Summary of probation period for project manager's confirmation
The summary of the project manager's probation period is always like running water, and it has been two months since he came to xx Company in a blink of an eye. During this time, I feel the passion and development of xx company every day. In getting along with my colleagues, I got a lot of help, most of which came from my mentor Lu. Whenever I meet some unfamiliar work links or tasks, I always get his careful guidance. Now I have a comprehensive understanding of xx company, and feel the harmony and friendship among many colleagues, as well as the team consciousness of the project team.
In the past two months, I was responsible for the demand discussion of X module, database design, progress management of code writing, and development progress management of xx platform of X project. Through everyone's full cooperation, I basically completed most of my business needs within the specified time. Through this project, I also enhanced my experience in project management, learned a lot of X-related business knowledge, and fully understood the comprehensive quality and working ability of all members of the project team. In terms of personal business, I have made an in-depth understanding of most of X's businesses. Xx evaluation, mainly to understand * * * and other businesses. Of course, this is largely due to the careful guidance of Tang Xiao, Xiao Wei and Xiao Feng, and I am very grateful to them.
In the past X project implementation process, I also found some advantages and problems of the project team. Not much to say about the advantages, mainly because everyone has a strong fighting spirit. In view of some problems existing in the project team, I would like to express my personal views here for reference only.
1, control of the project team
Because our current project is a brand-new combination, there are too many unfamiliarity and uncertainties among the members, which leads to that we are not optimistic about the degree of risk control in the process of carrying out the planned tasks. We always rely on our first feelings to deal with related planning tasks, so many events are lagging behind in the implementation process. We must work overtime to make up for these lags. Excessive overtime and rework will inevitably damage the control satisfaction of the team members to the project team, and of course directly affect the cognition and evaluation of the company.
I feel that we always lack the ability to control and foresee, and there are always unpredictable risks in the process of completing any thing or goal, but how to control risks before they break out and reduce their impact is something we should consider and control.
2. Collaboration of the project team
Speaking of the cooperation of the project team, I think we are doing badly at present. In the process of task execution, the current project team is like the Three Kingdoms period in ancient China-competing with each other and doing their own work. Every day we are very busy, but we are all busy with our own space, and there is too little time for communication and cooperation with each other. The realization of a functional module is not to seek business fit to the limit, but to scribble on one's own head, make one's own wheels, and impose one's consciousness on customers at all times.
In the past coding time, I always found that many colleagues had a problem, and the modules they made were related to the existence of others. At this time, they need simple communication and cooperation. But many people don't communicate, but write down other people's code and then submit it with their own needs. When their specific personnel find that their code has been modified without knowing it, they eventually encounter problems and pass the buck. This is the result of lack of communication.
Speaking of collaboration, by the way, division of labor, the most important thing in the process of code writing should be a clear division of labor. We need to strictly stipulate who has the right to modify related files, and those files need to be played before being deleted. Instead of blindly changing, deleting and adding when you are unhappy, have you considered the impact on its projects or others before operation?
Project manager's probation period summary. 2. Dear company leaders at all levels:
Hello! First of all, thank you for giving me the opportunity to work, grow and study in xx Property Management Company. During the one-month probation period, my main job is to be familiar with the environment, personnel and institutional processes. Through learning, I am familiar with the whole operation process of the company's projects. At work, I have always been strict with myself, earnestly and timely doing every task assigned by the leaders, and at the same time actively sharing worries for the leaders and giving good ideas; Ask colleagues modestly for questions you don't understand about the project, and constantly improve and enrich yourself. I hope I can integrate into my work as soon as possible and make greater contributions to the company. With the help of company leaders, all employees have been working for 1 month, and the work report during this period is as follows:
First, fully familiar with the company, project personnel environment, system process, feel the company's corporate culture:
When I joined the company, all employees in the company, under the leadership of the boss, were full of enthusiasm and enterprising, showing a vigorous corporate atmosphere. Encouraged by this good corporate culture, I quickly put myself into my work.
