Is it necessary to carry out the main demolition and water and electricity when decorating a house? I bought a rough house of Evergrande, and the apartment type is the same as the finely decorated one

Is it necessary to carry out the main demolition and water and electricity when decorating a house? I bought a rough house of Evergrande, and the apartment type is the same as the finely decorated one. First, the steps of decoration

1 preliminary design -2 main body demolition -3 hydropower renovation -4 carpentry -5 tiling -6 wall painting -7 kitchen and bathroom ceiling -8 cabinet installation -9 wooden door installation-10 floor installation-1wallpaper laying -65448 5 hardware and sanitary ware installation-/kloc-

(1) Pre-design

The same is construction. The difference between people and bees is that the construction of bees is a reflection of instinct, and before the construction, people will first form ideas and frameworks in their minds. Therefore, if we compare home improvement to a battle, then the preliminary design of home improvement is the "battle plan" of this battle and the "soul bond" of home improvement.

In the early design, friends must do one thing, that is, make a detailed measurement of their rooms. Don't be lazy, you'd better measure yourself. The measurement contents mainly include:

1. Define the areas involved in the renovation process. Especially tile area, wall paint area, wallpaper area and floor area;

2, clear the bearing wall size. Especially it is necessary to design the wall size of furniture in the future.

(two) the main body is removed or changed.

When entering the construction stage, the main body removal is the first project, which mainly includes wall removal, wall building, wall skin removal, heating removal, plastic steel window replacement and so on. To put it bluntly, the main body demolition is to put up the framework of the construction site first.

(3) Hydropower transformation

Before the water circuit reform, the main structure should be basically completed. Between hydropower transformation and main demolition, some suggestions are put forward on the location of water inlet and socket on the range hood reserved by the developer. Mainly includes:

1, to see whether the position of the lampblack machine socket affects the installation of lampblack machine in the future;

2. See if the location of the water meter is appropriate;

3. See if the location of the water inlet is convenient for installing the sink in the future.

The first measurement of cabinets can be done by experienced friends themselves. After the waterway reconstruction is completed, it is best to waterproof the bathroom immediately. The kitchen generally doesn't need to be waterproof.

(4) Woodworking

Woodworking, bricklayer and oiler are the "three brothers" in the construction process, and the basic order of appearance is: wood-tile-oil. The basic entry principle is-whoever is dirty goes first. "Who gets dirty first" is also one of the basic principles to determine the order of home improvement.

(5) Tiling

During the operation of "bricklayer's second child", the installation of the following three links is also involved:

1. Installation of lintels and marble windowsills. The installation of the threshold can be completed together with the floor tile laying, or after the floor tile laying. Generally, after the window cover is completed, the marble installation union prepares glass glue and seals the marble and window cover with glass glue.

2. Install the floor drain. Floor drain is the first hardware in home decoration, because it should be installed with floor tiles. Therefore, when friends start to buy building materials, they should buy floor drains as soon as possible.

3. Installation of range hood. The range hood is the first appearance of household appliances. After the kitchen walls and tiles are paved, you can consider installing a range hood.

When the "second bricklayer" left the scene, it was time to measure the cupboard for the second time. Accurately speaking, after the kitchen wall tiles are pasted and the range hood is installed, it is time to measure the cabinet for the second time.

(6) Paint the wall

The "Third Oil Worker" enters the site, mainly completing the basic treatment of the wall surface, painting the top coat and brushing the furniture made by the "carpenter". Friends who are going to wallpaper, let the "third oil worker" do the basic treatment on the wall that is going to wallpaper.

(7) Ceiling of kitchen and bathroom

As an installation link, the cabinet ceiling is still continuing the "packaging" of the home. At the same time as the ceiling of the kitchen and bathroom, the moisture-proof ceiling lamp and exhaust fan (Yuba) of the kitchen and bathroom should have been bought. Friends had better install ceiling lamps and exhaust fans (Yuba) in the kitchen and bathroom at the same time, otherwise thread ends and holes will be left.

(8) Install the kitchen cabinet

After the ceiling is completed, you can make an appointment to install the cabinet at home. If it goes well, it can be finished in one day. At the same time, there are sinks (excluding water fittings) and gas stoves. It is best to coordinate the property to turn on the gas before the cabinet is installed, because the gas stove needs to be tested after installation.

Many friends choose waterproof gypsum board with waterproof paint as kitchen and bathroom ceiling. The quotation of decoration team is generally above 120 yuan per square meter, which is more expensive than ordinary aluminum gusset plate and PVC gusset plate ceiling. The gypsum board ceiling looks flat visually, but once there is a problem with the top water pipe in the future, or the upstairs water leaks and needs to be repaired downstairs, the gypsum board ceiling will be removed as a whole, which is much more troublesome than the gusset ceiling. Therefore, everyone should be careful when choosing gypsum board ceiling.

