How long is the construction period of Xu Long Hydropower Station?

The construction period of Xu Long Hydropower Station is 96 months.

According to the public bidding for dam construction supervision of Xu Long Hydropower Station, the total construction period is 96 months, the construction preparation period is 2 years, the main project construction period is 5 years and 8 months, the project completion period is 4 months, and the power generation period of the first unit is 7 years and 8 months.

Xu Long hydropower station project is one of the backbone power supply points of the country's power transmission from west to east, and its development task is mainly to generate electricity.