In the process of project supervision, it is mainly emphasized to control beforehand, give priority to prevention and nip in the bud. The following is a summary model essay on project supervision that I have compiled for you. Welcome to read it! Summary of construction project supervision (1)
Looking back and looking forward to the future, I have the joy of this year's harvest and the eager expectation for the future. The joy is that with the care and help of leaders and colleagues, I have carefully studied and understood the corporate culture spirit of the company, guided by the company's service concept, and through my unremitting efforts, I have successfully completed my own work and the tasks arranged by the leaders; The expectation is that I deeply understand that there are still many shortcomings to be learned and improved in the supervision work. I will sum up my experience, reflect on my own shortcomings, improve my supervision business level, and become a member of the company in the process of better and faster development. Now I summarize the supervision work this year as follows:
1. Personal annual main work materials and job responsibilities
In the first half of 2xx, I mainly participated in the on-site supervision work of soft foundation treatment project in the central business district of xx Development Zone, and in the second half. Proverbs of helping others
In this year's work, I obeyed the leadership's arrangement and earnestly performed my post responsibilities. During my work, I never relaxed and strengthened my study of theory and practice, strictly demanded myself, earnestly served the construction unit with enthusiasm, and fulfilled my supervision responsibilities in strict accordance with the supervision contract requirements and supervision norms and procedures.
during the construction process, the process control of each working procedure is carried out by means of standing by, patrolling and parallel inspection. Investigate and study the quality and safety problems existing in the site, find out the root causes of the problems, ask the construction party to take effective solutions to solve them, and follow up and supervise the construction party to implement rectification throughout the process to prevent similar problems from happening again.
for the materials (high-strength geogrid, geotextile, fence board, presser foot block, stepping stone, etc.) entering the site, the relevant inspection materials submitted by the construction party shall be checked according to the standards and design requirements, and the appearance quality of the materials shall be checked when they enter the site, and it is forbidden to use them in the project if the appearance quality does not meet the requirements.
during the construction of key parts of the project, arrive at the station position ahead of time, check the construction preparation, and keep a written record of the station during the whole construction process. Classic dialogue
The concealed works to be accepted shall be accepted in strict accordance with the acceptance specifications. If the acceptance is unqualified, it shall be rectified until it is qualified before the next working procedure can be carried out. Inform the project management department of the construction unit in oral or written form of the problems found during the inspection in each construction process, report the problems to the director in time, and urge the construction unit to carry out rectification and re-check the inspection. Do your best to do a good job of supervision in the construction stage of the project.
second, the experience and feelings in the work
in the process of supervision, through the study of supervision theory and the cognition of the development state of the supervision industry at this stage, I deeply realized that as a supervisor, taking the initiative to think about the interests of the construction unit, being responsible for the quality of the project and being responsible for the safety of the construction personnel are the beliefs and infinite strength of supervision work. Only with high professional skills, comprehensive quality and good professional ethics can we really do a good job of supervision and embody the practice principles of law-abiding, honesty, justice and fairness. Understand the importance of supervision work, establish a correct attitude towards supervision work, and deal with all kinds of problems in construction with a realistic attitude, so as to effectively carry out the work, actively use their professional skills and intelligence, exercise supervision rights and obligations scientifically and fairly, cooperate well with the construction unit, meet the requirements of the construction unit, and bring high-quality and efficient services to the owners.
III. Future work plans and personal career development opinions
As a young supervision worker, I love my job, have a good work style and hard-working spirit, and my work attitude is forbidden. I like to study the causes and solutions of problems in engineering supervision, and I am keen on the accumulation of solutions to engineering problems.
in the future work, earnestly perform their duties, and carry out supervision work in strict accordance with national standards and based on design drawings. In the work, we should constantly reflect on our own shortcomings, strengthen the study of supervision business, constantly improve our own quality, do a good job in supervision, strengthen the study of management theory knowledge, deal with practical problems flexibly, conscientiously complete all the work assigned by the leaders, and strive to raise our professional and technical level to a new level and truly become a qualified supervisor.
IV. Opinions and recommendations to departments/companies
1. Recommend companies to provide targeted professional training for different employees, and recruit more talents with professional qualification certificates who can work independently.
2. Recommend the company to organize talents with good public relations potential, and set up relevant departments to deal with the socialization of supervision industry and the openness and complexity of supervision bidding.
