Job Recruitment Website - Zhaopincom - The commissioning time of Lanzhou No.2 Thermal Power Plant

The commissioning time of Lanzhou No.2 Thermal Power Plant

The thermal power plant was officially put into operation in February 1989.

The predecessor of Guodian Lanzhou Thermal Power Co., Ltd. is Lanzhou No.2 Thermal Power Plant, which is known as the "second heat". Although it has been renamed many times, the initial abbreviation of "Erre" has always remained in the mouths of countless Lanzhou people.

According to public information, Erre is a cogeneration project that was built by raising funds to realize urban central heating and improve the atmospheric environment during the Seventh Five-Year Plan period in Gansu Province. 1987, the second thermal power plant started construction; 1989,65438+February, officially put into operation for power generation; 199 1, 165438+ 10.