What are the acceptance tests for the completion of real estate development projects?

Rain and sewage pipeline formalities:

(1) Receive and fill in the rain and sewage pipeline acceptance form, with the rain and sewage pipeline construction drawing, construction project approval letter, construction project environmental impact approval form and construction project environmental impact report (form) attached, and go to the Construction Bureau of the administrative examination and approval center where the project is located to handle the rain and sewage pipeline acceptance.

(2) The construction of rain and sewage pipes must be carried out after passing the water closing test at the site of the Drainage Management Office.

Extended data:

Acceptance conditions:

After receiving the project completion report submitted by the construction unit and meeting the following conditions, the construction unit may organize the relevant personnel of the survey, design, construction, supervision and other units to carry out the completion acceptance:

1, which completed the engineering design and the contents agreed in the contract.

2. The construction unit shall inspect the quality of the completed project, confirm that the project quality conforms to the relevant laws, regulations and mandatory standards for project construction, meets the design documents and contract requirements, and submit a project completion report. The report shall be reviewed and signed by the chief supervision engineer (for the entrusted supervision project), the project manager and the relevant person in charge of the construction unit.

3, a complete technical files and construction management information.

4, the construction administrative department and the entrusted engineering quality supervision institutions and other relevant departments shall be ordered to rectify all problems.

5. For the project entrusted for supervision, the supervision unit shall submit the project quality evaluation report under the condition that the supervision information is complete, and the report shall be reviewed and signed by the chief supervision engineer and the person in charge of the supervision unit. The project quality evaluation report of the project not entrusted with supervision shall be completed by the construction unit.