What are the data of property takeover and handover?

When handling the property acceptance formalities, the construction unit shall hand over the following information to the property management enterprise.

(1) Property ownership information

Planning permit, investment permit, land use contract, construction permit, land red line map.

(2) Comprehensive completion acceptance data

1, completion general plan _ single building, structure, water, heating, electricity, gas, equipment and ancillary works.

Completion acceptance data such as industry completion drawing and underground pipe network project completion drawing _

2, the construction project completion acceptance certificate _

3, building fire acceptance certificate _

4. Comprehensive acceptance certificate of public supporting facilities _

5. Elevator Permit _

6, communication facilities certificate _

Three, mechanical and electrical equipment information

1, mechanical and electrical equipment factory certificate _

2, mechanical and electrical equipment operating instructions _ Chinese requirements _ _

3, mechanical and electrical equipment installation and debugging report _

4. Equipment warranty card and warranty agreement _

Four, property quality warranty documents and property use documents _

1, completion acceptance record form, comprehensive acceptance certificate of real estate development and construction project completion, residential quality guarantee, residential instruction manual, and construction project quality certificate _

2. Pipeline distribution as-built drawing _ Water, strong current, weak current, structure _ Measured area table _

Verb (abbreviation for verb) owner information

1. Name, location, area and telephone number of the owner who has purchased the house.

2. Payment situation or payment method of the owner who has purchased the house _

Legal basis:

Article 29 of the Property Management Regulations shall, when handling the property acceptance formalities, the construction unit shall hand over the following materials to the property service enterprise:

(a) the completion of the general plan, single building, structure, equipment completion drawings, supporting facilities, underground pipe network project completion drawings and other completion acceptance data;

(2) Technical data such as installation, use and maintenance of facilities and equipment;

(three) property quality warranty documents and property use documents;

(four) other information required for property management.

When the prophase realty service contract is terminated, the realty service enterprise shall hand over the above information to the owners' committee.