What conditions does BYD need to install charging piles?

Pacific Auto Network 1 First of all, there must be a fixed parking space, whether it is a property parking space or a rental parking space, it is just needed (the rental parking space requires a lease contract); 2. The property management unit will issue the Power of Attorney for Agreeing to Install Charging Equipment, and the general property management company will verify the site conditions and agree to install private charging piles, and sign and seal the Confirmation of Charging Conditions for Purchase of New Energy Passenger Cars, so as to apply for cable installation.

I. Electric Meter In response to the call, State Grid Shanghai Electric Power Company installed an independent electric meter for free. Independent meters don't use ladder electricity prices, so they don't go up or down. The difference between day and night is 0.33 1 yuan after night.

Application place: Application procedures for the business hall of the electric power company to which the residence belongs: application form (to be filled in on site by the business hall of the electric power company), parking space certificate (long-term parking space lease contract or certificate issued by the property, property parking space title certificate), certificate that the property or neighborhood committee agrees to install charging piles (the first two certificates can be written on a piece of paper and stamped by the property or neighborhood committee), car purchase contract (with frame number required) or car purchase invoice, real estate license (or rental contract).

After the above materials are submitted, the power company will come to the site for investigation, and if there is a suitable place to install independent meters, the construction can begin. It was the third day after the submission of the materials, and the construction came a week later. It is recommended to communicate with the property in advance, choose the most suitable location for installing the electric meter, and ask for the introduction of the line. Once you pass the property electricity meter, you can't install the electricity meter.

Personally, I suggest whether to apply for independence, because charging the car is likely to raise the electricity in the home to the third gear, which is very expensive and uneconomical. And if you take the route from the property, the property electricity bill is more expensive than the residents' electricity.

(Photo/Text/Photo: Pacific Auto Network Q&A called Beast)