Job Recruitment Website - Property management company - Simple engineering contract agreement
Simple engineering contract agreement
Contract Agreement for Simple Project (I) Employer: _ _ _ _ _ _ _ _ _ (hereinafter referred to as Party A)
Contractor: _ _ _ _ _ _ _ _ _ _ (hereinafter referred to as Party B)
According to the Contract Law of People's Republic of China (PRC), both parties have reached an agreement through consultation, signed this contract and earnestly performed it.
Rule number one Project item
1. Project name: _ _ _ _ _ _ _ _ _ _ _
2. Project location: _ _ _ _ _ _ _ _ _ _ _ _
3. Project number: _ _ _ _ _ _ _ _ _ _ _
4. Project scope and content: The total construction area of the project is _ _ _ _ _ _ square meters.
5. Project cost: The construction drawing budget cost of all projects is RMB _ _ _ _ _ _ _ _. (For details of individual projects, please refer to the project list.)
Rule number two Project duration
1. Commencement and completion dates: According to the time limit quota promulgated by the state, the commencement and completion dates of this contract project are as follows through negotiation between both parties:
All projects will start on _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
2. The preparatory work before construction shall be completed by both parties in accordance with the provisions of Article 3 of the project agreement.
3. In the process of construction, in case of the following circumstances, the construction period can be extended. If the time limit is extended, both parties shall negotiate and sign an agreement in time and report it to the relevant departments for the record.
(1) Those who are forced to stop work due to force majeure;
(2) The construction cannot be continued because Party A changes the plan or construction drawing;
(3) Because Party A fails to provide drawings, materials and equipment on schedule, or the required materials and equipment fail to meet the requirements, Party A is forced to stop work and cannot carry out construction smoothly.
Rule three. Material supply
1. All materials required for this project shall be supplied according to the following terms (_ _ _ _ _ _).
(1) Special materials, unified materials and unified mechanical and electrical products shall be purchased by Party A and supplied to the place designated by Party B. Other materials shall be purchased and supplied by Party B. ..
(2) Party B is responsible for the application, ordering and adjustment of materials, unified distribution and departmental management; Party A is responsible for purchasing and supplying special materials and mechanical and electrical products that are uniformly distributed and managed by the department to the place designated by Party B, and Party B is responsible for purchasing and supplying other materials.
(3) All materials and equipment shall be purchased by Party A and supplied to the site or designated processing place.
(4) Other ways: _ _ _ _ _ _
2. Variety, specification, quantity and entry time of materials and equipment provided by Party A (see the list of materials and equipment provided by Party A for details).
3. Party A is responsible for the application, ordering and processing of complete sets of equipment and non-standard equipment, and for the inspection of imported and built equipment before delivery to Party B. When Party A entrusts Party B to undertake equipment ordering and non-standard equipment processing, a separate agreement shall be signed.
4. If the materials needed for the project cannot meet the requirements of the project due to the specifications, varieties or materials of the supply department, they must be replaced or processed with other specifications and varieties, and the original design unit and Party A shall obtain the consent in advance, and the three parties shall sign an agreement before implementation. The quantity difference, price difference and processing fee caused by substitution or processing shall be settled according to the existing regulations.
5. All materials that should be accompanied by a certificate of conformity must be verified by the supplier when entering the site; If there is no certificate, it must be tested by the supplier before it can be used, and the testing fee shall be borne by the supplier. As the construction unit or design unit requires re-inspection of materials with factory certificate, the test expenses shall be borne by Party A. ..
6. If the materials and equipment supplied by Party A are not supplied on time, or the specifications and quality can't meet the requirements, and it can't be solved through the efforts of both parties, thus causing losses to Party B, Party A shall bear it. ..
Article 4? Project payment settlement
1. The settlement method of all engineering expenses shall be handled according to the following item (_ _ _ _ _ _).
(1) The settlement is based on the approved construction drawing budget plus the change budget.
(2) According to the construction drawing budget plus the lump sum coefficient, the lump sum expenses shall be settled, and the expenses beyond the lump sum scope shall be paid according to the relevant regulations.
(3) According to the standard construction drawing, the unilateral expenses shall be settled by lump sum, and the expenses beyond the scope of lump sum shall be paid according to the relevant regulations.
(4) Labor costs shall be settled according to the budget quota.
(5) The project subject to tender shall be settled at the bid-winning price.
2. The disbursement and settlement of project funds shall be handled according to the existing regulations (see the annex for details).
Article 5? Construction and design changes
1. Party B shall organize the construction according to the national construction acceptance specifications, quality inspection standards and equipment requirements, and all of them are qualified.
2. Adhere to the construction according to the drawings, and neither party may change the design at will. In the following circumstances, the responsible party shall bear the responsibility for the losses caused to the other party by slowdown, rework, overstock of materials and components, relocation of construction forces and institutions, etc.
