20 19 Longyan shantytown renovation planning and compensation standard for shantytown renovation

Xinluo district Municipal People's Government and the units directly under the municipal government:

With the consent of the municipal government, we hereby print and distribute the implementation plan for the transformation of shantytowns (dilapidated houses) in Suxi community to you, please earnestly organize the implementation.

the people's government of longyan municipality

March 65438, 2006

(This film is voluntary)

Implementation plan of shantytown (dilapidated house) reconstruction in Suxi community

In order to further accelerate the transformation of shanty towns (dilapidated houses) in the central city, improve the living environment of residents and enhance the city's taste, the following implementation plan is formulated in combination with the actual situation:

I. Overview of the Project

The renovation scope of Suxi community shanty town (dilapidated house) project is about 302 mu, with a total area of 660,000 square meters, east to sports center, south to Shiluogu Park, west to xi 'an South Road and north to Gaodeng West Road.

Second, the work objectives

The project is organized and implemented in three stages. The first phase of the project is about 29 mu south of the sports bureau and 24.6 mu south of the customs dormitory, totaling about 53.6 mu. * * * About 80 houses are involved, and it is planned to start construction in June 65438+ 10 and complete it in June 65438+ 10; The second phase of the project is planned to start in February 65438 and be completed in February 65438. The third phase of the project is scheduled to start in February 20 17 and be completed in February 2020.

Third, the focus of work

(1) The first stage of the renovation project

1. Planning and design work: formulate traffic impact assessment design and surrounding hydropower design, and complete transfer control scheme, planning and design conditions, transfer red line map and other related planning drawings.

Lead unit: Municipal Planning Bureau

Partners: xinluo district Municipal Government, City Investment Company, Xicheng Sub-district Office and Suxi Community Neighborhood Committee.

Responsible leader: Su Huimin

Time limit for completion: before March 15.

2. Formulation of expropriation and compensation scheme: Formulation of expropriation and compensation scheme, and clarification of expropriation and compensation standards and resettlement methods.

Responsible unit: xinluo district Collection Center.

Partners: City Investment Company, Xicheng Sub-district Office and Suxi Community Neighborhood Committee.

Responsible leader: Xue Xiaoping

Time limit for completion: before April 15.

3. Household survey and survey: conduct a comprehensive household survey to find out the number of households needing renovation and the area of households needing property rights exchange and monetary compensation and resettlement, and arrange survey companies to measure the land and houses involved in the relocation.

Lead unit: Xicheng Sub-district Office

Partners: xinluo district Collection Center, Silla Storage Sub-center, Suxi Community Neighborhood Committee.

Responsible leader: Jiang Xiaoying

Time limit for completion: before April 15.

4. Design of resettlement houses: define the number, apartment type, construction area and construction standards of resettlement houses.

Responsible unit: Suxi Community Neighborhood Committee

Partners: City Investment Company, Xicheng Sub-district Office, Silla Storage Sub-center, Silla Collection Center.

Responsible leader: Liu Hong (Secretary of Suxi Community Neighborhood Committee)

Time limit for completion: before April 15.

5. Land approval: the land involved in the red line of the first phase of the project ("total land") will be approved for transfer.

Lead unit: Silla Storage Sub-center

Partners: Municipal Bureau of Land and Resources, xinluo district Collection Center and Suxi Community Neighborhood Committee.

Responsible leader: Lin Yongjun

Time limit for completion: May 1 before.

6. Land Transfer: The land department draws up the transfer plan and announcement of Mao Di according to the relevant documents and materials issued by the housing and construction planning department, and organizes public bidding, auction and hanging according to law.

Responsible unit: Municipal Bureau of Land and Resources

Partners: Municipal Housing and Construction Bureau, Municipal Urban and Rural Planning Bureau, Silla Land Reserve Sub-center, Suxi Community Neighborhood Committee.

Responsible leader: Feng Tiangui

Time limit for completion: before June 1.

7. House expropriation: After the land transfer is completed, the land and house expropriation decision will be issued by the land department and the district government to expropriate the land and houses within the red line of the project.

Responsible unit: Xicheng Street

Partners: Municipal Bureau of Land and Resources, xinluo district Municipal Government, xinluo district Collection Center, Suxi Community Neighborhood Committee.

Responsible leader: Jiang Xiaoying

Time limit for completion: before September 1.

8. Construction work: Land bidders need to obtain a construction permit and start infrastructure construction before mid-September; After completion, each department shall organize acceptance according to relevant functions.

Responsible unit: land bidder

Partners: Municipal Housing and Construction Bureau, Urban and Rural Planning Bureau, xinluo district Housing and Construction Bureau, Xicheng Sub-district Office, Suxi Community Neighborhood Committee.

Responsible leader: the person in charge of the land bidder.

Time limit for completion: before September 1, 2065438.

