Waterproof engineering construction contract

Chapter 1: Construction Contract of Building Waterproofing Project

Employer: Beijing Guojia Deyu Technology Construction Co., Ltd.? (hereinafter referred to as Party A)

Contractor:? (hereinafter referred to as Party B)

According to the Construction Law of People's Republic of China (PRC), the Economic Contract Law of the People's Republic of China and the specific conditions of this project, Party A and Party B sign this contract through consultation, and both parties shall abide by it.

1. Project name and address: Office of the Ombudsman of Shaanxi Ministry of Finance (Cai Zhong Building)

Second, the scope and content of the project: the roof is 4mmSBS waterproof, and the original protective layer is removed. A newly made protective layer.

Third, the way of contracting: contracting for labor and materials

Four. Material: product name, specification and grade.

5. Project cost: RMB per square meter (including auxiliary materials and labor costs), which will be settled according to the actual area after completion. The construction area is square meters, and the total project cost is RMB Yuan only.

Duration of intransitive verb project: commencement date.

Completion date (postponed due to rain)

Seven. Settlement method: When materials and personnel enter the site, Party A confirms that they meet the contract requirements and pays the total project price? Pay after the completion experience is qualified, and the rest will be paid in one lump sum after one year as quality guarantee.

Eight. Responsibilities of Party A and Party B:

1. Party A shall provide Party B with written materials related to the design drawings of this waterproof project, and Party B shall carry out the construction according to the design standards and construction technology and the notice of commencement issued by Party A.

2. Before the construction within the scope of this contract, Party A and Party B shall jointly check and inspect the quality and site construction conditions of the previous procedure, and Party A shall be responsible for solving the situation that affects the waterproof construction of the previous procedure.

3. Party A shall create conditions for Party B's warehouse, and Party B shall respect Party A's jurisdiction and relevant rules and regulations, accept Party A's supervision and management, and ensure civilized and safe construction.

4. Party B shall provide Party A with relevant copies of the construction as required, and report the progress and quality of the project to Party A in time. Party A shall timely check and accept the progress and quality of Party B. ..

The warranty period of this project is three years. In case of leakage caused by Party B's construction or materials during the warranty period, Party B will immediately organize construction personnel to rush to the site for maintenance within the specified time after receiving the notice, and do their best to do a good job of service during the warranty period without any remuneration. Party B shall not be responsible for the damage to the waterproof layer caused by Party A's improper use or natural disasters.

Nine. Other agreements:

1. In case of expansion joints, settlement and other special-shaped waterproof projects during construction, the construction shall be carried out according to the national building waterproof standards, and the price shall be determined by both parties through consultation.

2. Party B shall complete the construction task as scheduled. During the construction period, due to the influence of climate and the limitation of on-site construction conditions, Party A and Party B shall coordinate in time, and the contract period shall be postponed accordingly. If Party A fails to pay according to the contract, thus affecting the construction period, Party A shall bear the responsibility.

3. During the construction period, Party B's personnel shall unconditionally obey Party A's safety management, but Party B shall improve the safety awareness of construction personnel by itself. If Party A's safety facilities are not suitable during the construction, and Party B does not raise any objection, the economic losses caused by the construction shall be borne by Party B. ..

4. During the construction period, Party A may conduct random inspection of materials, and the inspection fees of authoritative organizations shall be borne by Party A. ..

5. For matters not covered, Party A and Party B may negotiate at any time and sign a supplementary agreement as an annex to this contract.

6. This contract is made in duplicate, with each party holding one copy. This contract is valid for a long time from the date of signing.

Party A: Beijing Guojia Deyu Technology Construction Co., Ltd.

Party B:

Legal representative or client:

Address: Xinyuan International Building, No.5 Chengshousi Road, Dafengtai District, Beijing

Address:

Telephone:? 0 10-67909500? Telephone:

Chapter II: Waterproof Project Construction Contract

Employer: Company (hereinafter referred to as Party A)

Contractor: Chemical Corporation (hereinafter referred to as Party B)

After Party A's examination of Party B's construction professional qualification, it is agreed to entrust Party B to undertake the construction of XX waterproof project of our company. In order to clarify the rights, obligations and responsibilities of both parties in the construction process, and in accordance with the principle of ensuring project quality, project progress and project safety, the following contract terms are determined through consultation for common compliance and implementation.

I. General principles

1. Project name: Buildings 2 and 3 of Meilin production and living base of the company.

2. Project location: in the compound of Shanghai Meilin Shenhua Stone Company.

3. Project content:

According to the requirements of the company's xx project construction contact list and design change notice, polymer cement-based waterproof coating (1.5 thick) is used for kitchen and bathroom waterproof engineering, and polyurethane "85 1" waterproof coating is used for roof waterproof engineering (leveling layer is used for basic treatment).

Second, the way of contracting:

The general contracting mode of Party B includes contracted projects, materials, quality, management, safety and progress.

Third, the project cost:

Polymer waterproofing between kitchen and bathroom is 20 yuan per square meter; Roof "85 1" polyurethane waterproof per square meter 28 yuan. According to the actual area of settlement.

Fourth, the quality standard:

Party B shall ensure that the waterproofing works of Building 2 and Building 3 of Meilin Life and Production Base of the Company reach excellent standards, strictly refer to the new Guangdong waterproof engineering standard DBJ 15- 19-97 and the current relevant standards in Shenzhen and Party A's requirements, and ensure that the coating works are not peeling, hollowing, delaminating, dew-free, flat and uniform, and have certain adhesion with the base.

