Job Recruitment Website - Property management company - In the process of semi-package decoration, the owner can do this.
In the process of semi-package decoration, the owner can do this.
Semi-package decoration process 1. Before construction (about 30 days)
The decoration company made it.
1, measuring room
2. Design (about 20 days)
What I want to do
1, go through the commencement formalities.
(Go to the property to apply for a work permit. Worker pass)
2. Pay the decoration deposit
Ready to buy
1, central air-conditioning, floor heating, fresh air, water purifier (pay before construction, and make an appointment for the construction site).
2, security doors, windows
3. Customized cabinets and wardrobes for the whole house
Matters needing attention
1. According to living habits, fully communicate with designers before starting work.
2. Make a decoration budget table. The more accurate the budget, the less budget overruns in the later period.
3, prepare the material schedule, advocate material should be purchased in advance by stages.
Second, the demolition stage (about 10 days)
The decoration company made it.
1, shovel the wall, 2, demolish 3, build the wall, 4, seal the balcony, 5, clean up the garbage, 6, measure the cupboard, what do I want to do?
1, confirm floor heating paving mode 2.
2. Determine kitchen appliances (you don't need to buy them first, but you need to determine the model and size of embedded household appliances in advance) 3. Contact the construction garbage truck.
Ready to buy
1, temporary toilet. Protection cover of sewer pipe
2, smoke pipe, check valve (need to be embedded when hydropower transformation)
3. Sanitary ware to be embedded: bathroom, wall faucet and embedded shower head.
4. Strong box and weak box
Matters needing attention
1, protect it to prevent construction waste from entering the sewer and causing blockage.
2. Installation (water purifier, water dispenser, garbage disposal, etc. ) It should be arranged together: if there is floor heating, Xinfeng will coordinate the order with the construction party.
3. If it is necessary to cooperate with the intelligent equipment of the whole house, the preliminary construction shall be carried out in the demolition stage.
4. Plan the position cover layout of the switch mass seat.
III. Hydropower transformation (about 10 day)
The decoration company made it.
1, water and electricity disclosure 2, slotting 3, water circuit laying 4, wall drainage and water transformation 5, embedded shower, bathroom and other accessories 6, punching 7, toilet backfilling 8, kitchen and bathroom waterproofing 9, central air conditioning, floor heating installation.
What I want to do 1. Contact window vendor and cabinet vendor to measure the size. 2. Take photos to record the location of water and electricity to prevent later maintenance. 3. Make an acceptance box after the completion of water and electricity.
Ready to buy 1, bedroom door, kitchen sliding door, bathroom door.
2. Bathroom
3, wall tiles, floor tiles
4. Floor drain pipe
5, shower room water stop
6, threshold stone, windowsill stone
Iii. Hydropower transformation (about 10 day), and matters needing attention
1. You can buy a floor drain online in the early stage of hydropower, which is more affordable (there is no need to lengthen the floor drain).
2. The confirmation of hydropower stations requires the presence of owners, designers and long-term workers. After completion, mark it with chalk (take photos to record the position for later construction).
3. After the completion of water and electricity, remember to ask the master for a statistical table of the quantity and size requirements of switches, sockets, spotlights and downlights, so as to facilitate the online shopping of related materials in the later period.
Fourth, the bricklayer stage (about 30 days)
What does the decoration company need to do?
1, brick arrival 2, bricklayer's disclosure 3, basic treatment 4, wall and floor tile paving 5, floor drain installation 6, whole house customized resurfacing 7, threshold installation, water stop, window sill 8, beautiful joint (one week after tile paving) 9, tile floor protection
What I want to do
After tiling, we will re-measure the dimensions of the whole house custom merchants, indoor door merchants and shower room merchants.
Fourth, the bricklayer stage (about 30 days)
What does the decoration company need to do?
1, brick arrival 2, bricklayer's disclosure 3, basic treatment 4, wall and floor tile paving 5, floor drain installation 6, whole house customized resurfacing 7, threshold installation, water stop, window sill 8, beautiful joint (one week after tile paving) 9, tile floor protection
What I want to do
After tiling, we will re-measure the dimensions of the whole house custom merchants, indoor door merchants and shower room merchants.
