What is the detailed process of examination and approval of construction permit (unit)?

You can learn from it.

1. Necessary materials for handling the construction permit (except 1 8, the following materials shall be submitted as originals, and the remaining materials shall be submitted as copies (A4 paper) after verification; A copy must be stamped with the official seal of the reporting unit, and indicate the storage location of the original; Please bind in the following order, and the drawings should be folded according to the samples provided by the lobby):

1. Construction Permit Application Form in duplicate (the contents should be completely filled in, and the application statement should be filled in the column of "Applicant": "Commitment to the authenticity and validity of the application materials, stating that the construction land has not been sealed up, and now the construction permit is applied for", and the legal person of the construction unit should identify and stamp it) (window of the Construction Committee of the approval hall:

2. Approved project quality supervision registration form (the quality supervision fee is calculated at 65438+ 0.8‰ of the project price) (submit the original tender and get the form at the window of the Municipal Construction Committee in the examination and approval hall.

3, the building (demolition) project safety construction measures for the record form "audit (approval hall is built appoint window or city is built appoint safety supervision department:

4. Application report for commencement (signed by the person in charge of construction, supervision and construction and stamped with the official seal of the unit)

5, real estate development project agreement (only real estate development projects need to be handled) (Development Department of the Municipal Construction Committee or the Office for Ageing:

6. Unified bill of labor insurance fee for construction and installation projects [issued by Nanning Jian 'an Engineering Labor Insurance Institute (or labor insurance institutes of cities and development zones), and paid by the construction unit to the account of the municipal labor insurance institute at 2% of the bid price (see the Registration Form for Paying Labor Insurance Fee for Jian 'an Engineering, downloaded from Nanning Construction Information Network)] (Municipal Labor Insurance Institute:

7. Accidental injury insurance certificate and terms for construction personnel (the construction unit shall apply for insurance with an insurance company, and the insurance shall be anonymous, regardless of the number of people, covering all personnel engaged in construction operation and management on the construction site, and calculated according to the bid-winning rate in the project. The minimum compensation amount is 654.38 million yuan for accidental injury insurance and 20,000 yuan for accidental injury medical insurance).

8, migrant workers wage security card [unified payment of migrant workers wage security special account (name: Nanning Municipal Finance Bureau; Account number: 210210912930001501; Bank of deposit: ICBC Urban Construction Sub-branch), and after receiving the account, issue a payment voucher to ICBC (the first floor of Chuangning Building, No.76 Dongge Road) entrusted by the Municipal Finance Bureau. The construction unit pays 2% of the bid price, and if the deposit exceeds 800,000 yuan, it pays 800,000 yuan, and the fourth original of the payment voucher; The construction unit shall apply for Nanning migrant workers' wage guarantee certificate in accordance with N.F.F. [2007] No.51Opinions on Perfecting the Wage Guarantee System for Migrant Workers in the Construction Industry, and the construction department shall issue a Letter of Deposit for Migrant Workers' Wage Guarantee to verify the amount paid by the enterprise and a certificate of project payment (the certificate of funds provided shall be issued within the last three months); If the construction period is less than one year, the funds in place shall not be less than 50% of the project contract price in principle, and if the construction period is more than one year, the funds in place shall not be less than 30% of the project contract price in principle).

9, the project land approval procedures (state-owned land use certificate, mortgage registration certificate within the validity period of the original) (City Land Resources Bureau window: and the construction project planning permit (certificate within the validity period of the original, attachments and drawings) (City Planning Bureau window:

10, bid-winning notice (for projects that can be directly contracted out, contract-issuing audit notice shall be provided) (special seal for construction project filing of Nanning Construction Project Bidding Supervision and Management Office shall be affixed) (Municipal Bidding Office:

Second, matters needing attention:

1, for projects with an investment of less than 1 10,000 yuan, apply for a construction permit at the Municipal Urban Construction Bureau; The projects of Qingxiu Mountain Management Committee, Xiangsihu New District, High-tech Development Zone, Economic and Technological Development Zone and Overseas Chinese Investment Zone shall be handled by the Development Zone Construction Bureau (or Management Committee).

2, is to complete the construction permit procedures need to provide information such as instructions or loss statement and punishment certificate;

3, according to the relevant provisions of the document number. The State Council Guofa [2004] No.78 stipulates that if the construction unit refuses to cooperate with the debt settlement work and evade the repayment responsibility, it will be regarded as that the project construction funds have not been implemented, and our Committee will not handle the construction permit for its new project.

4. Real estate projects must log in to the real estate market information system as required and truthfully fill in the project information.

5. The project name, construction unit, construction unit, building area, structure type (in which special attention should be paid to the description of floors: floors include or exclude jumps, sundries and overhead floors) specified in the submitted bid-winning notice (or contract approval notice), Construction Project Quality Supervision Registration Book and Construction Project Planning Permit should be consistent; The construction area and structure type shall be subject to the matters specified in the construction drawing review and filing procedures. Without the permission of the issuing authority, the contents of the construction permit shall not be changed.

6. After obtaining the construction permit, the construction shall be started within three months from the date of issuing the certificate. Overdue, go through the formalities of extension (the extension is limited to two times, and each time shall not exceed three months). If the extension is not handled or the number and time exceed the legal time, the construction permit will be automatically invalidated.

7. Since the date of issuance, the validity period of the construction permit is one to three months according to the calendar days of the construction period specified in the bid-winning notice; Invalidated from the date of expiration of the validity period; If it is not completed within the time limit, it shall apply to the issuing authority 30 days before the expiration of the construction permit. Failing to apply for extension within the time limit, the construction permit shall be cancelled according to law.

8. The construction administrative department may examine the construction permit; Any unauthorized construction without obtaining a construction permit is illegal construction and will be punished according to the provisions of the Construction Law of People's Republic of China (PRC).

9. Temporary construction projects are not applicable to the Measures for the Administration of Construction Permit of Construction Projects.

Three, before the project starts, you should go through the relevant formalities in the following departments as soon as possible:

1, fixed assets investment new construction registration form (Municipal Bureau of Statistics

2, a construction waste disposal certificate (Urban Council

3, the construction site noise emission application form (Municipal Environmental Protection Bureau

4, the project environmental impact assessment report approval

5, lightning protection device design audit opinion

6. Proof of paying special funds for bulk cement

7, seismic fortification administrative licensing examination and approval

Four. Commitment time: 8 working days