What are the points and details of the decoration flow chart?

Family decoration is actually a very troublesome thing, and there are many precautions and details that must be paid attention to during the decoration process. However, although there are many precautions, as long as you master the relevant details and understand the relevant steps, we will share the flow chart of the decoration for you. What are the precautions and details of the decoration? Let's have a look.

Decoration flow chart

A, decoration flow chart, property procedures

Before construction, you need to go through the following decoration procedures with the residential property before you can start construction smoothly.

1. Sign the renovation agreement issued by the property.

2. Provide the property with its own decoration drawings, and the property mainly reviews whether the hydropower and wall demolition and reconstruction projects are qualified.

3. Apply for a work permit, which is the time limit for property inspection.

4. Handling entry and exit documents for workers.

5. Pay the decoration deposit. As long as you work normally, it will be returned within 3 months after the renovation is completed.

6. Pay the garbage cleaning fee, which is used to pay for the garbage cleaning and decoration of the property.

Second, the decoration process table, decoration disclosure

The first step is not to urge the decoration company to start work quickly. But about designers, foreman to do the final construction confirmation, the main contents include:

1. Confirm all the engineering projects and design drawings that need to be dismantled, such as defining doors and windows, walls, water and electricity, wall modeling, etc.

2. Confirm all decoration materials, and explain the materials that Party A and Party B are responsible for purchasing on site.

3. Clear acceptance criteria and specific payment nodes, preferably with written proof.

Third, the decoration process table, the main demolition.

The main demolition and transformation mainly includes wall demolition, wall building, wall skin, heating removal, plastic steel window replacement, etc. After that, it is best to determine kitchen cabinets, range hoods, cookers and water heaters so as not to delay the construction period.

Four, decoration schedule, water and electricity transformation

Hydropower transformation is a concealed project, buried in the wall or under the tile. It is not easy to dismantle and change later. Therefore, it is necessary to determine the specific location of switches, lamps, sanitary ware, electrical appliances and furniture before decoration. Moreover, the kitchen cabinet designer will help you determine the transformation plan of kitchen power supply and waterway.

Five, decoration flow chart, waterproof.

After the completion of hydropower, it is necessary to wrap the riser of kitchen and bathroom with light steel keel or red brick. Then the kitchen, bathroom and balcony are waterproof.

Six, decoration process table, wall and ground leveling, brick.

Level the cement floor first, and then tile the living room, balcony, kitchen and bathroom floor. Therefore, it is necessary to determine the entry date of tiles in advance and make an appointment for bricklayers to enter the site for construction on the same day. After the wall and floor tiles are laid, the water heater can be installed, and the embedded flue check valve and smoke pipe are ready to be installed; Inform indoor wooden door brands to be present to measure the size of wooden doors and choose styles to start production. In addition, according to the final plan of cabinet brand, contact natural gas company to replace natural gas pipeline. Finally, you can inform the kitchen and bathroom ceiling brand to measure the ceiling and install it immediately.

Seven, decoration flow chart, woodworking engineering

Mainly engaged in all kinds of cabinets (cabinets made of large core boards for carpentry, not finished products) and wooden keels for ceiling and wall modeling.

Eight, decoration flow chart, painting project

Scrape putty and paint the walls. Generally blow putty 2-3 times. After scraping, polish evenly and prepare to brush latex paint. Protect the paint from touching the ground.

Need to remind everyone that if you want to paint the wall, you must pay attention to color matching. The adjusted color is lighter than the color card, and it must not be the same as the color card or darker than the color card. Because when you paint the wall, you have to brush it at least twice, and some have to brush it three times. The color of the upper wall will get darker and darker.

Nine, decoration flow chart, furniture comes into play

The last step of hard installation is to install custom furniture, doors, wooden floors, bathrooms and other hardware. The finished door should be installed before the floor, because the steps of installing the door are complicated and many tools are used. It can avoid unnecessary damage to the floor during door installation. Then complete a hard wall repair, and finished furniture, lamps and other soft clothes can enter in turn.

What are the precautions and details of the decoration?

1. What are the points and details of decoration? The waterproof wall of the bathroom should not be shorter than one meter eight when applying waterproof paint. Considering from the moisture-proof level, it is better to make waterproof layer on the bathroom and bathroom wall. The power switch device should be reserved in advance and must be installed behind the door, otherwise it will be very troublesome to use; The socket of the power supply is 30cm high from the ground, and the switch is1.4m high from the ground.

2. What are the points and details of decoration? The purchased cement cannot be used after three months of production. In addition, different types and models of cement cannot be mixed. Don't just buy wall tiles and floor tiles; After the joint pressing is completed, clean the tiles immediately, waterproof the back of the stone, and skew the tiles to avoid water accumulation.

3. What are the precautions and details of the decoration? It's best to buy a double-controlled room lamp for easy use. At the same time, we should pay attention to the structural orientation of the room and try to use soft color matching, which will give people a particularly comfortable and natural feeling.

4. What are the precautions and details of the decoration? The decoration structure of the kitchen does not conform to the principle. The distance between the pool and the stove should not be too far or too close. Lighting is usually equipped with general lighting or limited lighting. Every kitchen appliance must be placed for future use.

5. What are the precautions and details of the decoration? When using cement, we must pay attention to heat preservation, especially after the brick is paved, the heat suddenly decreases, which is the easiest to affect the viscosity of cement. When working in cold weather, antifreeze can be added to cement to ensure the construction quality. If it is a high-grade residence, when laying bricks on the terrace, it needs to be covered with an external thermal insulation material to achieve double protection.

6. What are the precautions and details of the decoration? In the process of decoration, the use of wallpaper is necessary. How to choose low-carbon healthy wallpaper? Try to avoid using monotonous and bright materials. Monotonous materials can not be well matched with the living environment, which is easy to cause a bad mood; Brightly colored materials contain a lot of harmful substances, which is very harmful.