After seven steps, the elevator can be installed in Xi 'an's old residential area.
Step 1: Determine the implementer.
According to the introduction of Xi City Construction Committee, the main body of elevator construction in old residential quarters is the housing property unit, the original housing reform sales unit or the residential management unit entrusted by it in writing and the property service enterprise, which is responsible for project declaration, scheme publicity, fund raising, equipment procurement, project implementation and maintenance management, and undertakes corresponding obligations and responsibilities. It is understood that Xi 'an's old residential area before 2000 is about 40 million square meters, involving more than one million people.
Step 2: Apply for the project.
The implementer entrusts the design unit to preliminarily judge the technical feasibility of the elevator installation project. When a feasible project is preliminarily judged, the implementation plan includes design, capital, construction, procurement and maintenance. It should be prepared, and after publicizing the residents' opinions and signing relevant agreements, a written declaration should be made to the District Housing and Construction Bureau. District construction, district planning and other departments to guide the responsible units to carry out preliminary work.
Step 3: Preliminary review of the project
The District Housing and Construction Bureau organizes the planning sub-bureau and other relevant departments to conduct a preliminary examination of the declared projects and materials, and submit the qualified projects in the preliminary examination to the Municipal Construction Committee. The preliminary provisions are as follows: (1) it must be approved by the owner of this unit or the exclusive part of this building, which accounts for more than 2/3 of the total construction area and more than 2/3 of the total number of people; Old residential areas with legal ownership certificates or legal examination and approval procedures can be declared; The addition of elevators should basically meet the requirements of planning and fire protection, and within the scope of the original red line of construction land, it has no significant impact on urban planning and does not affect the safety of building structures; If the walls of the hoistway and car are made of transparent materials, and no electrical equipment is placed at the top, the building spacing shall meet the following requirements: the long sides of the two buildings shall not be less than12m; The long side of one building is not less than 9 meters relative to the end side of another building; The opposite ends of the two buildings are not less than 9 meters.
Step 4: Plan Release
Xi City Construction Committee organized the municipal finance, planning, quality supervision departments, and related experts to jointly review the reported projects through on-site reconnaissance and data review, and issued a pilot program for installing elevators in old residential quarters for eligible projects. It is planned to release projects that are combined with the comprehensive upgrading and transformation of old residential areas, and give priority to pilot projects.
Step 5: Organize implementation.
After the pilot scheme is issued, the implementer shall organize the implementation in accordance with the construction procedures, and must entrust a design, construction, supervision, construction drawing review and elevator installation inspection unit with corresponding qualifications. All units shall bear the responsibility for quality and safety according to laws and regulations, and organize the completion acceptance according to laws. The construction, planning and quality supervision departments of all districts strengthen the process supervision, urge all units to implement the project quality responsibility system, ensure the project quality and construction safety, and handle the elevator supervision, inspection and use registration procedures in time.
Step 6: Preliminary inspection
After the project is completed, accepted and safely operated, the implementer shall submit the relevant materials for completion, maintenance and operation, and the District Housing and Construction Bureau shall organize the district-level departments to conduct preliminary examination, and then submit them to the Xi Construction Committee.
Step 7: Joint inspection
Finally, Xi Construction Committee organized relevant municipal departments to conduct joint inspection. After the acceptance, the Xi Construction Committee and the Municipal Finance Bureau will allocate the subsidy funds of municipal departments 1.5 million yuan to the finance of each district in one lump sum, and each district will timely allocate the subsidy funds. (Reporter Jin Wen)
(The above answers were published on 20 17-04- 12. Please refer to the actual situation for the current purchase policy. )
Click to receive the red envelope for viewing the house, and directly receive 100 yuan in cash.
- Related articles
- What about Xi Anjunhua Real Estate Co., Ltd.?
- Where do I get off at Dalian Champs Elys¨¦ es Square?
- How to get to Manhattan Plaza A from Rantun East Road Rantun Road?
- LU ZHOU LAO JIAO CO.,LTD Co., Ltd. 60th Edition Album Songs
- Xi An San Di Feng Dan Community Coding
- How to write a Christmas sentence?
- How far is it from Hongmei to Tianhe Zhucun?
- Provisions of Guangzhou Municipality on the Classification and Management of Domestic Waste
- Brief introduction of Argo county project
- How about Zibo Hongcheng International Plaza Apartment?