Job Recruitment Website - Property management company - What is the time limit for submitting fire protection drawings for approval?

What is the time limit for submitting fire protection drawings for approval?

1. To report to the construction site, you need to fill in the construction site report record form and stamp it?

2. The construction unit shall provide a copy of business license and qualification certificate, construction organization design, fire power system, fire safety agreement and seal it. ? After obtaining the work permit, prepare the above documents and go through the on-site filing formalities at the fire department where the construction is located. Step 4, eliminate inspection and electrical inspection.

1.? The technical inspection of professional units shall complete the elimination inspection, electrical inspection and report (1-2 days).

2. There are usually three kinds of burning tests for materials designated by the fire department. The reference unit price is 3500 yuan per test.

The fifth step is the procedures and required documents for fire declaration and acceptance.

65438+

2. After the fire department notifies the time, when the fire department sends someone to the site for acceptance (7 working days), the construction management personnel will cooperate with the site for acceptance and obtain fire safety inspection opinions (7 working days).

Step one, collect the drawings and drawings description required for the fire report?

1. Drawing Directory: lists all drawing names and drawing numbers.

2. Legend: list all legend numbers and names. If each picture is marked with a legend, you don't have to do this page.

3. Description of decoration design: description of project address, area, basis and specification of drawing preparation, and fire rating of decoration materials.

4. Description of electrical design: description of specifications and standards involved in the design, and brief description of distribution box, lamps, emergency lighting, wires and circuit materials.

5. Description of fire protection design: description of design basis and reference codes, general situation of main buildings, description of fire protection water sources and fire protection facilities.

6. Original structural drawing: The original wall structure of the building area in the original structural drawing of the building provided by the property has an axis.

7. Wall distribution map: The wall reaching the ceiling and the wall not reaching the ceiling are represented by different lines, indicating the fire escape. Unless there are approval documents and drawings from the design institute and stamped, the load-bearing wall, firewall or seismic box wall shall not be removed or widened.