What do you need for property acceptance after renovation?

1. When the planning department examines and approves the documents, it is usually required to provide the project planning permit (copy), but the original must be verified. Copy and official seal of the construction unit indicate the original storage location.

2, the project construction permit, provide a copy, submit the original verification, copy stamped with the official seal of the construction unit and indicate the original storage location.

3, the approval document of the public security fire department, the design requirements to provide the original, that is, the construction project fire acceptance opinions.

4. The original document with environmental protection requirements approved by the environmental protection department is the Suzhou Construction Project Environmental Impact Report Form issued by the Environmental Protection Bureau of our city.

5, construction drawing design document review report, according to the original relevant provisions.

6. The Special Acceptance Opinion of Construction Project Archives, namely the Receiving Contact Sheet of Construction Project Archives provided by the Urban Construction Archives (original).

7. Other documents required by laws and regulations.

Extended data

Acceptance procedures:

1, application report

When the project meets the acceptance conditions, the contractor may submit a completion application report to the supervisor.

Step 2 accept

After receiving the application report for completion acceptance submitted by the contractor as required, the supervisor shall review the contents of the application report and handle it according to different situations.

3, unit project acceptance

According to the contract schedule, when the employer needs to use the completed unit project before the completion of all projects, or when the contractor proposes to be approved by the employer, the unit project can be accepted. After the acceptance, the supervisor shall issue the unit project acceptance certificate signed by the employer to the contractor.

4. Operation during construction

Refers to the contract project has not been fully completed, and one or more unit projects or engineering equipment installation has been completed, which shall be implemented according to the special contract terms. If it needs to be put into operation during the construction period, it can only be put into operation during the construction period after it is approved by the employer and proved to be safe.

5. Trial operation

6. Clean up the site after completion

Unless otherwise agreed in the contract, after the project acceptance certificate is issued, the contractor shall arrange the construction site as required. Before the supervisor passes the inspection, the contractor shall bear the cost of cleaning up the site after completion.