9. Relocation: After the acceptance of resettlement housing construction is completed, the relocated households will be organized according to the announcement time, and the related expenses will be settled as required.

Responsible unit: Xicheng Street

Partners: xinluo district Collection Center and Suxi Community Neighborhood Committee.

Responsible leader: Jiang Xiaoying

Time limit for completion: before 65438+10 month 1.

(2) The second-phase reconstruction project focuses on the first-phase project, and the construction period is from 65438+February to 65438+February.

(3) The third phase of the renovation project is mainly the first phase, and the construction period is 20 17 to 2020 12.

Fourth, safeguard measures.

Financial security policy

The project is expected to cost 5 billion yuan, and it will be carried out by rolling development. The source of funds is mainly composed of the following parts:

1. The initial start-up fund was raised by Suxi Neighborhood Committee, and a project company was set up to participate in the renovation project of shanty towns (dilapidated houses) to raise 250 million yuan.

2. Increase investment attraction, and attract powerful honest and trustworthy real estate enterprises and social forces to participate in shantytown (dilapidated house) renovation projects.

3. The municipal and district finance and taxation departments shall strive for preferential policies such as policy funds, taxes and fees according to the Notice on Doing a Good Job in the Renovation of Urban shantytowns (Caizong [2015] No.57).

4. The state, province and city have expressly provided for tax reduction and exemption for shantytown renovation projects, and the relevant departments are responsible for it.

Land support policy

For the land within the red line of shantytown (dilapidated house) renovation project, the land department shall organize the transfer of gross land according to law, and the project land shall be given priority in the land supply plan. Resettlement fees, compensation fees, development and consolidation fees are included in the land cost of publicly sold land. According to documents such as Caizong [2015] No.57, Civil Affairs Document [20 10] 106, the land leasing income of the renovation project of the shantytown (dilapidated house) in Suxi community will be returned to the xinluo district Municipal Government, which will be used for the expenses such as demolition compensation, resettlement housing construction, low-rent housing construction and supporting infrastructure construction.

(3) Land and housing expropriation policy

For the expropriation of land and houses in shanty towns (dilapidated houses) renovation projects, the principle of combining monetary resettlement with physical resettlement shall be adhered to with reference to the expropriation policy for the renovation of the central city, and voluntary selection, multiple resettlement and monetary resettlement shall be carried out in accordance with the requirements of the overall urban planning. Encourage monetary resettlement, fully consider and properly solve the housing problem of low-income families with housing difficulties.

Infrastructure construction policy

Water supply, drainage, power supply and other facilities of municipal roads and supporting municipal roads such as Yanhe Road, Yanhe Green Land, Xibei Road (Xi 'an Road-Jiuyi South Road) within the red line of shantytown (dilapidated house) renovation project shall be the responsibility of the Municipal Housing and Construction Bureau, and shall be included in the municipal engineering projects of that year, giving priority to organization and implementation. The project owner is responsible for the construction of infrastructure such as water supply, drainage, power supply and gas supply in the project area; Educational facilities such as primary schools shall be built by the municipal and district education bureaus according to the division of labor in urban areas, and supporting facilities such as kindergartens and community service houses and community pension houses shall be built by bidders and handed over to all units in accordance with relevant regulations after completion; During the same period, the collection of infrastructure projects and the renovation of shanty towns were submitted for approval, and the resettlement was unified.

Verb (abbreviation of verb) organization and implementation

(A) to strengthen leadership, strengthen responsibility

In order to strengthen the leadership of the transformation of the shantytown (dilapidated house) in Suxi community, under the leadership of the leading group of the transformation of the shantytown (dilapidated house) in the central city of the municipal government, xinluo district established the transformation headquarters of the shantytown (dilapidated house) in Suxi community, with Zou, deputy head of the district government, Guo, minister of the United Front Work Department, as deputy commander, and the district government office, district development and reform, housing construction, finance, land and Xicheng Street as member units. The district government will incorporate the renovation of shanty towns (dilapidated houses) into the annual target assessment content to ensure that the renovation task is implemented.

(2) Close cooperation and overall promotion.

Relevant functional departments should, according to their respective responsibilities, establish a sense of overall situation and responsibility, carry out their duties, strengthen coordination and close cooperation, and earnestly implement all the work such as planning, funding, land supply, policy, supervision, compensation and resettlement to ensure that all policies and measures are implemented. Implement the "through train" approval service, simplify procedures, shorten the approval time limit, and speed up the transformation progress.

(3) Strengthen supervision and improve efficiency.

Strict implementation of project supervision, quality responsibility system and project bidding system, strict project quality management, and resolutely put an end to "tofu residue" projects. After the completion of the project, the construction unit shall submit it to the relevant departments for joint inspection and acceptance, and it can only be delivered after it is qualified. The discipline inspection, auditing and supervision office is responsible for the progress, project quality, raising and arranging the use of renovation funds of shanty towns (dilapidated houses). ...