Second, correct mistakes and put forward reasonable suggestions:
Due to various reasons in the early stage, the work of the property management service center is relatively backward, especially in engineering maintenance. Through efforts to deal with them one by one, fully investigate and study, and scientifically and reasonably implement various matters explained by company leaders; Reasonably combine the property management characteristics of farmers' resettlement houses; On the premise of referring to the operating rules of the same industry, the property management of this project has been adjusted.
Three, standardize the management system, improve the project execution ability:
After taking over the xx project, talk with employees one by one to enhance understanding, and use regular meetings and temporary meetings for training, including national, provincial and municipal standards such as property management regulations, decoration, building quality standards and quality warranty period. Find problems and hidden dangers in the work, explain and learn to eliminate them in time, and improve and establish some rules and regulations on the basis of making good use of the original system:
1, decoration detection system;
2, the security department weekly service execution system;
3, cleaning service workflow allocation scheme;
After preliminary standardization and adjustment, every employee truly takes responsibility to people and rewards and punishments to people; Conduct regular training and assessment to effectively improve the professional service knowledge and skills of employees. At present, the service consciousness and customer service ability of the project staff have made great progress. After more than a month's work, although some achievements have been made, there are still some shortcomings. For example, the maintenance of other projects cannot be completely solved in time, and we are trying to solve them one by one. I believe that under the leadership of General Manager Ye and the support of company leaders, the work of Guilin Cuidao Property Service Center will definitely make greater progress.
Summary of project manager's probation period: 3. I joined the real estate company of XX Group on September 23rd, 20XX14th, and worked as the project manager at the project site of XXXX Department Store. It has been more than three months now. During these three months' work, with the strong support and guidance of the group real estate company, the project department has overcome many difficulties and it is extremely difficult to get to today. At present, the site is in the piling stage, and 46% of the pile foundation construction tasks have been completed. Although the next construction task is extremely arduous, I am confident and capable of completing the construction period of each stage. Next, I will summarize my work in 20XX for three months and my work plan for next year:
First, the preliminary construction preparation stage
As an investment promotion project in XX county, the XXXX department store project can basically get government support and help as long as it is conducive to the construction progress. However, before the smooth start of construction, the following work must be completed.
1, laying out the basement control line.
2. Building alignment.
3. The planning department shall conduct line inspection.
4. Submit the leveling points and coordinate control points provided by the surveying and mapping department to the general contractor. Organize the construction drawing design disclosure and blue prints.the design for foundation pit support twice.
6, pile foundation construction drawing design disclosure and the blue prints.the design.
7. The planning department shall provide the drawings of municipal pipelines around this project.
8. Assist to complete the expansion work of temporary power shortage on site.
9. Before construction, go through the quality supervision procedures at the quality and safety station.
Second, the construction stage
Before piling construction, the foundation pit earthwork has been dug to a depth of about two meters and five meters. Because there were no construction drawings at that time, most places were not excavated in place. Considering that there are enough working faces in the surrounding row of piles, it is necessary to cooperate with the earthwork excavation unit to dig out the remaining soil. For a long time, the earth excavation unit didn't cooperate with our work arrangement, kept antagonistic feelings with us, and even made trouble at the construction site, so the construction site work could not be carried out at the moment. Through our patient and meticulous communication, we learned the unit price of earthwork excavation in other local sites, and finally reached an agreement with the earthwork excavation unit through rewards. After the foundation pit is excavated for 2.5m, it will have a great impact on the site piling. The concrete truck can't drive into the construction site at all, and the surface of the foundation pit is covered with silt. Once it rains, the bearing capacity of silt layer drops sharply, and piling construction is very difficult. The general contractor will use this as an excuse that there is no condition of three links and one leveling on the construction site, which leads to claims for expenses and time limit. We made a decisive decision and actively organized the local construction unit to backfill the pond slag in the site, which ensured the need of piling construction in the site.
