What is the order of residential decoration?

1

Pre-design: mainly according to your living habits, make a detailed measurement of your room. Don't be lazy, you'd better measure yourself. The measurement mainly includes: defining the area involved in the decoration process. Especially tile area, wall paint area, wallpaper area and floor area; Determine the main wall size. Especially it is necessary to design the wall size of furniture in the future.

2

Demolition and transformation of the main body: when entering the construction stage, the demolition and transformation of the main body is the first project, which mainly includes wall demolition, wall building, wall covering, heating removal and replacement of plastic steel windows. To put it bluntly, the main body demolition is to put up the framework of the construction site first.

three

Hydropower transformation: before the water circuit transformation, the main structure should be basically completed. Some students may know that it is the first time to measure the cabinet between hydropower transformation and main body demolition. The so-called initial measurement of cabinets has no actual content, because the walls and floors have not been treated, and it is impossible for cabinet designers to give specific design dimensions, but only put forward some relevant suggestions on the positions of water inlets and lampblack machine sockets reserved by developers. It mainly includes: whether the position of the lampblack machine socket affects the installation of the lampblack machine in the future; See if the location of the water meter is appropriate; See if the location of the water inlet is convenient for installing the sink in the future. For the first measurement of cabinets, students with a little experience can do it by themselves. After the waterway reconstruction is completed, it is best to waterproof the bathroom immediately. The kitchen generally doesn't need to be waterproof.

four

Woodworking: Woodworking, bricklayer and oiler are the "three brothers" in the construction process, and the basic order of appearance is: wood-tile-oil. The basic entry principle is-whoever is dirty goes first. "Who gets dirty first" is also one of the basic principles to determine the order of home improvement, which I will mention later. In fact, carpentry, such as vertical pipe, decorative ceiling and plaster line, can also be considered as the fine link of main demolition and reconstruction in a sense, which does not conflict with the water circuit reconstruction itself, and sometimes needs some cooperation.

five

Tiling: In the process of "bricklayer's second child" operation, it also involves the installation of the following three links: the installation of threshold stone and the installation of marble window sill. The installation of the threshold can be completed together with the floor tile laying, or after the floor tile laying. Generally, after the window cover is completed, the marble installation union prepares glass glue and seals the marble and window cover with glass glue. Install the floor drain. Floor drain is the first hardware in home decoration, because it should be installed with floor tiles. Therefore, students should buy a floor drain as soon as possible when they start shopping for building materials. Installation of range hood. The range hood is the first appearance of household appliances. After the kitchen walls and tiles are paved, you can consider installing a range hood. "The second child of the bricklayer" left the scene. At this time, you can measure the cupboard for the second time. Accurately speaking, after the kitchen wall tiles are pasted and the range hood is installed, the second measurement of the cabinet can be carried out.

six

Paint the wall: The "Third Oil Worker" enters the site, mainly to finish the basic treatment of the wall, paint the top coat, and paint the furniture made by the "carpenter boss". Students who are ready to paste wallpaper only need to let the "third oil worker" do basic treatment on the wall surface where wallpaper is planned. As for whether I left my coat for the last time, I personally don't think it is necessary to take this question too seriously. From my experience in decoration, it is of little significance to leave the top coat, because the operation behind is not dirtier than painting.

seven

Ceiling of kitchen and bathroom: As an installation link, the ceiling of cabinet takes the lead, or it continues the "packaging" of home. At the same time as the ceiling of the kitchen and bathroom, the moisture-proof ceiling lamp and exhaust fan (Yuba) of the kitchen and bathroom should have been bought. It is best for students to install ceiling lamps and exhaust fans (Yuba) in the kitchen and bathroom at the same time, otherwise thread ends and holes will be left.

eight

Kitchen cabinet installation: after the ceiling is completed, you can make an appointment to install the cabinet at home. If it goes well, it can be finished in one day. At the same time, there are sinks (excluding water fittings) and gas stoves. It is best to coordinate the property to turn on the gas before the cabinet is installed, because the gas stove needs to be tested after installation.

nine

Wooden door installation: the second day after the cabinet was installed, after the wooden door measurement was completed more than a month ago, it can probably be installed now. If it goes well, it will be a day. At the same time, hinges, door locks and floor drains should be installed. Students should prepare related hardware in advance. If you want the wooden door manufacturer to install the window cover and pass it, you should also measure it when the wooden door manufacturer measures it, and install it at the same time on the day when the wooden door is installed. At the same time, you should consider putting the installation time of marble windowsill backward after the window cover is installed. Remarks: The production cycle of wooden doors is generally one month. Therefore, in order to make the construction period closely connected, wooden door manufacturers should go to the door to measure the size of the door opening as soon as possible after the main body is demolished and rebuilt. Regarding the treatment of the doorway, it should be noted that if the height of the doorway at home is inconsistent, workers need to treat it at the same height-beautiful.