(9) Wooden door installation

The second day after the cabinet was installed, as early as more than a month ago, after the wooden door was measured, it can be installed now. If it goes well, it will be a day. At the same time, hinges, door locks and floor drains should be installed. Related hardware should be prepared in advance.

If you want the wooden door manufacturer to install the window cover and pass it, you should also measure it when the wooden door manufacturer measures it, and install it at the same time on the day when the wooden door is installed. At the same time, you should consider putting the installation time of marble windowsill backward after the window cover is installed. Remarks: The production cycle of wooden doors is generally one month. Therefore, in order to make the construction period closely connected, wooden door manufacturers should go to the door to measure the size of the door opening as soon as possible after the main body is demolished and rebuilt. Regarding the treatment of the doorway, it should be noted that if the height of the doorway at home is inconsistent, workers need to treat it at the same height-beautiful.

(10) Floor installation

The floor can be installed the day after the wooden door is installed. If all goes well, it will take a day. The floor installation needs to pay attention to the following issues:

1. Before the floor is installed, it is best to let the manufacturer come to the door to investigate whether the ground needs leveling or partial leveling. Some decoration companies or teams will advise students to level the ground or partially level it, subject to the actual investigation of the floor manufacturer;

2. Before the floor is installed, the floor paved at home should be cleaned to ensure the floor is dry, so do not use water during the cleaning process.

3. When installing the floor, if possible, the floor must be cut in the corridor.

(1 1) Laying wallpaper

The next day after the floor is installed, the home is ready, and you can make an appointment to paste wallpaper. If it goes well, the same day will do. If possible, the floor should be protected on the day of wallpaper pasting; It doesn't matter if there are no conditions, and it's no problem to leave the wallpaper glue left on the floor to Pioneer for cleaning. Before pasting the wallpaper, try to make the wall "nothing".

(12) Installation of radiator

The day after the wallpaper is laid, friends who replace or remove the radiator can hang the radiator on the wall in a down-to-earth manner. It's also a day.

Wooden door-floor-wallpaper-radiator, which is recognized as the correct installation sequence. Install the wooden door first to ensure that the skirting line of the floor can be closely connected with the door cover of the wooden door; After the wallpaper was installed, it was mainly because the floor was dirty and dusty, which seriously polluted the wallpaper. Here, the principle of "whoever is dirty first" mentioned above is used again. Finally, install the radiator, because the radiator can only be installed after the wallpaper is laid on the wall.

The gradual renovation process is also designed under various constraints and restrictions. Occasionally there are exceptions. For example, the Holtz door needs to be fitted with the floor first and then the door, but this exception is rare in the decoration process.

(13) switch socket installation

(14) Installation of lamps and lanterns

Install the lights. There is nothing to say. After the lights were installed, the house lit up, saying goodbye to the dazzling light of 100 watt incandescent bulbs during decoration-it felt really good.

(15) Installation of Hardware Sanitary Ware

Before buying pipe fittings, bathroom fittings, toilets, clothes hangers, etc. , are all installed.

After the "big things" in front are installed, the home is still very "cold". When the lamps and hardware sanitary ware are installed, the home will be "alive", really "alive". It is no exaggeration to say that it will be beautiful to open the dragon water for the first time and watch the water flow out. Convenient, the toilet newly installed at home for the first time will have a great sense of accomplishment and give it a good name-"Virgo".

(16) Installation of curtain rod

The installation of curtain rod marks the basic end of home improvement.

(17) development and cleaning

Don't install curtains before the start-up cleaning, remember to remind everyone in the post of "explaining curtains" When cleaning, don't have furniture and unnecessary household appliances at home, leave as many "planes" as possible, so that the cleaning can be thorough.

(18) Furniture comes into play

As for the purchase time of furniture, it should be after the completion of water circuit decoration at the earliest, so as to get a general understanding of the basic size range of furniture. Therefore, some friends have been eager to book all the furniture before the renovation, and personally feel that it is not necessary.

(19) Home appliances enter the site

At this time, it's time for home appliances to enter the market. It's time to install and prepare to move in!

(20) Home accessories

Home decoration, the last step of home improvement, has changed from decoration to decoration, including the installation of curtains. As for buying curtains, it is best to book furniture first to avoid style conflict. Home accessories also include buying some green plants, hanging murals, decorative handicrafts and so on ... in short, you can play freely after staying.