Job Recruitment Website - Property management - Does the community without completion acceptance record have the right to charge property fees?
Does the community without completion acceptance record have the right to charge property fees?
1. According to Article 27 of People's Republic of China (PRC) Urban Real Estate Management Law:
Article 27 The design and construction of real estate development projects must conform to the relevant national standards and norms.
Real estate development projects can only be delivered after completion and acceptance.
2. According to Article 6 1 of the Building Law of People's Republic of China (PRC):
Article 61 A construction project delivered for completion acceptance must meet the prescribed quality standards of construction projects, have complete technical and economic data of the project, sign the project warranty, and meet other completion conditions stipulated by the state.
Only after the construction project is completed and accepted can it be delivered for use; Without acceptance or unqualified acceptance, it shall not be delivered for use.
3. According to Article 17 of the State Council's Regulations on Urban Real Estate Development and Management:
Seventeenth real estate development projects are completed and can only be delivered after passing the acceptance; Without acceptance or unqualified acceptance, it shall not be delivered for use.
After the completion of a real estate development project, the real estate development enterprise shall submit an application for completion and acceptance to the real estate development department of the local people's government at or above the county level where the project is located. The competent department of real estate development shall, within 30 days from the date of receiving the application for completion and acceptance, organize relevant departments or units such as project quality supervision, planning, fire protection and civil air defense to accept the contents involving public safety.
Based on the above-mentioned national laws and regulations, houses that have not been completed and accepted for the record shall not be delivered for use.
- Previous article:Dragon boat festival stick to your post newsletter
- Next article:Legal procedures for the change of industry Committee
- Related articles
- What street office does Guiyang Xiaohe Vanke Metropolis belong to?
- Is it difficult to park in Shenzhen Oriental Building? How many years have you owned it? How about a parking space?
- What is the floor area ratio of Yiyang Country Garden in Luoyang?
- Kunshan Shuncheng Mingwan Details!
- How to write the recommendation letter from the team of the best order maintenance department of the property?
- How about Zi Long Tower in Shanwei? OK or not? Is it worth buying?
- How about Shaanxi Ruichengbo Industry and Trade Co., Ltd.?
- Where is the light of Guangzhou Vanke City?
- How to get to Huaihe Garden from Hefei Xinyi Middle School?
- Who is the developer of No.1 Hospital of Guangzhou Road, Heze?