10

Floor installation: the floor can be installed the next day after the wooden door is installed. If all goes well, it will take a day. Pay attention to the following problems when installing the floor: 1. Before installing the floor, it is best to let the manufacturer visit the site to investigate whether the floor needs leveling or partial leveling. Some decoration companies or teams will advise students to level the ground or partially level it, subject to the actual investigation of the floor manufacturer; 2. Before the floor is installed, the floor paved at home should be cleaned to ensure the floor is dry, so do not use water during the cleaning process. 3. When installing the floor, if possible, the floor must be cut in the corridor. The forum also discussed this issue before, and some students thought it was immoral to cut the floor pollution area in the corridor. My idea is to clean up after completion, which doesn't matter. Cutting the floor indoors has serious pollution to the wall surface, and there is also the cutting of artificial stone countertops in cabinets. I believe all the students who have been decorated have some experience.

1 1

Wallpaper laying: On the second day of floor installation, when the house is ready, you can make an appointment to lay wallpaper. If it goes well, it will take a day. If possible, the floor should be protected on the day of wallpaper pasting; It doesn't matter if there are no conditions, and it's no problem to leave the wallpaper glue left on the floor to Pioneer for cleaning. Before pasting the wallpaper, try to make the wall "nothing".

12

Radiator installation: On the second day after wallpaper pasting, students who have replaced or removed the radiator can hang the radiator on the wall in a down-to-earth manner. It's also a day. Wooden door-floor-wallpaper-radiator, which is recognized as the correct installation sequence. Install the wooden door first to ensure that the skirting line of the floor can be closely connected with the door cover of the wooden door; After the wallpaper was installed, it was mainly because the floor was dirty and dusty, which seriously polluted the wallpaper. Here I use the principle of "whoever is dirty first" again. Finally, install the radiator, because the radiator can only be installed after the wallpaper is laid on the wall.

13

Installation of switch sockets: Students should have a detailed understanding or record of the number and location of switch sockets in various natural rooms at home, especially those who paste wallpaper. Sometimes wallpaper workers are irresponsible, and the wallpaper is laid at once, and you don't need wallpaper knife to mark the position of your switch socket. So students still need to know for themselves.

14

Installation of lamps: there is nothing to say about installing lamps. After the lights were installed, the house lit up, saying goodbye to the dazzling light of 100 watt incandescent bulbs during decoration-it felt really good.

15

Installation of hardware and sanitary ware: all pipe fittings, bathroom fittings, toilets, clothes hangers, etc. Everything I bought before was packed together. After the "big things" in front are installed, the home is still very "cold". When the lamps and hardware sanitary ware are installed, the home will be "alive", really "alive". It is no exaggeration to say that it will be beautiful to open the dragon water for the first time and watch the water flow out. Convenient, it's the first time to install a new toilet at home, and I always feel a sense of accomplishment. By the way, I gave it a good name-"Virgo".

16

Installation of curtain rod: The installation of curtain rod marks the basic end of home improvement.

17

Pioneer cleaning: Do not install curtains before pioneer cleaning. Remember to remind everyone in the post of "explaining curtains" When cleaning, don't have furniture and unnecessary household appliances at home, leave as many "planes" as possible, so that the cleaning can be thorough.

18

Furniture entering the market: As for the purchase time of furniture, my suggestion is that the water circuit should be renovated at the earliest, so that you can get a general understanding of the basic size range of furniture. Therefore, some students have been eager to book all the furniture before the decoration, and personally feel that it is unnecessary.

19

Home appliances enter the site: at this time, home appliances should enter the site, and the installed ones should be installed and ready to move in!

20

Home decoration: Home decoration is the last step of home improvement, and it has changed from decoration to decoration, including the installation of curtains. As for buying curtains, it is best to book furniture first to avoid style conflict. Home accessories also include buying some green plants, hanging murals, decorative handicrafts and so on ... in short, you can play freely after staying.

The above is for reference only. . . .