What should be included in the acceptance of diversion (river closure) of the hub project?

The acceptance of diversion (flow) shall include the following main contents:

1 Check whether the completed underwater works, concealed works and water diversion (interception) works meet the requirements of water diversion (interception);

2. Check the completion of construction land acquisition, resettlement and bottom clearing;

3. Review the river closure scheme and check the implementation and preparation of diversion (river closure) measures;

4. Check the implementation of engineering measures taken to solve problems such as navigation obstruction;

5. Identify the construction quality of completed projects related to river closure;

6. Put forward handling opinions on the problems found in the acceptance;

7 Discuss and pass the stage acceptance certificate.