage 18 air conditioners, fresh fans,1blowers, 178 power distribution lines, 4 freezers, 23 butterfly valves and other water, electricity and gas equipment in the whole base, totaling 330.

3.PDS system-This system provides a flexible integrated wiring network, which can connect and support voice, broadband telecommunication network, computer data and high-speed image signals. The system uses the third type unshielded twisted pair and single mode/multimode optical cable as the main transmission media respectively. The system is divided into two parts. The voice and digital communication signals outside the building are introduced into the network computer room, telephone computer room and experimental computer room respectively through the telecom incoming room, and 3079 voice terminal interfaces and 3808 data terminal interfaces are introduced through the voice distribution system and optical fiber data distribution system respectively.

4.CCTV system —— The first area of ——XXXX is equipped with 5 16 channel video distribution amplifiers, 13 4-picture processors, 2 16 picture processors (perimeter cameras) and 15 time-delay video recorders. The video matrix control system has 96 inputs, 32 outputs, a 1 keyboard and a CPU.

Alarm input interface 1 set

Alarm output interface 1 set

20-inch color monitors 16 sets, TV wall 1 set, console 14-inch color monitors 2 sets.

Monitoring system software operation 1 computer and 1 printer.

1 set of UPS (provided by the computer room) power supply and system power distribution equipment.

A set of TV screen display wall

1 main console

1 Monitoring System Management Workstation

Electronic map alarm software for computer operation (alarm and patrol workstation)

In the second/third section of XXXX, there are 6 16 video distribution amplifiers, 18 4 picture processors, 2 16 picture processors (peripheral cameras) and 20 time-lapse video recorders. The video matrix control system has 196 inputs, 32 outputs and 1 set of keyboards.

Alarm input interface 1 set

Alarm output interface 1 set

20-inch color monitors 16 sets, TV wall 1 set, console 14-inch color monitors 2 sets.

There are 1 monitor for 9 digital video recorders and 1 video printer.

Monitoring system software operation 1 computer and 1 printer.

1 set of UPS (provided by the computer room) power supply and system power distribution equipment.

2 sets of equipment installation cabinets and 2 sets of wiring cabinets.

A set of TV screen display wall

1 main console

1 Monitoring System Management Workstation

Electronic map alarm software for computer operation (access control, alarm, patrol workstation)

There are 167 cameras in various important positions of XXXX.

5.ACS system includes burglar alarm system, smart card access control system and patrol system. 189 door magnets and 79 patrol points are set in all important positions in the base, and the HID card is uniformly used as patrol card, which is managed by the one-card server.

There are 7 1 access points in the whole base, and the HID card is used as the employee card and managed by the all-in-one card server.

6.TCS system-access control management, export charge management system (according to the owner's opinion) and image recognition function are implemented throughout XXXX. Temporary parking is managed by paper card and long-term parking is managed by HID card. It is designed as seven sets of two-way braking systems.

7.CATV system-cable TV programs are received from cable TV signals in the early stage of XXXX, and then enter the office building through cable TV trunk lines. After being amplified by the amplifier, the signal is divided into two paths. One path is distributed to 34 terminals on the first to fourth floors of the office building, and the other path enters the canteen through the trunk line. After being amplified by the amplifier, it is distributed to 8 terminals, and the branch distributor reaches 42 terminals. The system adopts two-way channel equipment.

8. Decoration of weak current computer room-The decoration scope includes a fire control and weak current control center (69M2), a network computer room (15M2) and 12 weak current (network) computer rooms (* * * *176m2); ) is located in XXXX 1 area; A fire control and weak current control center (66M2), a network computer room (49M2) and seventeen weak current (network) computer rooms (* * * * * 231m2); ) is located in the second district of XXXX; Four weak current rooms (***24M2) located in XXXX Zone III, with a total decoration area of 650M2. Decoration contents include sky, ground, wall, lighting, grounding, weak current trunking, commercial power distribution, UPS distribution, etc. Two fire control and weak current control centers are respectively equipped with three split ceiling air conditioners and a weak current system console, and two network rooms are respectively equipped with an air-cooled precision air conditioning.

1.2 compilation instructions

The organization and implementation of engineering construction is the key to the success or failure of the whole project. Only by making a feasible scheme before the project and implementing it in the project to realize high-quality safe production can we provide users with a high-quality system that meets the current needs, and should provide the greatest convenience and save money as much as possible for future maintenance and upgrading.

