20 13 answer to the last question of property manager's practice

The composition of property fees under the contract system is: cost+statutory taxes and fees+profit.

Cost = 200 (ten thousand)

Profit = cost × expected profit rate of the project =200* 10%=20 (ten thousand)

Tax = turnover × business tax and additional total tax rate

= (cost+profit) × business tax and total additional tax rate

=(200+20)*5.65%= 12.43 (ten thousand)

Total property service fee = cost+statutory tax+profit =200+20+ 12.43=232.43 (ten thousand)

Charge standard (unit price of property fee) = total amount of property service fee/(chargeable area of property service fee1February)

= 2,324,300/(65,438+million 12 months)

= 1.9369 17

≈ 1.94 (yuan/month/square meter)

So your answer is right. As long as the steps are not chaotic, the formula is not too different from what I wrote above, and the unit is well marked, you should be able to get full marks.

In addition, by the way, this question is consistent with Question 23 of Property Management Practice in June, 20 10 (I made a reference answer on my blog two years ago), and the result is not too bad. It can be seen that the question bank in previous years still has a certain repetition rate, so please pay enough attention to it!