Semi-package decoration technology

I. Pre-construction (about 30 days)

The decoration company made it.

1. The measuring room is the measuring room. 2. Design drawings (about 20 days)

Rough house exploration

What I want to do

Go through the formalities of starting work (go to the property to apply for a work permit and a worker's card)

2. Pay the decoration deposit

Property decoration specification

Ready to buy

1. Central air conditioning, floor heating, fresh air and water purifier (please purchase and pay before construction, and make an appointment for the construction site).

2. Safety doors and windows

3. Customized cabinets and wardrobes for the whole house

Matters needing attention

1. According to living habits, fully communicate with designers, and start construction after the design is satisfactory.

2. Make a decoration budget table. The more accurate the budget, the less budget overruns in the later period.

3. Make a material schedule, and the main materials should be purchased in advance by stages.

Check whether the external wall leaks water in rainy days and confirm the construction budget.

Second, the demolition stage (about 10 days)

The decoration company made it.

1. Shovel the wall. 2. remove. 3. build a wall. 4. Close the balcony. 5. Clean up the garbage. 6. Measuring cabinets.

What I want to do

1. Confirm the floor heating paving method.

2. Determine the kitchen appliances (you don't need to buy them first, but you should determine the type of embedded household appliances in advance.

What I want to do

Number and size)

3. Contact the vehicle to remove the construction waste.

Ready to buy

1. temporary toilet and sewer pipe protective cover

2. Smoke pipes and check valves (embedded during hydropower transformation)

3. Sanitary ware to be embedded: bathroom, wall faucet and embedded shower head.

4. Strong box and weak box

Matters needing attention

1. Take precautions to prevent construction waste from entering the sewer and causing blockage.

2. If you want to install (water purifier, drinking water

Machines, garbage disposal, etc. ) come together; If there is floor heating, the fresh air shall coordinate with the construction party.

3. If you need to cooperate with the whole house equipment, you should carry out preliminary construction in the demolition stage.

4. Plan the layout of the switch socket

III. Hydropower transformation (about 10 day)

The decoration company made it.

1. Water and electricity disclosure

Step 2: Slotting

3. Waterway laying

4. the wall row is renovated into water (the wall row is made by those people)

5. Embedded hidden shower, hanging toilet and other accessories.

In the main material, water purification system, fresh air,

Floor heating,

central air-conditioning

The decoration company made it.

punching

7. Toilet backfill

8. Waterproof kitchen and bathroom

9. Install central air conditioning and floor heating

What I want to do

1. Contact window vendors and cabinet vendors for home measurement.

2. Take photos to record the location of water and electricity to prevent later maintenance.

3. Do a good job of acceptance after the completion of hydropower.

Ready to buy

1. Bedroom door, kitchen sliding door, bathroom door

2. Bathroom

3. Wall tiles and floor tiles

4. Floor drain pipe

5. Shower room hose

6. sill stone

Matters needing attention

1. You can buy a floor drain online in the early stage of hydropower, which is more affordable (there is no need to lengthen the floor drain).

2. The confirmation of hydropower stations requires the presence of the owner, designer and permanent worker, and shall be marked with chalk after completion (take photos to record the position for later construction).

3. After the completion of water and electricity, remember to ask the master for a statistical table of the quantity and size requirements of switches, sockets, spotlights and downlights, so as to facilitate the online shopping of related materials in the later period.

Rough house exploration

Fourth, the bricklayer stage (about 30 days)

The decoration company made it.

1. Bricks appear.

2. The bricklayer's exposure

3. Primary treatment

4. Laying wall tiles and floor tiles

5. Install floor drain

6. Customize the whole house.

7. Install doorsill, water stop and window sill.

8. Fine sewing (one week after tile laying)

9. Tile floor protection

Main materials entering the site: ceramic tile, floor drain, threshold, windowsill stone, waterproof strip and joint sealant.

What I want to do

After tiling, the whole house will be customized and the dimensions of the interior door and shower room will be re-measured.

Ready to buy

1. Masked paper dustproof protective film

2. Wood flooring

3. Plaster line

4. Aluminum gusset ceiling

5. Embedded downlights, spotlights and linear light troughs

6. Bathroom embedded Yuba and kitchen cool bully

7. Wood veneer (purchased on demand)

Matters needing attention

1. It is best to brush the back glue of the tile when sticking the wall brick to prevent it from falling off later.

2. Whether it is necessary to install the threshold will affect the previous leveling work. If extremely narrow slats are laid and used, there will be no horizontal height difference on the ground.

3. When the kitchen and bathroom are tiled? Prepare flue check valve.

Matters needing attention

4. The tiles must be accepted, the quantity must be counted, and they must be opened to check whether they are aligned and vouchers. If you want to align the tiles, you must first explain.

5. Before tiling, the tiles should be soaked in water, the tile paving method, the reserved joints, and whether to make the begonia angle (whether to soak in water depends on the characteristics of the tiles).

Five, woodworking stage (about 25 days)

The decoration company made it.

1. Woodworking base

2. The ceiling and curtain box of the whole house

3. Special styling

4. Embedded lamps and lanterns

5. Embedded flue

6. Open position of lamps and lanterns

7. Opening size of lamps and lanterns

8. Measuring door (as high door)

9. Install range hoods, stoves and sinks.

10. Woodworking acceptance

Main materials entering the site: gypsum line, ceiling, heavy cigarette machine and water tank.

Ready to buy

Wallpaper (on demand) wall paint (one bottom and two sides) floor protective film

Matters needing attention

1. The keel spacing is less than 1000mm, and the secondary keel spacing is less than 400mm.

2. The ceiling spacing is less than 1000mm, the ceiling width is greater than 700mm, and the keel is added.

3. The side keels are light steel keels, which are fixed with expansion screws. The spacing is small, and the spacing is less than 600 mm The side keels and the auxiliary keels should be fixed in a straight line with not less than two main keels.

Six, petroleum engineering stage (about 15 days)

The decoration company made it.

1. Wall treatment

Step 2 determine the wall material

3. Grinding and acceptance

Step 4: Color matching and painting

Main materials entering the site: putty, latex paint and plastering line.

What I want to do

The door-to-door installation of customized cabinets, interior doors, door covers, wooden floors and skirting lines shall be reserved in advance.

Ready to buy

1. Switches and sockets

2. Bathroom cabinets and mirror cabinets

3. Whole house lights

4. Sanitary ware: faucets, showers and sinks.

5. clothes rack

6. Angle valve

7. Glass glue

Seven. Installation stage (about 15 days)

The decoration company made it.

1. Land reclamation and cleaning

2. Switch socket installation

3. Installation of lamps in the whole house

4. Installation of sanitary ware

5. Installation of cabinets in the whole house

6. Indoor door installation

7. Wall repair

Main entry materials: switch socket, whole house lamps, whole house customization, sanitary ware, floor and indoor.

What I want to do

1. Contact the flooring vendor for home installation.

2. Return the surplus materials

Ready to buy

1. Some decoration companies include the cost of land reclamation and the installation cost of various main materials. Please consult in advance.

2. After the decoration is completed, ask the decoration company for a quality guarantee.

3. After installation, remove formaldehyde and ventilate for at least 3 months.