Job Recruitment Website - Job seeking and recruitment - How to arrange the construction period? The most detailed decoration period guidance.
How to arrange the construction period? The most detailed decoration period guidance.
Example of construction schedule 1
The following is a short timetable example:
March 65438 +06-23:
1, the bathroom and bathroom walls are paved;
2. The furniture is well painted
3, windowsill stone pavement
4, metope batch again putty
April 23rd-May 15:
1, on April 23rd, batch of wall putty twice.
2. On April 25th, the wall putty was approved for three times.
3. Grind and install the kitchen sliding door on April 30th.
In April and May 1, brush the wall primer again.
5. Floor tiles for balcony and living room began to be laid on May 3rd.
6. On May 8th, paint the wall.
7.5 10 wall painting.
Kitchen cabinets will be installed on May 1 1 day.
September 5 12, install the floor of the room.
10, May 13, doing sanitation.
Hand over the house for acceptance on May 15.
This schedule is rough, and there are also various construction projects, construction time and personnel in the detailed schedule. The foreman's purpose in providing the owner with this progress plan is to let the owner know the basic arrangement of the construction period, such as when the water circuit transformation, wood sealing, tile pasting, ceiling keel making and so on will be completed this month. In this way, the owner can arrange his own time reasonably and regularly check the quality at important steps. If the foreman does not take the initiative to provide the owner with the time limit for a project schedule before entering the site, the owner must personally ask the foreman, otherwise the owner will only feel unlucky if the time limit for a project is delayed or important links cannot be accepted in time in the future.
Example 2 of construction schedule
How should the owner arrange the construction period?
It takes about 45 days to decorate a three-bedroom apartment of 140- 150 square meters. A small two-bedroom apartment with a smaller area can save four or five days, and a duplex apartment of more than 200 square meters needs four or five more days. The process of house decoration can be divided into three stages: prophase, metaphase and anaphase.
The pre-renovation work is mainly decoration design. It takes 10- 15 days from choosing a decoration company to determining the design scheme. During this period, customers must choose the main materials for decoration, especially tiles and cabinets. Because cabinets are generally customized, it takes 20-35 days to complete. Professional cabinet designers should also design the kitchen according to the actual situation, such as determining the position of water circuit, so as to carry out hydropower transformation in time after construction. Tiles are used after construction, so in the early stage of decoration, cabinets and tiles must be selected first.
The middle period of decoration is mainly the construction period. After the construction begins, plumbers and carpenters will go to the advanced construction site for construction. It takes 4 days to a week to rebuild the water circuit, and it takes about 15 days for carpenters to make ceilings, background walls and cabinets on site. About 7 days later, the water circuit was rebuilt and the bricklayer began to lay tiles. First lay the kitchen and bathroom, and then lay the public parts. The whole process lasted until about the 30th day. About 15, the carpenter finished his work, and the painter began to enter the site. The work of leveling the wall, painting the wood and painting the wall will last for two or three days before the decoration is completed. During this time, you can look for your favorite furniture in the market.
Owner's construction schedule
1. At least 10 days before commencement; Formulate the design scheme; Select the decoration company and put forward the decoration content and requirements; Measure relevant data on the spot and draw detailed drawings; Communicate with designers in an all-round way to determine the final plan.
2. At least 5 days before the start of construction: sign the contract according to the budget; Determine the materials to be used; Do a good job in the preliminary budget of home improvement expenses and compare it with the budget of home improvement companies; Sign the renovation contract.
3. At least 2 days before construction; Make preparations before entering the site; Contact the property department and complete the necessary procedures; Say hello to neighbors; Door and window materials and auxiliary materials come into play; Hand over the key of the construction party; Pay the down payment for the decoration.
4.65438+ 0-2 days after construction: knocking on the wall to change the structure.
5.5- 10 Commencement days: installation of water pipes and circuits; Handling and acceptance of pipeline materials; Acceptance of concealed works.
6. 10- 20 days after construction: stick on the wall; Acceptance of mud tile project; Acceptance of wall materials, such as wall paint, tiles, etc.
7.20-30 days construction: carpentry and painting; Acceptance of paint materials; Acceptance of woodworking projects.
8.30-50 days construction: the kitchen and bathroom equipment shall be laid with floor; Acceptance of floor materials; On-site installation and acceptance of cabinets; On-site installation acceptance of sanitary ware products; Buy back electrical appliances and install them; On-site installation and acceptance of sanitary products.
9. 50-60 days after commencement: acceptance and final accounts; Perform summary calculation.
Decorative process
1. Masonry: trenching (used for hydropower lines and concealed works), tearing down walls (changing walls according to design requirements, etc.). ).
2. Plumber: threading and wiring of waterways (water supply and drainage), circuits (strong and weak electricity) and gas circuits (gas).
3. Masonry works: civil works (wall building, repair, etc. according to design requirements). ), wall and floor tile surface decoration (ceramic tile).
4. Woodworking: all wood products (furniture, wall decoration, ceiling, etc.). ) According to the design requirements.
5. Painter: furniture paint and wall paint (of course, the wall may also be covered with wallpaper)
6. Installer: Installation of finished products such as sanitary wares and lamps (such as shower room installation and glass installation).
7. Cleaner: Clean up the whole land.
Pay attention to the arrangement of decoration period.
1. The decoration schedule should be detailed, including various construction projects, construction time, personnel, etc.
2. The owner can ask the decoration company about the schedule of the decoration period, and have a basic understanding of the arrangement of the family decoration period, such as when to complete the water circuit renovation, wood sealing, tiling, ceiling keel production and so on this month. In this way, the owner can arrange his own time reasonably and regularly go to the site for quality inspection of important steps.
3. Different housing types, areas and construction contents require different construction periods. Generally speaking, oil workers are time-consuming and should not be rushed. Generally, the construction period should be controlled within 45 days. Generally, the flat floor of two bedrooms can be completed in 40 days, but it is not very plentiful. To arrange the process and main materials.
- Related articles
- Don't say you don't know! Three new car brands have been born, and the first two are a bit fierce!
- How do ordinary printers print fixed format stickers?
- Brief introduction of Qingdao talent recruitment network
- What is the general salary of locksmiths?
- Which is better, Yancheng Rongyuehua Building or Zhonghai Wanjin Building?
- What are the routines for insurance companies to recruit sales staff? How to avoid being fooled?
- Where is the open recruitment announcement of Shandong prison guards in 2022?
- What are the large enterprises in Hubei?
- Which Beijing Otolaryngology Hospital is the best?
- Working hours of Cuiqiao liquefied gas station