V. Conclusion
The care and support of the company leaders and the comfortable working conditions have given me the motivation to work hard. The warm care and cooperation among colleagues have given me a sense of comfort and sureness in my work, and the unique corporate culture atmosphere of the company has given me confidence in my work. I firmly believe that I can do better in my future work and contribute to the development of the company. Summary of construction project supervision (II) < P > I. General situation of the project < P > The business building project of X county government has a building area of 8,492.64 ㎡, a building height of 19.2 meters, and a five-storey frame structure, which is a multi-storey public building. The design life of the building structure is 5 years, the safety level is Grade II, and the seismic fortification is classified as standard fortification (Grade C); The design grade of foundation is Grade C..
at present, the foundation project of the X county government business building has been completed since it was started on April 6th. The main structure was capped at the end of July, and the masonry of the second and third floors has been basically completed. According to the project schedule, the masonry of the whole project was completed in October this year. Part of plastering and part of installation works will be completed by the end of this year.
the main building structure of the cadre turnover house project in X county: it is a four-story frame structure with a total construction area of 1965.24㎡, and it is a multi-story public building. The reasonable design life of the building structure is 5 years, the safety level is Grade II, the seismic fortification crack is Grade VII, and the foundation design level is Grade C..
since the construction of the cadre turnover room in X county started on July 6th, the foundation excavation has been completed, and the foundation pile caps and foundation frame columns have been completed. It is expected that the foundation will be completed by the end of July, the main body will be capped before mid-September, and the infilled wall and partial plastering will be completed before mid-October.
II. Work of supervisors
According to the requirements of the supervision service contract, after the two parties signed the supervision entrustment contract, the overall goal of project quality, progress and investment supervision was determined, and the project supervision department was established. According to the supervision contract and the Code for Supervision of Construction Projects, the supervision project list is decomposed, and the responsibilities of the chief supervision engineer and professional supervision engineer are defined. Make the supervision work institutionalized, standardized and standardized to ensure the smooth implementation of the supervision task.
with the strong support of the owner and the company, the supervision work of this project is progressing smoothly. In the whole supervision project, we strengthened and standardized the supervision's own management work, strictly implemented various rules and regulations, and ensured the quality of the project and the earnest implementation of the contract.
while strictly supervising, we aim at the problems in the construction of the project and the inadequate management. Intensified the intensity of "strict supervision" and strengthened the power of patrolling the sidelines; Put forward more reasonable suggestions, strengthen the "pre-supervision" and "active supervision". In the process of supervision, 1% of the hidden projects and key parts are on the sidelines, and the quality problems of the projects are eliminated in the bud.
iii. project supervision management
examination and approval of overall commencement report and sub-project commencement report: our supervision department strictly reviews the contractor's labor, materials and machinery input, the rationality and feasibility of the construction scheme, the specific measures to ensure quality and the construction of the contractor's quality inspection system in accordance with the requirements of ensuring the construction period and quality and meeting the contract conditions.
the handover of sub-project processes is an important part of supervision's daily work and control of engineering construction quality. The supervision department first conducts a comprehensive inspection of the previous process and confirms that it meets the relevant requirements after treatment, before it is allowed to transfer to the next process.
the supervision department has strictly checked the ex-factory quality certificate of the incoming materials of this project with the model, specification and ex-factory date of the incoming materials on site. After the arrival of raw materials, the contractor's re-inspection and supervision sampling inspection shall be carried out in strict accordance with the specified batch, so as not to miss the inspection and clarify the use parts of materials.
for the problems found by the station and patrol, the site shall be informed orally in time, and the construction unit shall be required to make rectification. If the problem is serious or the contractor fails to make rectification as required, the supervision department will issue a notice to the supervision engineer. All the quality problems found were rectified and improved under the supervision of the supervision department, and the instructions were closed.
iv. Project progress management
The overall construction progress plan, phased construction plan and monthly construction plan reported by the construction unit. The supervision department has comprehensively considered the requirements of the contract time limit for a project and the principles that are beneficial to the project quality. In view of the reasonable input of labor, materials and machinery required to complete the plan, the construction plan to ensure the completion of the contractor's plan and the quality assurance to ensure the completion of the plan, the supervision department has made a reasonable adjustment reply after detailed review. When the construction period is tight, the construction unit is required to reverse the construction period and the contractor is required to invest the necessary equipment, manpower, material resources and financial resources in a scientific organization and strict management to ensure the normal construction progress.
v. Construction of a clean government and safety management
The supervision department actively follows the requirements of the owner and superior departments in the aspects of clean government construction, civilized construction, safety and environmental protection. And organize relevant meetings regularly, so that every supervisor can carry out his work in an honest and fair manner. Monitor the implementation of safety measures and the results of rectification. Up to now, no safety accidents have occurred in this project.
in short, in the construction supervision work, we have grasped the important parts and key links, put prevention first, strictly controlled all the time, and ensured the quality. The project is safe and reliable, and meets the design and specification requirements. We will correct the existing problems in time with a rigorous and pragmatic working attitude, overcome the ineffective factors, intensify our work, and hand in a satisfactory project answer sheet for the owner! Summary of construction project supervision (III) < P > (I) Quality control < P > Adhere to the quality standards of decoration construction, strictly check, give priority to prevention, and strengthen process quality control. According to the supervision procedure of decoration quality control, according to the engineering-related standards, design documents and technical data of this major, as well as supervision planning and construction organization design, various supervision measures were taken to ensure the realization of the engineering quality supervision objectives.