The hardest part is actually in the beginning After three weeks at the site, the general contractor still hasn't arranged for the pile driver to enter the site. It is also a fact that the general contractor has not received the formal construction drawing of pile foundation provided by us, which is not convenient for organizing machinery to enter the site. However, after we provided the blueprint for pile foundation construction on 10/5, the general contractor still failed to enter the pile frame. The general contractor encountered great difficulties in finding subcontractors, and found more than a dozen units back and forth, but they were unwilling to undertake this business. It was not until1October 22 that several piles were entered one after another. 1October 29th, the trial pile construction of podium and tower was started. The trial pile construction of podium was successful, but the tower ended in hole collapse after 6 days of trial drilling. The tower pile must enter the rock 1.5 meters, and the circulating drilling rig encounters pebbles with large particle size in the sandy pebble layer (the particle size of pebbles collected on site is close to 40 cm), which is easy to block the pipe.
Later, with the consent of the design unit, the tower recycling hole-forming process was changed to impact hole-forming process, and the general contractor organized six impact hammer drills to enter the site on 1 1 July 7. First try to make a hole in the north side of the tower, but the soil layer about three meters on the north side of the ground is quicksand. When lifting the hammer, the heavy hammer, quicksand and casing are pulled up together, which makes it very difficult to form a hole. In order not to delay the construction period of the tower pile foundation as much as possible, the pile test construction began on the south side of the tower, and the pile test began on 1 1 month1month 16, and the first concrete pouring was completed. However, due to the limited working face on the south side of the tower, only four piles can be placed for construction.
At the same time, we have not given up our efforts on the north side of the tower. After consulting various experts, we put forward some suggestions, such as dewatering first, and then arranging piling construction. The general contractor has successively carried out well point dewatering, shallow tube well dewatering, grouting and other strengthening foundation construction technologies, but none of them have achieved the required results. Geological factors on the north side affect the construction of about 60 pile foundations, and together affect the construction of about 70 uplift piles in the surrounding pure basement. The next step will be deep well dewatering, and then piling construction will be arranged. The task of pile foundation construction has been completed, including 57 towers and 1 15 pure basement piles, with a total of 349 piles (46%).
Three. 20XX work plan arrangement
The progress of pile foundation construction is lagging behind, and the main work in the next stage is to arrange work around earthwork excavation to ensure that the basement floor pouring is completed before the flood season. The main work arrangements are as follows:
1, 20XX 65438+1October 15 entered the site and started excavation.
2. Piling (including retaining piles) will be completed before the end of 20XX 1, but the next stage of piling construction and foundation pit retaining construction will not affect earthwork excavation. 20XX Earth excavation will be completed before March 20th, and the basement will be started in early March of 20XX, and completed on April 15.
3.20XX concrete structures below XX shall be completed before the end of May.
4.20XX Complete the concrete structure of the podium before the end of August.
This tower will be capped before the end of 20XX.
6. Electromechanical installation, curtain wall construction, secondary structure construction and fine decoration construction are carried out in the main structure construction.
Four, the current need to coordinate other work.
1. Provide a full set of construction drawings, and examine and approve the construction drawings.
2, fire, HVAC, weak current, hardcover, curtain wall, elevator and other subcontractors.
3. Determine the brand information provided by Party A and Party A. ..
- Previous article:Wedding layout scheme of residential property
- Next article:Total real estate development in Xiangtan (high score)
- Related articles
- What is the telephone number of Handan Yuefu Marketing Center?
- What is the telephone number of the sales office of Xining Qian Xin International Apartment?
- Ask for an accounting resume.
- Which bus should I take from Jingjiang Hongqiao Head to West Ring Green Air Conditioning?
- What is the sales service hotline of Nanning Long Yuan University?
- How to do a good job in community culture construction
- How about Shaanxi Branch of Xuanyuan Insurance Agency Co., Ltd.?
- Does Xiasha Baolong belong to Yunbin Community?
- Notice of Huangpu District on lifting temporary control measures in some areas of Huangpu Street, Luogang Street and Yonghe Street
- What is the address of Nanjing Fahua China Resources Land Vientiane Tiandi?