(1) If there is any mistake or serious irrationality in the design during the construction, Party B shall notify Party A in writing, and Party A shall negotiate with the original design unit within seven days to propose to modify or change the design documents, and the construction can only be started after both parties sign an agreement.
(2) In the process of construction, if the design changes exceed the original design standard or scale, the construction shall be re-submitted for approval according to the examination and approval procedures before construction, and the project budget shall be reviewed by the auditing organ, and the investment shall be reviewed by the handling bank. Only after the two parties sign an agreement can the construction be started. Otherwise, either party shall not force the construction.
(3) During the construction process, in case of suspension or postponement of construction, both parties shall agree on the safe parts of the project under construction.
(4) In the course of construction, if it is found that Party A's investment is insufficient, the project progress payment can't be paid on time, and the construction is stopped or postponed halfway, the losses caused to Party B shall be borne by Party A. ..
3. Party B shall strictly implement the concealed engineering acceptance system. After the concealed work is completed, it must be recorded, and the next working procedure can only be carried out after the acceptance. Before the concealed works are concealed, Party B shall notify Party A for inspection. If Party A fails to inspect it in time, Party B can inspect it by itself, fill in the inspection records of concealed works and send them to Party A. Afterwards, Party A will inspect the concealed works, and if it meets the quality standards, the inspection expenses shall be borne by Party A; If it does not meet the quality standards, the inspection expenses shall be borne by Party B. If Party B conceals the project and fails to notify Party A for inspection, the inspection expenses shall be borne by Party B. ..
4. When Party A and Party B encounter engineering problems in the construction, they shall submit for approval according to the quota management method. The change budget attached to the change project agreement shall be sent to the handling bank in time before construction as the basis for settlement of the project payment.
Article 6? Completion acceptance, settlement and warranty
1. Party B shall notify Party A of the acceptance date in writing five days before the completion of a single project. If Party A cannot attend the acceptance on time, it shall notify Party B in advance, and set another acceptance date after obtaining Party B's consent, but Party A shall acknowledge the completion date. If Party A fails to attend the acceptance on time, all the management expenses and losses arising therefrom shall be borne by Party A ... and Party B shall be paid a penalty of one ten thousandth of the budgeted expenses every day.
2. After the acceptance of the completed project, Party B shall hand it over to Party A within three days from the date of acceptance. If Party A fails to take over on schedule, resulting in the loss of the acceptance project, Party A shall bear it. ..
3. If a unit project in a project needs to be handed over to Party A separately, both parties shall go through the intermediate acceptance procedures at the time of handover as the basis for the completion acceptance of the unit project.
4. During the acceptance of the completed project, if it is found that the quality of the project does not meet the requirements, Party B shall be responsible for free repair or rework, and complete it within the measures and time limit agreed by both parties. After the acceptance, the handover. If the delivery of the project is delayed as a result, Party B shall pay Party A a penalty of one ten thousandth of the estimated cost every day.
5. The project has been basically completed. If both parties can't solve a certain material or equipment, the project can't be completed on schedule. With the consent of both parties, the completion can be reduced, and the completed project can be handed over after completion acceptance.
6. The acceptance of the completed project is based on the construction acceptance specifications, quality inspection standards and construction drawings issued by the state. Upon completion acceptance, Party B shall provide Party A with the following documents 10 days before acceptance:
(1) Increase or decrease negotiation records such as change documents;
(2) concealed engineering acceptance records and intermediate completion acceptance records;
(3) After the completion of the project, the completion drawing should be drawn, and the construction unit should explain the slight changes of the project on the original construction drawing and submit it to the construction unit for the record. When the project changes greatly, the construction unit may draw by itself or entrust the design unit and construction unit to draw the completion drawing.
7. After the completion and acceptance of a single project, Party B shall submit the completion settlement to Party A for review within 15 days after the completion and acceptance, and within 30 days after the completion and acceptance, if it is a civil construction project or an industrial construction project. Party A shall complete the civil engineering review within 15 days and the industrial review within 20 days after receiving the completion settlement documents. If no objection is raised at maturity, the handling bank will examine and approve the appropriation.
8. After the project is completed and accepted, Party B shall be responsible for the quality warranty of civil engineering for one year (the heating project is the first heating period). During the warranty period, Party B shall be responsible for the maintenance of quality accidents such as roof leakage, pipeline leakage, air leakage and blockage caused by the responsibility of the construction unit (professional construction and installation works shall be handled according to the special regulations of relevant competent departments in the State Council). )
9. If Party A uses the project or uses the project without authorization before acceptance, Party A shall be responsible for the quality or other problems arising therefrom.
Article 7? Liability for breach of contract and arbitration
1. As Party B fails to complete the project according to the date stipulated in this contract, it shall pay Party A a penalty of one ten thousandth of the budgeted cost for each day overdue (calculated on the date of completion acceptance); If it is a contractor without materials, it shall pay _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ to Party A.
2. Party A and Party B shall not make an excuse to default on various payables. If the payment is not made in time, the penalty for overdue payment shall be paid to the other party according to the short-term loan interest rate of the bank.