XXXX believes that a complete engineering process consists of design, business, construction, commissioning, acceptance, completion and maintenance. Therefore, a complete project organization and implementation plan should fully consider the above links, not only to arrange the progress, quality and safety of construction links, commissioning links and acceptance links, but also to organize the management of design links, business links and completion links, formulate the progress plan and promotion, quality management and control of each link, and finally arrange and implement the maintenance plan.

The project implementation of weak current system is a comprehensive and coordinated management work, which needs the cooperation of civil engineering, hydropower, HVAC, air conditioning and decoration, and its core is effective management. As the engineering design and project construction manager of positioning weak current system, XXXXX Company has ISO900 1 certification, introduced the international advanced Six Sigma management concept, adhered to the enterprise concept of "people-oriented, * * * common development", and trained and introduced a group of mature technical designers and project managers after years of practical engineering training. At the same time, we will continue to explore the project implementation mode, set up a "joint fleet" with overall operation, and realize the transformation from the practical engineering mode designed and installed by our company to the intelligent mode of continuously strengthening our own technical strength, quality assurance system and export project management mode, so as to control the project cost, flexibly integrate the organization, and implement the management concept of XXXX in the complete weak current system project.

XXXX Company's mission: to constantly exceed the growing needs of customers.

1.3 compilation basis

As the basis for guiding the construction of XXXX weak current construction subcontracting project, this construction organization design fully considers the construction period, quality objectives, project management organization and labor organization, construction progress control, mechanical equipment and turnover materials, main technical schemes and measures, safety guarantee measures, civilized construction, cost reduction, promotion of new technology maintenance management and many other factors, which highlights its scientificity and feasibility and ensures the smooth progress of the project.

1) XXXX weak current design drawings and bidding documents

2) Design Standard for Intelligent Buildings GB/T 503 14-2000

3) Code for Electrical Design of Civil Buildings (JJ/T 16-92)

4) Code for Electrical Design of Civil Buildings (JJ/T 16-92)

5) Detailed Manual of Code for Electrical Design of Civil Buildings (JJ/T 16-92)

6) Code for Engineering Design of Integrated Wiring System for Buildings and Buildings GB/T 503 1 1-2000.

7) Code for Acceptance of Building and Building Complex Integrated Wiring System Engineering GB/T 503 12-2000

8) Revised Edition of Code for Engineering Design of Building and Building Integrated Wiring System CECS 72: 97

9) Code for Communication Design of Industrial Enterprises GBJ42-8 1

10) telecommunication wiring system standard for commercial buildings. Part1; General requirements are ansi/TIA/EIA-568-B.1-2001.4.

Standard for telecommunication wiring system in commercial buildings. The third part; Optical fiber wiring department

Parts standard ansi/TIA/EIA-568-B.1-2000.3.

12) telecommunication channel and space standard for commercial buildings TIA/EIA-569-A

13) telecommunication infrastructure management standard for commercial buildings TIA/EIA-606-A-200 1

14) Code for Construction and Acceptance of Low-voltage Electrical Apparatus in Electrical Equipment Installation Project (GB50254-96)

15) Code for Construction and Acceptance of Electrical Equipment Installation Engineering 1KV and below (GB50258-96)

16) Code for Construction and Acceptance of Lighting Devices in Electrical Equipment Installation Project (GB50259-96)

17) Code for Construction and Acceptance of Ventilation and Air Conditioning Engineering (GB50243-97)

18) Code for Construction and Acceptance of Storage Batteries in Electrical Device Installation Project (GB50 172-92)

19) code for construction and acceptance of architectural decoration engineering JGJ 73-9 1

20) Code for Lightning Protection Design of Buildings (GB50057-94)

Code for Design of Automatic Fire Alarm System GB50 1 16-98.

22) Code for Fire Protection Design of High-rise Civil Buildings (GB50045-95)

23) Technical Specification for CATV System Engineering (GB50200-94)

24) Code for Design of Antenna Television System in Industrial Enterprises BGJ 120-88

25) Code for Design of Satellite Radio and Television Earth Stations GJ4 1-89

26) Code for Design of Antenna Television System in Industrial Enterprises BGJ 120-88

27) Technical Specification for CATV Broadcasting GB/T 106-92

28)30 MHz- 1 GHz cable distribution system for TV and sound signals GB/T65 10- 1996.

