Job Recruitment Website - Property management - Construction process of real estate project
Construction process of real estate project
1 Project Approval (NDRC)
2 site selection submissions (CMC)
3. Land Certificate (Land Bureau)
Declaration of Place Names (Civil Affairs Bureau)
5. Construction Land Planning Permit (Planning Bureau)
6. EIA Report (commissioned by the Environmental Protection Bureau)
7. Information required for the design of soil and water conservation scheme (Tax Bureau)
8. Construction Project Planning Permit (Planning Bureau)
9. Fire Audit Declaration Form (Fire Brigade)
10 civil air defense basement construction approval form (civil air defense office)
1 1 Documents to be submitted for planning review (Urban and Rural Planning Commission)
12 declaration of planning and design scheme (planning bureau)
13 construction drawing review requirements (drawing review organization)
14 declaration of architectural design scheme (planning bureau)
15 supervision bidding and contract filing materials (Construction Bureau)
16 materials required for construction bidding and contract filing (Construction Bureau)
17 materials needed for design contract review and filing (Construction Bureau)
18 filing materials for safe and civilized construction of the project (Construction Bureau)
19 entrusted quality supervision materials (bureau of quality and technical supervision)
20. Construction Permit for Construction Project (Construction Bureau)
2 1 Application for Construction Water (Water Supply Company)
22 application for construction electricity (electric power company)
23. Handling temporary occupation and opening (Urban Management Bureau)
24 materials needed for price approval (Construction Bureau)
25. Property management for the record (Construction Bureau)
26 Initial Registration (Construction Bureau)
27 Pre-sale Permit for Commercial Housing (Construction Bureau)
1, land acquisition stage
Sign a land transfer contract
Demolition completed
Handover completed
The analysis and design of land planning indicators passed the examination and approval.
Obtain site selection opinions
Obtain a planning permit for construction land
Pay land transfer fee
Obtain approval for construction land
Obtain state-owned land use certificate
2. Overall planning of housing construction.
The master plan was approved.
The floor plan of the apartment was approved.
The general plan shall be submitted to the construction drawing for distribution.
Detailed rules for distribution (five pictures, one book, one newspaper and one picture).
Obtain the approval of the general layout plan
Obtain detailed planning approval
Comprehensive pipeline approval
3, monomer scheme stage
Single scheme construction drawing
Monomer scheme approval
4. Development, construction, application and preliminary preparation stage
The preliminary design was approved.
Release construction report drawings
Road construction drawing release
Municipal drainage construction drawing release
Temporary water use construction drawing is issued.
Permanent water construction drawing issuance
Release of construction drawing of gas general plan.
Control center, telecom room, network room
Building layout
Distribution of drilling layout
Distribution of technical data for foundation pit bidding
The foundation pit supporting scheme passed the examination and approval.
Pile foundation construction drawing release
Obtain construction drawing review opinions
Obtain initial approval for the expansion
planning permit of construction engineering
Get a formal project
Get the payment book
Obtain environmental protection approval
Obtain fire protection approval
Obtain the approval of the general regulations for civil air defense.
Obtain the examination and approval of civil air defence basement construction drawing.
Complete the construction and supervision bidding.
Obtain the certificate of residual mud discharge.
Complete the construction and report to the supervisor.
Complete the construction permit
Community place name reply
5, foundation and basement engineering
commencement of works
Obtain geological drilling report
Pile foundation completion
Submission of settlement data of pile foundation
Obtain the intermediate acceptance registration form of pile foundation
Earthwork excavation completed
Foundation pit support is completed
Main structure
Complete the blue prints.the design
Issuance of construction drawings below 0.00.
More than 0.00 construction drawings were issued.
Distribution of settlement observation map
Distribution of fixed plates of building materials
Diesel engine model completed
Supervision contract issuance
Issue a pile foundation construction contract
Issue a pile inspection contract
Issue settlement observation contract
Earthwork contract issuance
Issue a foundation pit support contract
Contract issuance of basement waterproofing works
Contract issuance of civil air defense projects
Contract issuance during the installation of the main building
0.00 for sale
Time to 0.00
Submission of settlement data of basement structure engineering
Obtain the intermediate acceptance registration form of the basement.
Masonry completion
On-site handover of model house
Completion acceptance of decoration project of sales department
Model room, lobby, first floor facade decoration project, sales elevator, sales environment completed.
Progress from theme to sales image
Obtain a road engineering planning permit
Obtain planning permit for drainage works.
Distribution of supporting construction drawings in residential quarters
Organize three-level inspection
The latest construction drawing will be released after the meeting on the third floor.
Provide and review the sales plan and decoration standard of houses, shops, parking spaces and gardens.
The decoration scheme of the sales department has been recognized by the group.
Sales department decoration construction drawing issued.
The decoration scheme of the model house, the lobby on the first floor and the elevator front room passed the examination and approval.
The decoration scheme of model house, lobby on the first floor and elevator front room was approved by the group.
Decorative material fixing plate distribution.
Obtain a pre-sale certificate
Organization regional forecast
Complete the sales regional budget
Obtain the area calculation results of the housing management department
Complete the sales regional budget
Complete the audit of the calculation results of the housing management department.
Submit the approved calculated area to the sales center.
The calculation of residential, shops, parking spaces and garden areas has passed the examination and approval.
Sales elevator installation project contract
Issuance of elevator purchase, sales and installation contracts
Issuance of drawings for garden construction and greening construction.
Landscape materials are posted on fixed boards.
Landscape greening completed
The greening of the surrounding environment of the watchtower passage and the model house is completed.
Determine the location, quantity and related requirements of model houses.