Verb (short for verb) Responsibility of both parties:

1. Party A's responsibilities:

(1) Put forward the construction plan in advance, arrange the working face to meet the waterproof construction standard, and submit it to Party B for construction.

(2) The construction period plan should be put forward, but the construction period should be postponed in consideration of the inevitable factors such as weather and manpower.

(3) Cooperate with Party B in construction, such as providing necessary on-site vertical transportation and workers' accommodation.

(4) Party A has the right to supervise and inspect the engineering quality of Party B during the construction process, and ask Party B to make rectification within a time limit if problems are found.

2. Party B's responsibilities:

(1) Party A informs that the waterproof material will enter the site immediately, and submit the waterproof material certificate, test report and license issued by Shenzhen Construction Bureau, which will be used after the on-site person in charge of Party A passes the sampling inspection. If necessary, Party A will select the municipal "Engineering Institute" and use it after it is qualified.

(2) Cooperate with the overall progress of Meilin Living Base of Urban Construction Company, and carry out the construction according to the construction plan put forward by Party A. Except for inevitable factors, there shall be no artificial delay.

(3) Party B shall abide by the rules and regulations of the construction site and shall not violate the rules, otherwise it will be punished by Party A in various forms.

(4) Construction shall be carried out in strict accordance with waterproof engineering standards. If problems are found, solve them in time to ensure the quality of the project to reach excellent standards. The project is guaranteed for three years.

Terms of payment for intransitive verbs:

There is no advance payment for this project, and Party A shall pay the progress payment according to Party B's progress. After all the projects have passed the completion acceptance and reached the excellent standard, Party A shall pay 95% of the total project price to Party B, and keep 5% of the project price as warranty money. After the expiration of the three-year warranty period, if Party B has no quality problems, Party A shall pay the balance.

7. This contract is made in duplicate, one for each party, with the same legal effect. After the expiration of the three-year warranty period, this contract will automatically become invalid after Party A pays off the balance. Matters not covered shall be settled by both parties through consultation.

Party A: (signature) Party B: (signature)

Representative: representative:

Chapter III: Waterproof Project Construction Contract

The Employer (hereinafter referred to as Party A):

Contractor (hereinafter referred to as Party B):

After Party A's evaluation of Party B's construction professional qualification, it is agreed to entrust Party B with the waterproofing project of XX New Town Phase I 1#, 2#, 3#, 4#, 6#, 7#, 8#, 9#, 27# and 28#, in order to clarify the rights, obligations and responsibilities of both parties in the construction process and ensure the project quality, progress and quality.

I. General principles

1. Project name: XX New Town Phase I 1#, 2#, 3#, 4#, 6#, 7#, 8#, 9#, 27# and 28# buildings.

2. Project Location: XX New Town Construction Site

3. Project content:

According to the drawings of design institute, construction contact list and design change notice, single-layer 300g polyethylene polypropylene polymer waterproofing membrane is used for kitchen and bathroom waterproofing project, and double-layer 400g polyethylene polypropylene polymer waterproofing membrane is used for roof waterproofing project.

Second, the way of contracting:

The general contracting mode of Party B includes contracted projects, materials, quality, management, safety and progress.

Third, the project cost:

Kitchen and bathroom per square meter 14 yuan; 28 yuan per square meter of roof. According to the actual area of settlement.

Fourth, the quality standard:

Party B shall ensure that the waterproofing works of XX New Town Phase I 1#, 2#, 3#, 4#, 6#, 7#, 8#, 9#, 27# and 28# meet the excellent standards, and strictly refer to the national waterproofing codes and standards, current relevant provincial and municipal standards and Party A's requirements to ensure that the waterproof layer is free of peeling, hollowing, delamination and dew point.

Verb (short for verb) Responsibility of both parties:

1. Party A's responsibilities:

(1) Put forward the construction plan in advance, arrange the working face to meet the waterproof construction standard, and submit it to Party B for construction.

(2) The construction period plan should be put forward, but the construction period should be postponed in consideration of the inevitable factors such as weather and manpower.

(3) Cooperate with Party B in construction, such as providing necessary on-site vertical transportation and workers' accommodation.

(4) Party A has the right to supervise and inspect the engineering quality of Party B during the construction process, and ask Party B to make rectification within a time limit if problems are found.

2. Party B's responsibilities:

(1) After receiving the notice from Party A, the waterproof material will be put into the site immediately, and the waterproof material certificate, test report and license will be submitted, which will be used after sampling inspection by the person in charge of Party A's site, and Party A will send it to the laboratory for inspection if necessary.

(2) According to the construction plan proposed by Party A, there shall be no artificial delay except for inevitable factors.

(3) Party B shall abide by the rules and regulations of the construction site and shall not violate the rules, otherwise it will be punished by Party A in various forms.

(4) Construction shall be carried out in strict accordance with waterproof engineering standards. When problems are found, solve them in time to ensure the quality of the project to reach excellent standards, and the project is guaranteed for five years.

Terms of payment for intransitive verbs:

There is no advance payment for this project, and Party A shall pay the progress payment according to Party B's progress. After all the projects have passed the completion acceptance and reached the excellent standard, Party A shall pay 95% of the total project price to Party B, leaving 5% of the project price as the warranty money. After the expiration of the five-year warranty period, if Party B has no quality problems, Party A will pay the balance.

7. This contract is made in duplicate, one for each party, with the same legal effect. Upon the expiration of the five-year warranty period, this contract will automatically become invalid after Party A pays off the balance. Matters not covered shall be settled by both parties through consultation.

Party A: (signature)? Party B: (signature and seal)

Representative: representative: