Construction Process of Chinese Decoration in Harbin Xianju Decoration and Beijing Yuan Teng Decoration

(1) enter the site, tear down the wall and build the wall.

(2) Do a 24-hour closed water test on the bathroom and kitchen floor (the developer needs to complete this task).

(3) Trenching, hydropower transformation and acceptance.

(4) Underground trunking concealed hydropower renovation project, and waterproof project will be started when there is no leakage in closed water test.

(5) Stick a magnetic disk on the wall in the bathroom and kitchen.

(6) When carpentry comes into play, ceiling and plaster corner line shall be hung.

(7) Door covers and window covers.

Wooden cabinet frame.

(8) Synchronize all kinds of wooden doors, modeling doors and flat pressing.

(9) Brush dust-proof paint (clear oil) on the wooden panel.

(10) leveling and laying of marble countertops on windowsills.

(1 1) Sticking, scribing and hardcover of wood veneer.

(12) wall foundation treatment, grinding and leveling.

(13) For furniture, adhesive (edge protection) should be stuck at the joint of the door.

(14) wall oil ICI at least three times.

(15) Furniture paint comes into play, nail holes are repaired and painted.

(16) corner treatment, floor tiles, solid wood or composite wood floors, waterproof marble strips and skirting lines.

(17) Installation and debugging of lamps, sanitary wares, handles and door locks.

(18) Cleaning, floor tile repair and withdrawal.

(19) Internal preliminary acceptance of decoration company.

(20) The three parties agree to formally accept and deliver it to the owner.