Sales to project completion
Theme capping
Submission of settlement data of main structure engineering
Obtain the project acceptance registration form
Obtain the registration form for intermediate acceptance of low-voltage distribution.
Masonry project completion
Roofing project completion
Kitchen flue project completed
Floodlighting project completed
Progress of aluminum alloy door and window frame installation project
Progress of balcony railing installation project
Interior wall plastering completed
Exterior wall plastering completed
Exterior wall brick project completed
The removal of the grille has been completed.
Progress in building and ground engineering
Door frame installation progress
Installation progress of fire door frame in elevator front room
Progress of elevator front room reconstruction
The renovation of the lobby on the first floor is completed.
Elevator project completed
Fire control project completion
Completion of natural gas project
Permanent water use completion
Permanent power consumption completion
Complete drainage and road works.
Generator installation completed.
Installation of equipment in power distribution room is completed.
Telecommunication room completed
Indoor intelligent project completion
Household acceptance and rectification
Open permanent waters
Turn on the permanent power supply
Gas opening
Cable TV has the conditions to declare.
Telecom has the conditions to declare.
Intelligence has the conditions for use.
Emergency standby power supply has the use conditions.
Obtain the unit project quality acceptance record.
Obtain an elevator permit
Obtain fire control acceptance certificate
Obtain the gas engineering acceptance certificate
Complete civil air defense works (including installation of doors and windows, power supply to alarm room and four alarms).
Project completion
Luxury decoration completed
External wall brick fixing plate issuing
Provide a complete set of construction drawings to the property management company.
Balcony railing fixing plate distribution
Aluminum alloy door and window fixing plate distribution
Luxury decoration construction drawing issued
Permanent residential water contract
Obtain a permanent electricity use agreement
Get a house number reply
It can be reached by postal communication.
Issue roofing and indoor waterproofing contracts.
Issuance of aluminum alloy doors and windows construction contract
The balcony railing contract has been issued.
Issuance of CATV construction contract
The floodlighting construction contract has been issued.
Intelligent building contract issuance
Central air conditioning project construction contract issuance.
Issue installation contracts for entrance doors and fire doors.
Fire engineering construction contract issuance
Permanent water project contract issuance
Contract signing of electromagnetic flowmeter
Contract for the sale and installation of equipment in water pump house is issued.
Issuance of gas engineering construction contract
Issue contracts for permanent power projects.
Renovation contract, lobby and elevator lobby on the first floor.
Generator procurement, sales and installation contract issuance.
Distribution of supporting contracts for community municipal works
Issue a sports ground construction contract
Issue contracts for the sale and installation of swimming pool equipment.
Issue broadband network construction contract
The luxury decoration construction contract is issued.
Distribution of indoor environmental test contract
Issued a contract for luxury decoration supporting electrical appliances.
Issuance of boiler equipment purchase and sale contract.
Issue a contract for the construction of kitchen exhaust flue.
Distribution of deformation joint construction contract
Issue building cleaning contract
Issuance of steel structure construction contract
Curtain wall project contract issuance
Contract issuance of outdoor power pipe network project in residential quarters
The issuance of the three-dimensional parking equipment project contract.
Complete the construction of environmental park.
Submit the settlement data of garden construction supporting projects.
Complete the comprehensive evaluation of the construction unit after completion.
Completion and delivery of property rights.
Complete the cleaning work before handover and hand over all properties to the sales department.
Unsold properties, self-operated properties and properties that should be handed over to the government shall be handed over to the operation department.
Provide a complete set of completion data and construction contract to the property management company.
Obtain quality acceptance opinions.
Obtain approval documents
Submit all completion settlement data.
Submit the settlement data of luxury decoration
Issue the construction completion drawing.
Obtain planning acceptance certificate
Environmental protection acceptance opinion
Obtain line inspection records
Civil air defense acceptance certificate
Lightning protection acceptance certificate of each phase of the community
Support the transfer of education
Obtain the project completion record form
Historical surveying and mapping achievement report
Obtain a certificate of ownership
Completed the formalities for filing the ownership of the housing management department, and had the conditions for inquiring records.
Organize the establishment of a handover leading group and hold a handover comprehensive coordination meeting.
The property sold should be handed over to the property management company.
Sign the preliminary property management service contract.
Prepare the list of accounts payable and submit it to the finance department for review.
Organize the examination and approval of property handover notice.
Organize and complete the joint review of "Residential Quality Guarantee" and "Residential Instruction Manual"
"Residential quality guarantee" and "residential instruction manual" to the property.
Send a "delivery notice"
Send a notice for collection.
Report the completed building permit information to the housing management department.
Finished the real estate license.
Establish a building maintenance service center.
Transfer of property by maintenance service center
Determine the handover service hotline
Complete the condolence work of building handover.
The finance department reviews the list of accounts payable and returns it to the sales department.
Make a property management plan
Complete the handover office layout and hotline arrangement.
Complete the household handbook, building feedback form, key handover book,
Audit and printing of owner's files
Completion of project settlement
- Related articles
- Basic information of COFCO Xiangyun international living quarters
- How far is Xincheng Jingcheng from the subway?
- Summary of voluntary activities of epidemic prevention and relief
- What's wrong with Hengfeng c building
- How about Beijing Baoxin Industrial Development Company?
- How long is the property right of Jiurong Mansion in Xiaguan City, Longguang, Nanjing?
- What is the telephone number of Hangzhou Huiyaxuan Sales and Marketing Center?
- How about the property service of Macheng Jinqiao Xintiandi?
- What about Shenzhen Survey and Research Institute Co., Ltd.?
- What is the telephone number of Yantai Mountain and Chengcheng Marketing Center?