3. Where rationalization proposal award and early completion award are implemented, Party A and Party B shall sign another agreement according to relevant policies.
4. When a contract dispute occurs in the construction and installation project contracting, both parties shall settle it through consultation in time. If negotiation fails, either party may apply to the urban and rural construction committees at all levels or the superior business departments of both parties for mediation; If it can't be solved, you can bring a lawsuit to the building or directly to the people's court.
Article 8? supplementary terms
1. budget review procedure, the construction unit will send the construction and installation project contract (with the construction drawing budget) to the municipal construction project contract budget review office for review. If verification is needed, it can be carried out at the district or county administration for industry and commerce where the building is located.
2. Before the signing of this contract, the construction preparation contract (project agreement) signed by both parties can be used as an annex to this contract. Letters, faxes, emails, etc. After confirmation by both parties, it will become an integral part of this contract and have the same effect as this contract.
3. For the project subject to tender, the contract shall be signed according to the Interim Measures for Bidding and Bidding of _ _ _ _ _ _.
4. Other matters agreed by both parties: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Article 9? Contract number and validity period
1. This contract was signed on _ _ _ _ _ _. Party A and Party B each hold one original and submit one copy to the competent business departments of both parties; The remaining copies shall be sent by Party A to the district and county administration for industry and commerce where the handling bank and the building are located for the record.
2. This contract shall come into effect as of the date of signature by both parties. It will become invalid after all projects are completed and accepted and the final payment is settled.
Party A (signature): _ _ _ _ _ _ _ _ _ Party B (signature): _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _.
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _.
Contract Agreement for Simple Works (II) Employer (hereinafter referred to as Party A): _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Contractor (hereinafter referred to as Party B): _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
After friendly negotiation, Party A decided to entrust Party B with the decoration. In order to protect the legitimate rights and interests of both parties, combined with the specific conditions of this project, the two parties reached the following agreement for common compliance.
I. Overview of the Project
1. Decoration construction site: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
2. Decoration construction content: See the attachment for details.
3. Contracting method: contracting for work and materials.
4. Construction period: from: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Second, the project price and settlement agreement
1. Total project price: _ _ _ _ _ _ _ Yuan, in words (RMB): _ _ _ _ _ _ _ _ _ _ _ _ _ _.
2. The payment method of the project payment is as follows:
(1) When the contract is approved for the first time, 30% of the total project cost will be paid, totaling _ _ _ _ _ _ _.
(2) 70% of the total project cost will be paid on the day of the second completion acceptance, totaling _ _ _ _ _ _ _ _ _ _.
(4) The project quality warranty period is 1 year. The warranty period is calculated from the date of signing the completion acceptance.
Three. Material supply and decoration process agreement
1. If the materials and equipment provided by Party B do not meet the quality requirements or have different specifications, they shall not be used. If there are quality problems or specification differences in the materials and equipment provided by Party B, resulting in engineering losses, Party B shall bear the responsibilities.
2. During the construction process, Party A shall contact Party B in advance when proposing design modification opinions and adding or subtracting engineering projects. The construction of this project can only be carried out after both parties agree, thus affecting the completion date. Both sides agree.
3. During the construction period, Party B shall take necessary safety protection and fire control measures to ensure the safety of operators and nearby residents, and prevent accidents such as pipeline blockage, water leakage, power failure and destruction of articles. In case of the above situation, it shall be the responsibility of Party A, and Party A shall be responsible for and compensate; Where Party B is responsible, Party B shall be responsible for repair and compensation.
4. Party B shall participate in the on-site disclosure of construction drawings or work instructions organized by Party A, organize the construction as required, complete the construction tasks with good quality and quantity on schedule, and solve all matters for which Party B is responsible, and Party B shall recognize its actions. Without the consent of Party A and the approval of the local housing management or property management department, the original building load-bearing structure, various equipment and pipelines shall not be dismantled and modified at will.
Fourth, the way of dispute settlement.
Any dispute arising from the execution of the contract between the two parties shall be settled through friendly negotiation. If negotiation fails, a lawsuit may be brought to the people's court.
After this contract is signed by both parties, both parties must strictly abide by it.
Party A (signature): _ _ _ _ _ _ _ _ _ Party B (signature): _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _.
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _.
- Related articles
- The car was hit by the railing of the community. Who is responsible?
- Thank you letter to customers
- What are the legitimate reasons for not paying property fees?
- I want to buy a house in Hengxiang, Harbin. Who knows how Hengxiang Phase III works? Is it worth starting with?
- Where can I get a Pudong medical insurance card?
- How to get from Hongqiao Railway Station to Changxin Building on Changle Road?
- How about Jiangsu Mole Biotechnology Co., Ltd.?
- Jilin Thermal Power Company Telephone
- Is there a bus from Shenzhen Buji Bus Station to Shenzhen Airport?
- Where is fairview park in Daye, Texas?