Job Recruitment Website - Job seeking and recruitment - Recruitment examination questions of production manager at construction site

Recruitment examination questions of production manager at construction site

"Building safety" answers a multiple-choice question

1a; 2℃; 3b; 4a; 5b; 6、A; . 7 D

Second, multiple choice questions

1 A,D; 2. A, B, C and E

Third, if there is any problem.

Case 1 Answer: (1) Summary table

Calculation method of actual score:

Real collapse score = (the sub-item should be scored in the summary table × the actual score is in the sub-item inspection score table) ÷ 100.

"Safety management" score = 10×82÷ 100 = 8. 2 points

"Civilized construction" Yashi score = 20×84÷ 100 = 16. 8 points

The score of "Three Treasures" and "Four Guarantees" 10× 85 ÷ 100 = 8.5 points BR/> The score of "Construction Equipment" is 5× 78 ÷ 100 = 3. At 9 o'clock, the fault was "lifted"

(2) In each sub-summary table, if there is more than one score when viewing the score table, then this score is the personal arithmetic average, and there should be a solid result.

Scaffolding score =(86 +80)÷2 = 83.

Translated into summary table, the score is = 10×83÷ 100 = 8. three?o'clock

(3) If there is any omission in the sub-table, the calculation method of the scoring table is as follows:

Missing Item Sub-table = (actual value of inspection item, actual score of inspection item/actual value that should be scored) × 100.

& gt Ensure that the project is used up, the subtotal score is below 40, and the scoreboard is zero.

Missing items in the table = [66/(100-20)] ×100 = 82. Five points.

Summary of distribution scores under construction = 10×82. 5100 = 8,25 points.

If the true total score of other "guarantee items" is 20,20/40 = 50% 40/60 = 66.7%, the sub-list cannot be scored, that is, it is always zero.

(4) The total score of this project is 8 1.85. Check whether the security level is excellent.

[Case 2] A:

(1) According to the Regulations of the Ministry of Construction on Reporting and Investigation Procedures for Major Accidents in Projects, these projects with serious accidents can be defined as Class III major accidents. The above Regulations are generally Article 3: In case of a serious accident of Grade III, one of the following circumstances occurs:

(1) More than three people died and less than nine people died;

② More than 20 people were injured;

(3) The direct economic loss is more than 300,000 yuan but less than 6,543,800+0,000 dollars.

(2) The cause of this accident is because:

(1) full-time personnel responsible for lifting operations, in violation of the provisions of production safety, lifting operations seriously overloaded.

② Safety management is not in place and rules and regulations are not implemented.

③ Conduct safety training and education for workers who lack knowledge and discipline.

(4) to supervise the operation and safety of mechanical equipment.

(3) The main forms of safety inspection are:

(1) Organize regular safety inspection once a week or every ten days under the guidance of the principal.

(2) Before going to bed every day, the team leader and the organization's security personnel shall conduct safety inspection, and the construction team shall be on duty.

(3) Organize full-time production management personnel, safety personnel's security, labor protection and pre-season safety inspection through responsibility letters.

(4) safety management team, staff functions, full-time security guards, and professional and technical personnel are responsible for special safety inspections such as electrical, mechanical equipment, scaffolding, climbing facilities, special facilities and equipment, aerial work, electrical safety and fire prevention.

(5) It is composed of members of the safety management team, part-time safety officers, and security personnel on duty for daily safety inspection.

6. After the installation of crane and other lifting equipment, derrick, gantry, scaffolding, electrical equipment, hanging basket, cast-in-place concrete formwork and auxiliary facilities, safety inspection and inspection shall be completed.

[Case 3] A:

The (1) cause of this accident is because:

(1) The construction personnel violated the safety rules and laid seriously overloaded materials, which led to the welding of load-bearing beams during the intermission and the stability of the platform decreased.

(2) It is not enough to weld the I-beam, but only the stiffening plate, resulting in insufficient overall strength.

(3) The safety inspection was not detailed and the accident was not found in time.

④ The platform burden of safety rope is unreasonable, and it can't play an insurance role. (2) The project manager shall organize regular inspection of the construction project.

The contents of safety inspection mainly include inspection system, mechanical equipment, safety inspection equipment, safety education and training, business behavior, use of personal protective equipment and treatment of injured people.

(3) Standard for Safety Inspection of Building Construction 17 Inspection Score Sheet. That is, safety management inspection score table, civil construction inspection score table, scaffold inspection score table outside the building, cantilever scaffold inspection score table, portal scaffold inspection score table, hanging basket scaffold inspection score table, formwork engineering safety inspection score table, excavation safety inspection score table, "three treasures" and "four haves" protection inspection score table, and electricity consumption inspection score table. Material hoist (gantry, tic-tac-toe frame) inspection score sheet, external elevator (elevator dual-purpose goods) inspection score sheet, crane inspection score sheet, lifting operation safety inspection score sheet, construction equipment inspection score sheet.

(case 4) A:

(1) The method of safety inspection is:

"Look": mainly check the management records, certificates, site identification, data transmission and acceptance, the use of "Three Treasures", the protective devices of equipment under the protection of "holes" and "limbs".

"Quantity": It mainly measures the quantity of a real ruler.

"Test": This instrument carries out field measurement.

"Real Action": It is suitable for all kinds of device drivers with practical action limitations, and its sensitivity is tested.

(2) The matters needing attention in safety inspection are:

(1) safety inspection, at the grass-roots level, closely rely on employees, adhere to the principle of combining leadership with the masses, and organize inspections.

(2) Establish organizational leadership, inspection and appropriate inspection efforts, and select skilled business personnel to participate in a higher level.

(3) check all preparations, including ideas, business knowledge, laws and policies, check equipment, and prepare bonuses. Purpose and requirements

(4) Clear inspection.

⑤ Combination of self-examination and peer review.

⑥ Adhere to the combination of seeking change.

⑦ Establish inspection files. ..& ltBR /:

Today, when making a safety checklist, the safety checklist should be based on the specific purpose and use of the tree species.

(3) The main provisions of the project manager's safety inspection system should be clear >: Check the implementation of safety control ① Plan, record, evaluate and evaluate, and issue regular safety rectification notices for work behaviors and safety risks. After the relevant departments formulate the reform plan and implement the rectification measures, they should review and implement the rectification.

(2) According to the characteristics, requirements and safety objectives of the construction technology, which safety inspections are determined. (3) The safety inspection shall be equipped with necessary equipment or appliances, which shall be found by the person in charge of the inspection and the inspectors, and the inspection methods and requirements shall be defined.

④ Take random sampling, on-site observation and on-site inspection, record the test results, and correct the illegal command and operation.

⑤ Analyze the inspection results, determine the potential safety problems and determine the degree of risk.

⑥ Safety inspection report and report writing.