Engineering supervision weekly
1. This time span: March 22, 2008-March 28, 2008.
2. The work completed in the renovation project of the computer room includes: shifting the fire control box, connecting the fire control system with the building property control center, and adjusting the air conditioning equipment.
The work to be completed on Saturday or next week includes: laying anti-static floor; Lighting system threading; The upper part of the west wall is closed; Installation of gas fire extinguishing system; Unified adjustment of fire fighting system and air conditioning system.
3. The completed work of the five-story decoration project includes: demolition; 6, 7, 8, 9, 10 room ground dust removal; Laying of strong and weak grounding pipes (boxes).
Projects under construction include: dismantling the original air conditioning system; The ground is covered with dust.
In addition, the transformation of the power supply system on the fifth floor has been completed.
Second, the construction quality
1. There are hidden quality problems during the installation of the battery cabinet in the machine room: ○ 1 The equipment rack is not welded with special grounding screws; ○2 The equipment is not completely placed on the beam. After the supervision engineer pointed out, the construction unit completed the rectification.
2. There are some quality problems in the construction process, such as poor heat preservation of air-conditioning condensate pipes and uneven application of fire retardant coatings on fire-fighting pipes. The supervision engineer has issued a rectification instruction.
No quality accidents occurred during this period.
3. The supervision engineer has made physical acceptance of the wires, boxes, pipes, anti-static floors, fire-retardant coatings, light steel keels, bridges and other materials and equipment, and taken photos for archiving. The quality certification documents of various materials and equipment are complete and effective. No materials that do not meet the requirements of environmental protection were found to enter the site.
Third, the construction safety
When the supervision engineer inspected the site, no smokers were found. The number and location of fire extinguishers should be placed according to the requirements of the owner.
No safety accidents occurred during this period.
Fourth, the existing problems
1. The air-conditioning construction personnel on the fifth floor encountered difficulties when entering the site. After the coordination between the owner and the building property, the problem was solved. On the 27th, air-conditioning personnel went through the construction procedures.
2. During the renovation of the sixth floor computer room, due to the insufficient supply of building materials and other factors (see 3.25 Coordination Meeting Minutes for specific reasons), the renovation project was postponed for one week.
Verb (abbreviation for verb) supervises the work.
3.25 Hold on-site coordination meeting and form meeting minutes. Establish the guiding ideology that the decoration project is mainly based on SZ architectural decoration company, with Levin as the general manager. Other construction units are required to obey management and strengthen mutual cooperation.
Issue work contact sheet 1 copy, and put forward specific requirements for grounding of anti-static floor.
18 kinds (batches) of building materials and equipment enter the site for acceptance. The quality of five kinds of materials (batches) such as 1.5mm2 flame retardant wire, light steel keel, bridge frame and electric tube for fire fighting was tested, and no unqualified products were found.
For example, the construction progress of anti-static floor is lagging behind, and the installation of bridge and fan pipeline conflicts for 4 times.
Put forward five requirements for construction quality rectification. It has been implemented.
Examination and approval of project payment for computer room: 66,500 yuan.
Engineering Supervision Weekly 2 I. Construction Progress
20xx June 13 site construction summary of Songpan drainage system reconstruction project;
1, Xinsongpan Pumping Station Project
Last week, it was planned to complete the excavation of the first layer of soil in the pumping station and the erection of the second layer of steel support; Actually completed the first layer of earthwork excavation * * * 4000m3, and the second layer of steel support is under construction;
Last week, it was planned to complete the steel binding construction of the bottom plate of the culvert in the second section of the outlet pool, and the pouring of the bottom plate of the culvert in the second section of the outlet pool was completed as planned.
2. Drainage and outlet culverts
Last week, it was planned to complete the steel binding construction of the bottom plate of the culvert in the second section of the outlet pool, and the pouring of the bottom plate of the culvert in the second section of the outlet pool was completed as planned.
Second, this week's material acceptance and testing:
This week, * * * made two groups of compressive test blocks with 130m concrete, and 1 group of impermeability test blocks.
Third, the construction quality
1, check and accept the installation quality of reinforcement binding on the bottom plate of culvert in the outlet tank, which meets the requirements of design drawings and construction specifications.
2. There is a lot of rain in the near future, so the surface water in the foundation pit should be eliminated in time, and no water can be accumulated in the foundation pit, so as to reduce the unfavorable factors to the foundation pit and avoid affecting the next construction.
3. This week, witness and sample the steel bar to enter the site for inspection.
Four, safety and civilized construction situation
1. After the excavation of the foundation pit on the first floor of the pumping station, the surrounding buildings, flood control walls and outlet culverts were monitored, and the monitoring data has no alarm value for the time being;
2. The retaining wall at the gap of the pump station body has been completed, and the temporary enclosure is being installed;
3, safety inspection every week, the construction site fire equipment and distribution box safety inspection records are complete.
Verb (abbreviation for verb) Work plan for next week
1. Safety inspection during foundation pit excavation of pumping station and quality monitoring during steel purlin support installation.
2. Quality inspection of steel binding of the second section wallboard of outlet box culvert and installation quality inspection of bent frame and formwork.
3. Well points in the process of pumping station dewatering. Patrol to check whether the dewatering work is normal, and check the water level before the second excavation.
4. Participate in witness sampling inspection and supervision parallel inspection of raw materials.
5, urge the construction unit to do a good job of safety education and self-inspection on the construction site.
The supervision of intransitive verbs
1, supervision committee1;
2. 1 supervision safety inspection record;
In order to comply with the instructions of Jinan Engineering Vocational and Technical College on students' internship, I signed an internship agreement with Shandong Taishan Engineering Project Management Co., Ltd. on July 20xx 1 day, and after completing the relevant procedures in the college, I settled in the sixteenth supervision project department of our company and started a one-year internship task.
Our project department is entrusted by the Construction Department of Shandong Provincial Sports Bureau to supervise the supporting facilities of provincial venues in the third phase of the National Games. This project is a frame-shear structure, with a service life of 50 years, four-level seismic design, two-level waterproof, two floors underground and twenty-one floors above ground. Among them, 1-4 is a residence, the fifth floor is a comprehensive office building, and the underground garage is a civil air defense structure. All the projects were undertaken by the Second Company of China Construction Eighth Bureau.
When I entered the site, the three links had been realized, the foundation pit had been dug to the design elevation, and the slope protection of the foundation pit had been supported by bolting and shotcreting; Then enter the pile foundation construction, using manual digging pile with a diameter of 800/1000; After that, the civil air defense structure is built, and the civil air defense structure is a honeycomb core rib beam roof structure. Then enter the main structure construction. By the end of our internship, this project has entered the 16 floor structure construction.
In the supervision project department, through continuous understanding and learning, I learned the relevant knowledge of construction engineering. From watching to internship, I feel the progress and improvement brought by internship. I gradually learned and mastered the content of supervision work, from the related methods of quality, progress and investment control to the site construction technology, which benefited a lot. With the support of school system knowledge and on-site mastery and application, I am trying to become a qualified construction worker.
I work as a general supervisor in the project department, mainly responsible for the civil work related to 1, 4 and 5 buildings. In my work, I strictly supervise the built projects, serve warmly and devote myself wholeheartedly to the supervision work. In order to better manage the project, we have compiled the supervision planning outline and supervision implementation rules, and carried out strict project acceptance procedures on site, and we have strictly controlled every link from material entry to installation to concealed acceptance. We also have full-time experimenters to witness the sampling and inspection of incoming materials. For safety work, we have made a complete plan and arrangement, from safety disclosure and preparation of special construction plan to on-site safety inspection.
As a supervisor, I actively perform my duties, obey the management of the company, and be familiar with engineering drawings and related specifications and construction atlas. Strict supervision of admission materials, unqualified materials are strictly prohibited for engineering. Supervise and urge the contractor to implement the process inspection procedures formulated by the supervisor, conduct on-site inspection every day, organize the supervision log on time, supervise and urge the construction unit to inspect the inspection lot, check the authenticity, completeness and accuracy of the submitted materials, participate in the related work of design disclosure and blue prints.the design, review and file design changes, and handle visa claims. During my work, I also read the corresponding atlas specifications and construction technology, and read modern measurement technology, flat drawing and reinforcement calculation. Participate in the weekly project meeting, summarize and evaluate the weekly project progress and next week's plan, project quality and safety work, and put forward requirements for future work.
Through all the work, I gradually became familiar with the supervision business and work content, mastered the essentials and key points of supervision work, made clear the nature and requirements of supervision work, realized the independence and importance of supervision work, and put forward strict requirements for my future work, striving to make myself grow step by step in future work and contribute to the construction of the motherland.
- Previous article:How about the decoration of Tian Jun City Plaza in Wujiang, Loudi?
- Next article:What are the scope of property management?
- Related articles
- How about Hengshui Hengxiang Chemical Sales Co., Ltd.?
- What is the telephone number of Chongqing Poly _ _ Sales Department?
- What are the best decoration companies in Beijing?
- How is the decoration of Kunde Bookstore in Urumqi?
- What is the telephone number of Suzhou Fontainebleau Sales Office?
- What does a weak electrician do?
- Who will handle the construction waste in Weinan and how to charge it?
- Where is the address of Zhenjiang Huangpu Center?
- On June 365438+1October 3 1 day, there were 2 locally confirmed cases and 2 asymptomatic cases in Beijing.
- What is the telephone number of Chengdu Greenland New Mile Sales Office?