What are the relevant regulations for installing charging piles in the community?

Units or individuals who need to install charging facilities in the Pacific Auto Network need to go to the new energy passenger car manufacturer to confirm the charging conditions after signing the agreement on car purchase intention. After that, the enterprise will conduct on-site electricity consumption and construction feasibility investigation with the power supply company, and issue a confirmation letter on the charging conditions of the new energy minibus within 7 working days.

The details are as follows: Installation of electric vehicle charging piles: Confirmation of charging conditions The most critical step in the installation of electric vehicle charging piles is the confirmation of charging conditions. The key point is whether there is a fixed parking space and whether the property agrees to install charging piles. The specific steps to confirm the charging conditions are as follows:

1. After the user signs the car purchase intention agreement with the car manufacturer or 4S shop, the user shall go through the formalities for confirming the charging conditions of the car purchase. At this time, the materials to be provided include:

1) car purchase intention agreement;

2) the identity certificate of the applicant;

(three) proof of the property right or the right to use the fixed parking space;

4) Application for installing electric vehicle charging equipment in parking space (approved by property seal);

5) Parking space (garage) plan (or site environment photo).

2. After accepting the user's application and verifying the authenticity and integrity of the user's data, the automobile production enterprise or 4S shop will go to the site with the power supply company to conduct electricity consumption and construction feasibility exploration according to the agreed exploration time.

3. The power supply company is responsible for confirming the user's power supply conditions and completing the preparation of the preliminary feasibility plan for power consumption of self-use charging facilities.

4. The automobile manufacturer or 4S shop is responsible for confirming the feasibility of charging facilities construction, and together with the power supply company, it will issue a confirmation letter of charging conditions for new energy passenger cars within 7 working days.