Job Recruitment Website - Property management - How to write the completion acceptance opinion?

How to write the completion acceptance opinion?

Example of filling in the opinions on project completion acceptance

Project Name: Building 03, Banqiao Farmers Market

Employer: Nanjing Fengxiang Real Estate Development Co., Ltd.

Yuhuatai Construction and Installation Engineering Quality Supervision Station System Engineering Overview Project Name Banqiao Farmers' Market Building No.03 Project Address Banqiao

Structure type: Frame-shear wall floor, underground floor.

Ground space above the ground

Commencement Date Year Month Day Acceptance Date Year Month Day.

Acceptance and content

1, the information is complete, the five responsible subjects are here to participate in the completion acceptance, the owner presides over the acceptance, and the construction unit and supervision unit report the relevant information of the project commencement.

2. There are errors in the clear height of some rooms. (Adjustments have been reviewed)

3, male * * * pieces should be maintained in place as required.

4, local metope has empty drum.

5. The design, survey, engineering foundation, main body, heat preservation and energy saving meet the requirements, and the completion acceptance is agreed. The construction unit is responsible for rectifying the problems found in the acceptance.

The construction unit shall implement the basic construction procedures.

The construction unit shall implement the basic construction procedures in the process of project management, and adhere to the principle of first survey, then design and then construction.

The evaluation of survey results is consistent with the survey results in the survey report, and the technical data provided meet the engineering design requirements.

Evaluate whether the design meets the requirements of design documents (including changes), design specifications and mandatory standards.

Evaluation of supervision situation

1. The project supervision department conducted a comprehensive supervision of the project in strict accordance with the construction project supervision specifications, supervision contracts, supervision plans and supervision implementation rules.

2, foundation and foundation engineering construction quality comply with the design and specification requirements;

3. The construction quality of the main project meets the requirements of design and relevant specifications;

4. The construction quality of water, electricity, HVAC and other installation projects meets the design and specification requirements and meets the functional requirements.

Construction situation evaluation

1. The foundation, main body, decoration, heat preservation and energy saving of this project all meet the requirements of design and relevant specifications.

2. All materials in this project are subject to the system of certificate of approval and re-inspection, which meets the specified requirements.

3, engineering data management in accordance with the documents and relevant regulations.

4. The construction site management and construction procedures basically meet the requirements.

5, production safety management meets the requirements, no safety accidents.

Acceptance: The quality of the project meets the mandatory standards of engineering construction and the requirements of design documents, with strong quality assurance measures, sound quality management system and normal operation, so as to ensure that the quality of the project achieves good results, and the overall quality of the project meets the relevant national acceptance standards and is qualified.