1. Our supervision department has strictly reviewed the Construction Organization Design and quality assurance measures of the construction unit, ensuring the rationality of the construction scheme and the operability of the quality assurance measures. And organized professional supervision engineers to compile Supervision Planning, Station Supervision Scheme, Detailed Supervision Rules for Bored Piles, Detailed Supervision Rules for Main Works, Detailed Supervision Rules for Surveying Works, Detailed Supervision Rules for Elevator Construction, Detailed Supervision Rules for Decoration Works, Detailed Supervision Rules for Electrical Construction, Detailed Supervision Rules for Waterproofing Works, Detailed Supervision Rules for Fire Control Construction, Detailed Supervision Rules for Water Supply and Drainage Construction, etc. In the process of construction, the supervision department carries out supervision work in strict accordance with the requirements of design drawings, Construction Organization Design and Supervision Rules to ensure the effective supervision work.
2. Review the quality assurance system and management system of the construction unit, carefully check the technical qualifications of the main management personnel of the construction unit and the certificates of workers with special types of work, and urge the construction unit to do a good job in internal technical disclosure to ensure the full implementation of quality management.
3. Strictly control the quality of different decorative surfaces. For example, strictly control the empty drum phenomenon of ceramic tile paste; Control the pipeline layout height of hydropower, fire protection and air conditioning to meet the minimum requirements of suspended ceiling; Control the light steel keel hanger to be safe and reliable, and the coating anticorrosion meets the requirements; Control the ceiling shape and ceiling flatness to meet the requirements; Control the wall base, cracks and smoothness in accordance with relevant regulations; Control the level elevation, and the color, specification and mosaic pattern of floor tiles meet the design requirements.
4. Strictly review the use of engineering materials to prevent unqualified engineering materials from being put into use, especially the quality assurance materials required by the construction unit. For the unqualified materials found by witness sampling inspection, such as: roof floor tile (Yuexiang ceramic tile 5×5×8mm), bathroom floor tile (Zhenpeng ceramic tile 3×3×7mm), bathroom waterproof coating (polyurethane 911 waterproof coating) and other unqualified materials, our supervision department will follow up and make graphic records.
5. The supervision engineer made a patrol and acceptance check on the process quality, and found out the problems exposed in the construction in time, such as uneven latex paint on the decorated wall, empty floor tiles, uneven waterproof floor in the bathroom and other quality problems, and issued a notice to the supervision engineer in time, requiring the construction unit to rectify.
6. For the suppression test of fire fighting and air conditioning engineering, the supervision engineer insisted on being on call 24 hours a day, and kept on standby for the whole construction suppression process to ensure that all the equipment met the design requirements.
7. For the whole project, our supervision department * * * issued 24 supervision engineer notices, 39 regular engineering meetings and 1 special meeting minutes.
(II) Schedule control
1. After the supervision department enters the site, check whether the preparatory work of the construction unit in the early stage is sufficient, and confirm whether all equipment conditions are complete and whether all construction machinery, equipment and personnel are in place.
2. Strictly review the progress plan prepared by the construction unit, and the supervision engineer conducts on-site inspection and supervision every day to keep abreast of the implementation of the tracking progress plan, coordinate and solve the exposed problems in time, and coordinate and handle various internal and external relations to ensure the smooth progress of the construction.
3. Analyze and compare the schedule deviation in time, find problems from it, and ask the construction unit to take necessary adjustment methods and management measures in time.
4. Through the regular meeting of the project, report the daily construction completion of each construction unit and the failure to complete according to the construction plan, and solve the problems of mutual coordination and outsourcing conditions in the construction.
5. according to the requirements of the construction contract, timely verify the quantities of completed subdivisional works declared by the construction unit, and issue the payment voucher for the progress payment to ensure that the project payment is in place in time.
6. Organize the project progress data at any time, make records of project supervision, and require all construction units to report the construction data simultaneously.
(III) Investment control
Before the construction, carefully study the drawings, and strictly control the on-site visa and
- Previous article:How about Yihai (Jiamusi) Grain and Oil Industry Co., Ltd.
- Next article:How about Dezhou Huatang Food Co., Ltd.
- Related articles
- What health schools are there in Deyang?
- What are the precautions for the second landlord to rent a house?
- Zhejiang talent code classification standard
- Is it easy to find an immigrant job in Fiji?
- Has the Liulian subway station been opened?
- Which is better, Suzhou Yike or Hua Ting?
- How is the industrial market of Jianmen in Huxian County?
- Why does JD.com always recruit webmaster assistants?
- Sanya Luxun Middle School Score Line 2023
- Handling the qualification process of power transmission and transformation project