29) Fire Protection Standard for Architectural Design of Radio and Television Engineering GYJ33-88

30) Technical Code for Civil Closed-circuit Surveillance Television System Engineering (GB50 198-94)

3 1) safety prevention engineering procedures and requirements GA/T 75-94

32) Code for Design of Electronic Computer Room (GB50 174-93)

33) Code for Design of Low-voltage Distribution Equipment and Lines GBJ54-83

34) Code for Design of Power Supply and Distribution System GB50052-95

35) Technical conditions of computer site GB2887-89

36) Computer site safety requirements GB936 1-88

37) Technical Specification for Computer Software Engineering in Construction Field JGJ-/T90-92

38) Integrated wiring standards, such as EIA/TIA568, 569, 606, 607 and TSB72.

39) computer network IEEE802.3, IEEE802.3z, IEEE802.5, ANSIFDDI, TPDDI, FDDI, ATM and other standards.

40) Relevant regulations of Shenzhen Municipality

4 1) related industry standards

42) Guidelines and standards for internal procedures of XXXX Company

Chapter II Overview of Implementation of Construction Organization and Management

2. 1 project management organization structure

XXXX will adopt a special management mechanism for the project implementation management of key projects (such as this project): two levels of direct management of key project headquarters and on-site project management department.

The key project headquarters was specially established on the basis that the projects undertaken were included in the national and local key projects. It is the highest responsible department for major projects, responsible for signing contracts and orders, formulating all legal documents related to projects, and supervising the implementation of contracts and the progress of projects. The key project headquarters fully supports the work of the on-site project management department, accepts complaints from the construction unit and subcontractors, uniformly allocates various resources of XXXX, coordinates the actions of various departments, and establishes a rapid response and emergency handling mechanism to ensure the smooth completion of major projects by the on-site project management department. The project commander-in-chief shall be the engineering director of China Department of XXXX Company.

XXXX company has an engineering department, which is directly led by the project commander. Responsible for the arrangement of technical force during the project implementation, timely solve various technical problems encountered in the project implementation, arrange the procurement and supply of overseas goods, ensure the quality and delivery date of goods, and allocate 5 people.

In addition, the headquarters has set up a hotline, which is managed by the secretary of the headquarters.

On-site project management department is responsible for the specific implementation of the project, coordinating the relationship between the parties on site, managing the project site, performing project management functions on behalf of the company, solving various problems encountered in the project in time, arranging manpower, financial resources and material resources, promoting the project progress, organizing safe and civilized production, ensuring the project quality and completing the project on schedule. On-site project management department is the authorized representative of XXXX Company at the construction site; Considering that in the organization and management of XXXX project, professional companies in Hong Kong mainly carry out project management according to international practices, our company decided to arrange a senior project manager who has special experience in technology and management and has cooperated with this project as the on-site project manager to comprehensively manage the project progress, quality, safe and civilized production, and manage the project quality, safe and civilized production, commodity procurement and supply. Logistics warehouse management, data and documents, as well as administrative affairs, and focus on dealing with all kinds of affairs in line with international management; Set up deputy project manager and deputy project manager to assist the project manager to promote the organization and implementation of the whole project and complete the weak current subcontracting project with high quality as scheduled.

Under the direct leadership of the project manager, there is an administrative management group, which is responsible for the daily management of the project department, arranging and recording various meetings, sending and receiving documents, managing the current capital flow, handling the business related to project funds, and filling in the project diary; Two people, one is in charge of secretarial work and the other is in charge of meeting and financial work.

There is a quality and safety production team under the direct leadership of the project manager and the responsibility of the chief engineer to manage the design quality, construction quality, safe and civilized production in the process of project implementation, and handle various examination and approval procedures and acceptance procedures; There are three personnel, one is responsible for communicating with the general contractor and going through the formalities of examination and approval, one is responsible for checking the construction quality and the other is responsible for the construction safety.

Under the direct leadership of the project manager and the management of the deputy project manager, there is a commodity procurement team responsible for the procurement and supply management of various materials, equipment and tools.

There is a logistics warehouse management team, managed by the deputy project manager, to manage the receipt and delivery of goods, establish commodity files and record their entry and exit; There are 2 people on duty in turn.

There is a document management room, which is directly managed by the deputy project manager. Assign special personnel to classify and keep all kinds of specifications, design documents, engineering documents, commodity lists, commodity files and completion data, fill in the engineering records, and make a quota of 1 person.

There is a drawing group, managed by the deputy project manager, responsible for deepening the production of design drawings, weak current comprehensive drawings and project completion drawings, with a capacity of 2~3 people.