Ready to buy
1, textured paper dust-proof protective film
2. Wood floor
3. Plaster line
4. Aluminum gusset ceiling
5, embedded downlight, spotlight, linear lamp slot
6, bathroom embedded Yuba, kitchen cool bully
7. Wood veneer (purchased on demand)
Fourth, the bricklayer stage (about 30 days)
Matters needing attention
1, it is best to brush the back glue of the tile when sticking the wall brick to prevent it from falling off later.
2. Whether the lintel needs to be installed will affect the previous leveling work. If extremely narrow slats are laid and used, there will be no horizontal height difference on the ground.
3. When the kitchen and bathroom are tiled? Prepare flue check valve.
4, ceramic tile comes into play must first acceptance, count the number, dismantle check whether level off, whether the brick seam. Just to be clear.
5. Before laying the tiles, the tiles should be soaked in water, the method of laying the tiles, the reserved joints, and whether to make the begonia angle (whether to soak in water depends on the characteristics of the tiles).
Five, woodworking stage (about 25 days)
What does the decoration company need to do?
1, woodworking base
2. The ceiling of the whole house: curtain box
3. Special styling
4, lamps and lanterns embedded
5, pipeline embedded
6. Open position of lamps and lanterns
7. Opening size of lamps and lanterns
8, measuring door (hall)
9. Install range hoods, stoves and sinks.
10, woodworking acceptance
Five, woodworking stage (about 25 days)
What does the decoration company need to do?
1, woodworking base
2. The ceiling of the whole house: curtain box
3. Special styling
4, lamps and lanterns embedded
5, pipeline embedded
6. Open position of lamps and lanterns
7. Opening size of lamps and lanterns
8, measuring door (hall)
9. Install range hoods, stoves and sinks.
10, woodworking acceptance
Ready to buy 1, wallpaper (on demand)
2, wall paint (one bottom and two sides)
3, the ground protective film
Matters needing attention: 1, keel spacing less than 1000mm, keel spacing less than 400mm?
2. The spacing between lifting points is less than 1000mm, and the ceiling width is greater than 700mm, so add dragon.
3. The side keel is made of light steel keel and fixed with expansion screws. Small spacing, spacing less than 600 mm, side keel and auxiliary keel with not less than two main keel fixed, should be in a straight line.
Six, petroleum engineering stage (about 15 days)
What does the decoration company need to do?
1, wall treatment 2, wall material determination 3, grinding acceptance 4, color painting.
What I want to do
The installation of customized cabinets, interior doors, door covers, wooden floors and skirting lines in the whole house shall be reserved in advance.
Ready to buy
1, switch, socket 2, bathroom cabinet, environment cabinet 3, whole house lamps 4, sanitary ware: faucet, Huasan, sink 5, clothes rack 6, angle valve 7, glass glue.
Seven. Installation stage (about 15 days)
What does the decoration company need to do?
1, land reclamation and cleaning 2, switch socket installation 3, whole house lighting installation 4, sanitary ware installation 5, whole house cabinet installation 6, indoor door installation 7, wall repair.
What I want to do
1. Contact the flooring vendor for home installation. 2. Return the surplus materials.
Ready to buy
1. Some decoration companies include the cost of land reclamation and the installation cost of various main materials. Please consult in advance. 2. After the decoration is completed, ask the decoration company for quality certificate. 3. After installation, remove formaldehyde and ventilate for at least 3 months.
- Related articles
- Which community does Wujiang happiness belong to?
- Where is Jiuhua Garden in southwest Guizhou?
- Model essay on liquor research report
- Property fee debate
- What about Macheng Boyue Sports Culture Service Co., Ltd.?
- How about Hangzhou Ren Fei cleaning service co., ltd?
- What is the reason for the failure of the access card? What if the access card is invalid?
- What's the telephone number of Shijiazhuang Liuhe Jiulong Sales Department?
- Tianying Shangcheng property
- How much is the property management fee for the commercial and residential dual-use house in Building 45, Lane Jiuzhou Apartment, No.50/KLOC-0, Dongjing Changbang Road, Songjiang District?